Blog

  • Concrete Deflector for Top of Perimeter Walls

     We finished off the day’s work by building a deflector to control  the sloshy concrete being poured onto the top of the Perimeter Wall. The walls has hollow columns and they are all being filled up with the same ready mixed concrete being poured for our Floor Slab.

    Tool-to-aid-filling-the-columns

    Tool-to-aid-filling-the-columns

    The Concrete is going to be pumped using a big 30 metre boom arm coming from a massive diesel powered engine and the controller will move the wide diameter tube over the hollow columns by remote control, so we made this deflector to help him aim better!

    It is made of OSB boards and CLS timber, to make a 45 degree angle slope at the back and hooks to allow the tool to sit on top of the concrete  block walls without tipping off but allow it to move along. We also put two movable side hooks so one can lift these hooks when we come to a corner of the wall.

  • Day 2 of Assembly of Cells Framework in Floor Slab

     We completed the Assembly of the cellular framework in the rest of the Floor Slab, namely the Entertainment Room, Bedroom 2 and then Bedroom 3 and Utility Room.

    Floor-slab-Cells-Day-2

    Floor-slab-Cells-Day-2

    We then went around pinning into place all the fluffy expansion strips onto the framework where the 5 Energy Modules are, plus some extra pieces to aid possible concrete expansion when the whole Floor Slab warms up. That didn’t take so long and we finished up by putting concrete blocks on every “T” junction of the framework to weigh it down against the buoyancy when the heavy liquid concrete gets poured in. We calculated that the weight displaced by the OSB 100mm high strips will be approximately 3kg per every metre plus another 2kg displaced for the fluffy strips so in some lengths of the framework, it could add up to 15kg from junction to junction. We put plenty of concrete blocks weighing 20kg each on every junction so the total weight from all these blocks should counteract the uplift from the liquid concrete.

  • Floor Slab Cells Assembly – Day 1

     Today, we started assembling the wooden dividers which go across the whole Floor Slab from the sections we made last week. We have done the Great Room and the section that includes the Kitchen and Bedroom 1.

    Floor-slab-Cells-Day-1

    Floor-slab-Cells-Day-1

    It is working out reasonably OK, without too many difficulties, apart from sometimes the concrete foundation strip having a lumpy edge so we have to cut into the OSB strip a little bit to make it fit like a jigsaw. The fluffy expansion strips will be done later when we have completed all the wooden cells.

    Floor-slab-Cells-Joints

    Floor-slab-Cells-Joints

    We carried on with the front extension section and tomorrow, will continue across from the Hall and Entertainment Room, towards the back and Bedroom 2 and then over to Bedroom 3 and finally the Utility Room.

  • Floor Slab Dividers Cut and Ready

    While it was wet outside, we continued with making pieces of the cellular framework matrix that will divide up the Floor Slab into lots of rectangular regions so that no cracks (hopefully) will form when it cures and then gets heated up and cools down again and again and again!

    We put together a heap of readymade strips of various lengths (using the OSB 100mm wide pieces we produced the other day), plus another heap of strips ready to trimmed and fitted in place during the installation process.

    Slab-Matrix-parts

    Slab-Matrix-parts

    Monday, we will have to sweep the water off the plastic if it is still there, and then start assembling the dividing framework right across the slab, and then insert the fluffy expansion boards in and around the appropriate areas.

  • Day 4 of Setting in the DPM over Ground

     Today, while we waited  for the rain shower to clear up, we sliced up loads of strips of OSB left-over from our foundation shuttering, down to 100mm wide, and these will be used for forming the cells all over the Floor Slab to make sure that the soft fluffy expansion boards are held into place solidly, plus also make sure that no concrete is allowed to be more than 3metres in a single piece to avoid nasty cracks from appearing in jagged and random places when it cures but also in changes of temperatures over the seasons.

    We also sliced up more old shuttering boards into 50mm wide strips, after lunch, and these were used to mail up the flappy loose ends of the DPM up the walls.

    Edges-nailed-and-Conduits-sealed

    Edges-nailed-and-Conduits-sealed

    Then, we mixed a wheelbarrow load of dry concrete using 3 builder’s buckets of sharp sand ballast and left over cement and patted blobs down and around each and every item sticking up through the DPM plastic. There were 4 sewage pipes, 32 temperature probe conduits, 5 huddles of pipes, wide tubes and more conduits, some more water filling conduits as well and finally, the dozen electricity, water air and vacuum pipes and conduits to and from the Garage!!

    Sewage-pipe-sealed

    Sewage-pipe-sealed

    A-tank-connection-cluster-sealed

    A-tank-connection-cluster-sealed

    Utilities-sealed

    Utilities-sealed


    The next job is to use those 100mm wide strips and form the matrix of cells all over the ground. We have started the ball rolling for the “day” of the poring the slab to be Wednesday 5th October, but it still depends on our Building Inspector coming and approving our work and also for the concrete people to come back from Holidays to answer technical questions on whether we need some special additives to be included to make the concrete more suitable for coping with wide temperature fluctuations during the seasons as we have our Energy Modules being heated up during the Summer and then cooling down during the Autumn and Winter.

  • Day 3 – DPM All Down and Ready for Floor Slab .. Almost!

    Today, we finished off laying down the plastic sheeting over the ground. We completed the strip over the Entertainment Room and Bedroom 2 which was fairly difficult with the array of pipes etc. looming out of the ground! The last section was then levelled and scraped flat again (after the petrol compactor had whacked it down a week ago), and we put out the last strip of DPM across Bedroom 3 and the Utility Room. The corner in the Utility room was particularly complicated with dozen pipes and conduits sticking up including one tunnel as well!
    We also went around with our 100mm wide silver duct tape and sealed all the overlapping joints on all the DPM plastic sheets we have put down.

    Day-3-DPM placement Sump point

    Day-3-DPM placement Sump point

    Day-3-DPM-placement-Utility Conduits

    Day-3-DPM-placement-Utility Conduits

    Day-3-DPM-placement-finished

    Day-3-DPM-placement-finished



    Tomorrow, we will mix some light grade concrete and put a blob down at every single intrusion through the plastic where pipes and conduits had to come up so that any slits and cuts in the plastic are covered up nice and solid to avoid the very liquid free flowing concrete from sliding under the plastic and ruining the performance of the Floor Slab. No Thank You!

  • Day 2 of Laying DPM down for Floor Slab

     We carried on with the task of laying the Damp Proof Membrane (DPM) plastic down on the ground inside our perimeter wall of our house. We now have completed and reached up to the edge of the Entertainment room and half the Bedroom 2 at the back. We had to put down more sand to flash off these sections and scraped it level, which took all morning to do.

    Day-2-Laying-DPM-1

    Day-2-Laying-DPM-1

    Day-2-Laying-DPM-2

    Day-2-Laying-DPM-2


    We had no rain today which was nice, but it was rather windy and had our plastic sheets flapping in the wind a bit so we put down lots of concrete blocks on the edges to hold everything in place! tomorrow, we resume and do the last 2 strips, but after we go and buy another roll, our 4th from Jewson’s, and we will only need about 5 metres off this roll to finish the job – Oh Well!

  • Continuing with DPM and Final Levelling of Ground

     With an interrupted morning, we carried on with the laying out of the DPM plastic sheeting across the whole ground area of the building. We covered up the Great Room and most of the second strip of the Kitchen and Bedroom 1. We used another 2½ wheelbarrow load of sand to fill in the hollows which means getting a more consistent thickness for the Floor Slab.

    First-two-strips-of-DPM

    First-two-strips-of-DPM

    We also nailed up the necessary fluffy expansion boards (straight into the concrete blocks, we are using hardened T nails with one of our air nail-gun tools!) around the finished section to hold the plastic in place and help it not to get blown around in the wind.

    Expansion-Strip-nailed-to-walls

    Expansion-Strip-nailed-to-walls

    It rained for 15 minutes during the afternoon but it wasn’t so bad as to stop work. Tomorrow, we continue with this job, laying the sheet out, finding where the pipes needs to come through and smoothing out the surface, all ready for the concrete Floor Slab – not long now!

  • Checking Items off List Before the Floor Slab is Poured

     Today, we carried on with the preparation jobs to be done before the concrete Floor Slab is poured. We made a list of all the tasks that has to be performed, we have completed the following items.

    Sumps

    We wanted to make it easier for us to get rid of rainwater that will fall while we haven’t got the roof on the house to make it weatherproof. So we made two sump points in the middle of the floor slab, about 100mm deep so that a water pump can be dropped in and suck out the whole layer of rainwater quickly and easily. To make the concrete “dents”, we will put two builder’s buckers full of sand and stick on a large plastic foot which will sit upon the DPM in the dents. The concrete will pour around the and through the plastic foot, under the bucket and the weight of the bucket will stop the concrete lifting it up and hopefully create a hollow area once the concrete is set.

    Sump-points-excavated

    Sump-points-excavated

    Confirmation and Adjustment of Sewage Pipes

    Then, we double checked the position of all our Sewage Pipes coming up from the ground, in various location’s around the house. The Utility room is ok as well as the one over between Ensuite 1 and Ensuite 2. But one’s located in Ensuite 3 and the bathroom was slightly off so we wiggled it around so it was in a better position. We did the same with the final sewage pipe sticking up in the Cloakroom, adjusting that one too. All is now in the right place, in relation to our new frame of reference I.e. The Perimeter Wall.

    Energy Modules

    This will be the last time we have any options to deal with  any problems with our underground water tanks that makes up the 5 Energy Modules situated underneath our house. We checked the water levels (looking down the inspection tubes) in all 5 and they are still nice and full! The rubber membrane skin are still holding and we haven’t made any holes during the installation (and repair) jobs on each module! Phew and Thank Goodness!

     Fluffy Expansion Boards

    Next we sliced up all our 7 sheets of the fluffy low density fibre boards into a pile of 100mm wide strips (all 84 of them), ready for forming “cells” (in the concrete floor slab) around each Energy Module’s location. Also, these squash-able and water proof strips (the fibres have been treated with bitumen) will be nailed at the bottom of the Perimeter Block Wall, right around the circuit, to allow the expansion of the Floor Slab against the wall too.

    Exspansion-filler-board-cut-up

    Exspansion-filler-board-cut-up

    Exspansion strips against wall

    Exspansion strips against wall


    DPM

    Finally, we started the process of laying down the DPM (Damp Proof Membrane) plastic sheeting. We started at the Great Room, by putting down more sand and scraped across to fill in any last hollows and holes before the plastic goes down. We managed to finish levelling the Great Room but not the laying the DPM before the day ended!!

    So on Monday, we resume with that task, laying the plastic sheet out and making holes to allow all the various pipes and conduits to stick through. We will have to put an extra “patch” at all these intrusions and stick down all the edges to make sure that the special “free-flowing” concrete doesn’t get under the DPM and cause a fault in the Floor Slab structure and its strength.

  • Organised The Utility Conduits and Pipes

     Today, we tackled the task of digging and loosening all the various pipes and conduits that run from the Garage to the House, and get them all laid out to come up in the Utility Room in a neat pattern.

    Utilities-Tidy-Up-Before-A-long-time

    Utilities-Tidy-Up-Before-A-long-time

    There are conduits for the Mains Electricity, data / telephone, for the vacuum system and spare empty one. Then, there are the water pipes for things like the thermal solar heated water (there and back again), 6 pipes that run under the garage for pumping heat out of the ground, supply from underground rainwater tank located under the Garage, cold water feed from house to Garage and finally, the mains water supply from the Loke. Oh yes, I nearly forgot the compressed air supply from the Garage!!

    It is a pretty network of criss-crossing pipes and conduits down in the hole

    Utilities-Tidy-Up-All-dug-up

    Utilities-Tidy-Up-All-dug-up

    We used the edge of the foundation to screw an steel strap and used that to cable tie each pipe and conduit into a neat line.

    Utilities-Tidy-Up-Ready-for-reburial

    Utilities-Tidy-Up-Ready-for-reburial

    We also used some wooden strips to create a framework higher up as well, to help to keep everything straighter up. Then, we stamped and thumped the soil back into the hole and make sure it was well and truly compacted hard down.

    Utilities-Tidy-Up-Finished

    Utilities-Tidy-Up-Finished

    It is rather neat and tidy now, at long last, since this bunch of these pipes has been sticking out of the ground for 6 years!! Phew!