Category: Groundworks

  • Day 2 of Installing the Pipework for Rainwater off Roof

     This afternoon, we continued with installing of the pipework running around the perimeter of the house, connecting to the downpipes from the roof and the guttering.

    We went along the front, past the Great Room, the Kitchen, The Hall and Entertainment Room, and around the Utility Room, past the back door and alongside Bedroom 3. That is 3 more downpipes connected up to the “ring” circuit, so only 1 more to do tomorrow, the one next to the back of Bedroom 2, giving a total of 8 downpipes. The two “ends” of the ring circuit will finally be meeting together again and  joining to the Filtration Module at the end of the Swimming Lane.

  • Installing Pipework for Rainwater off the Roof and Guttering

     Today, while we are waiting for the arrival of the ready mixed concrete on Monday, we carried on with the preparation and installation of the pipework running around the perimeter of the building, with 8 separate connections to the roof and the guttering (when that is built!).

    Pipes-for-rainwater-ring

    Pipes-for-rainwater-ring

    The pipework is standard 110 mm diameter sewage underground pipes, with down-pipes from the guttering in all the internal corners of the building (except  the one beside the back door near the garage, which is along a straight section)

    Rainwater-pipe-along-back-of-building

    Rainwater-pipe-along-back-of-building

    Rainwater-downpipe-and-connection-to-the-ring

    Rainwater-downpipe-and-connection-to-the-ring


    We managed to do behind bedroom 2, bedroom 1, and around the Great Room (including the conservatory) doing 4 down-pipe sections. The depth of the main “ring” around the house is set to 350 mm below ground level, running 50 mm above the foundation strips, tight next to the Perimeter Wall.

    On Saturday, we will hopefully finish off the front of the house and down the side back toward the Swimming Lane and the Filtration Module where the rainwater pipes will terminate.

  • Laser Level Check and Final Adjustments of Cellular Framework of Floor Slab

     This afternoon, we went around checking the height of all our cellular framework that divides up the Floor Slab. It is rather satisfying that we didn’t get more than 10mm up or down and mostly within 5mm of required height all over the Floor Slab’s framework.

    We made some adjustment to one that were a little low (by propping up the framework on flat pieces of hardboard) and gently thumped down the highest points so we ended up with nothing more than 5mm out anywhere.

    Checking Cell Heights

    Checking Cell Heights

    As the picture shows, we used the laser level equipment to analyse the absolute height, by putting the sighting pole on top of all the concrete blocks lying on all the “T” junction points.

    We also wrapped a double layer of plastic around the buckets that are in the two sump areas so that we will have a fighting chance to get these buckets out of the concrete after it has set!!

  • Building Inspector Approves Preparation for Floor Slab!

    Our Building Inspector came along at lunch time and spent a few minutes looking over our DPM plastic, sticking up pipes and how it was all stuck together.

    Building-Inspector-calls

    Building-Inspector-calls

    He said it was very thoroughly done and he approves!! Yippee!

    P.S. He forgot to tell us he had visited and approved, we were at lunch!

  • Concrete Deflector for Top of Perimeter Walls

     We finished off the day’s work by building a deflector to control  the sloshy concrete being poured onto the top of the Perimeter Wall. The walls has hollow columns and they are all being filled up with the same ready mixed concrete being poured for our Floor Slab.

    Tool-to-aid-filling-the-columns

    Tool-to-aid-filling-the-columns

    The Concrete is going to be pumped using a big 30 metre boom arm coming from a massive diesel powered engine and the controller will move the wide diameter tube over the hollow columns by remote control, so we made this deflector to help him aim better!

    It is made of OSB boards and CLS timber, to make a 45 degree angle slope at the back and hooks to allow the tool to sit on top of the concrete  block walls without tipping off but allow it to move along. We also put two movable side hooks so one can lift these hooks when we come to a corner of the wall.

  • Day 2 of Assembly of Cells Framework in Floor Slab

     We completed the Assembly of the cellular framework in the rest of the Floor Slab, namely the Entertainment Room, Bedroom 2 and then Bedroom 3 and Utility Room.

    Floor-slab-Cells-Day-2

    Floor-slab-Cells-Day-2

    We then went around pinning into place all the fluffy expansion strips onto the framework where the 5 Energy Modules are, plus some extra pieces to aid possible concrete expansion when the whole Floor Slab warms up. That didn’t take so long and we finished up by putting concrete blocks on every “T” junction of the framework to weigh it down against the buoyancy when the heavy liquid concrete gets poured in. We calculated that the weight displaced by the OSB 100mm high strips will be approximately 3kg per every metre plus another 2kg displaced for the fluffy strips so in some lengths of the framework, it could add up to 15kg from junction to junction. We put plenty of concrete blocks weighing 20kg each on every junction so the total weight from all these blocks should counteract the uplift from the liquid concrete.

  • Floor Slab Cells Assembly – Day 1

     Today, we started assembling the wooden dividers which go across the whole Floor Slab from the sections we made last week. We have done the Great Room and the section that includes the Kitchen and Bedroom 1.

    Floor-slab-Cells-Day-1

    Floor-slab-Cells-Day-1

    It is working out reasonably OK, without too many difficulties, apart from sometimes the concrete foundation strip having a lumpy edge so we have to cut into the OSB strip a little bit to make it fit like a jigsaw. The fluffy expansion strips will be done later when we have completed all the wooden cells.

    Floor-slab-Cells-Joints

    Floor-slab-Cells-Joints

    We carried on with the front extension section and tomorrow, will continue across from the Hall and Entertainment Room, towards the back and Bedroom 2 and then over to Bedroom 3 and finally the Utility Room.

  • Floor Slab Dividers Cut and Ready

    While it was wet outside, we continued with making pieces of the cellular framework matrix that will divide up the Floor Slab into lots of rectangular regions so that no cracks (hopefully) will form when it cures and then gets heated up and cools down again and again and again!

    We put together a heap of readymade strips of various lengths (using the OSB 100mm wide pieces we produced the other day), plus another heap of strips ready to trimmed and fitted in place during the installation process.

    Slab-Matrix-parts

    Slab-Matrix-parts

    Monday, we will have to sweep the water off the plastic if it is still there, and then start assembling the dividing framework right across the slab, and then insert the fluffy expansion boards in and around the appropriate areas.

  • Day 4 of Setting in the DPM over Ground

     Today, while we waited  for the rain shower to clear up, we sliced up loads of strips of OSB left-over from our foundation shuttering, down to 100mm wide, and these will be used for forming the cells all over the Floor Slab to make sure that the soft fluffy expansion boards are held into place solidly, plus also make sure that no concrete is allowed to be more than 3metres in a single piece to avoid nasty cracks from appearing in jagged and random places when it cures but also in changes of temperatures over the seasons.

    We also sliced up more old shuttering boards into 50mm wide strips, after lunch, and these were used to mail up the flappy loose ends of the DPM up the walls.

    Edges-nailed-and-Conduits-sealed

    Edges-nailed-and-Conduits-sealed

    Then, we mixed a wheelbarrow load of dry concrete using 3 builder’s buckets of sharp sand ballast and left over cement and patted blobs down and around each and every item sticking up through the DPM plastic. There were 4 sewage pipes, 32 temperature probe conduits, 5 huddles of pipes, wide tubes and more conduits, some more water filling conduits as well and finally, the dozen electricity, water air and vacuum pipes and conduits to and from the Garage!!

    Sewage-pipe-sealed

    Sewage-pipe-sealed

    A-tank-connection-cluster-sealed

    A-tank-connection-cluster-sealed

    Utilities-sealed

    Utilities-sealed


    The next job is to use those 100mm wide strips and form the matrix of cells all over the ground. We have started the ball rolling for the “day” of the poring the slab to be Wednesday 5th October, but it still depends on our Building Inspector coming and approving our work and also for the concrete people to come back from Holidays to answer technical questions on whether we need some special additives to be included to make the concrete more suitable for coping with wide temperature fluctuations during the seasons as we have our Energy Modules being heated up during the Summer and then cooling down during the Autumn and Winter.

  • Day 3 – DPM All Down and Ready for Floor Slab .. Almost!

    Today, we finished off laying down the plastic sheeting over the ground. We completed the strip over the Entertainment Room and Bedroom 2 which was fairly difficult with the array of pipes etc. looming out of the ground! The last section was then levelled and scraped flat again (after the petrol compactor had whacked it down a week ago), and we put out the last strip of DPM across Bedroom 3 and the Utility Room. The corner in the Utility room was particularly complicated with dozen pipes and conduits sticking up including one tunnel as well!
    We also went around with our 100mm wide silver duct tape and sealed all the overlapping joints on all the DPM plastic sheets we have put down.

    Day-3-DPM placement Sump point

    Day-3-DPM placement Sump point

    Day-3-DPM-placement-Utility Conduits

    Day-3-DPM-placement-Utility Conduits

    Day-3-DPM-placement-finished

    Day-3-DPM-placement-finished



    Tomorrow, we will mix some light grade concrete and put a blob down at every single intrusion through the plastic where pipes and conduits had to come up so that any slits and cuts in the plastic are covered up nice and solid to avoid the very liquid free flowing concrete from sliding under the plastic and ruining the performance of the Floor Slab. No Thank You!