Category: Cladding

All Cladding materials and work on walls

  • Exterior Larch Cladding and Oak Frames Cleaned and Oiled

    In the glorious sunshine, while it was far too hot indoors, we decided to start one of our Summer job now. We needed to do some serious maintenance to our exterior cladding of our house, giving it a thorough clean, and give it a good treatment of oil, and perhaps a touch of colour dye as well.
    So, the first part of this task, is to clean the larch cladding and the oak guttering and the oak surrounds at each window.
    We got our pressure washer out, pulled the hose off the reel, all 50 metres of it and only just got to the far end of the house! And started washing down the walls, using the rotating nozzle that seems to do the trick of shifting the dust and dirt out of the grain of the wood. Some of the larch has fungi growing on them as well, especially in those locations that don’t have a lot of sunshine on them, and gets wet from the rain. We are planning to apply some anti-fungi treatment, mixed in with the timber oil solution as well and give the wood some protection against further fungi growth.
    But, right now, we slowly worked our way around the whole house, doing each section by section. We even blasted the gutters as well, they are starting to turn silver and the pressure washer seems to give them a new leaf of life and colour again.

    P1 Wall before cleaning

    P1 Wall before cleaning

    Clean a Stripe

    Clean a Stripe



    As you can see from the photo, the walls were definitely grimy, and also, much of the original “burnt” colouring has disappeared as well. It is amazing that the Sun was able to bleach even the burnt colouring. O Boy!

    So we now have a fresh looking house again!

    Walls all Cleaned up (1)

    Walls all Cleaned up (1)

    Walls all Cleaned up (2)

    Walls all Cleaned up (2)

    Walls all Cleaned up (3)

    Walls all Cleaned up (3)


    We have decided that the Larch Cladding had come out much better than we thought so we are not going to add any colouring dyes to the timber oil and just leave it natural.

    We pulled out a spray machine that we required from somewhere in the past but discovered that the old Lead Acid battery was dead. After replacing that with a 12V mains supply adapter, we got lovely pumping noises .. but no liquid coming out the nozzle! Upon opening up the little pump, we discovered that the rubber membranes had stiffen up and were no longer flexible anymore. So, we ordered a replacement 12V pump, trying to match the specifications, like size and shape and wattage, as much as possible. Our new one is only slightly more powerful but otherwise the same. We swopped the two pumps around and we now have a lovely sprayer. We poured in our timber oil we still had from our original application and poured in about 25litres into the tank. We started on the O section, at the back of the house, and worked our way clockwise around the house. We even sprayed all the Oak framework around each window, plus also the Oak covers on the corners of the building.

    Cladding all re oiled (1)

    Cladding all re oiled (1)

    Cladding all re oiled (4)

    Cladding all re oiled (4)

    Cladding all re oiled (6)

    Cladding all re oiled (6)

    Cladding all re oiled (8)

    Cladding all re oiled (8)


    We then had to wash all of our twelve windows, to remove the oil that had splattered onto the glass. We used a handy little vacuum wiper that sucks off the soapy water after the glass has been scrubbed.

    And, because we had washed the windows, we went around and painting more oil onto the sills. Some of them needed three coats of the oil before it stopped soaking in.

    Finally, we spent an afternoon, rubbing down the Oak timber, to reduce the “fur” texture that had lifted off the surface after we had blasted the timber with our pressure washer. We used a soft sanding pads to knock off most of the white furry surface, also rubbing the sills as well. Some of the windows needed a bit more energetic scrubbing using courser sandpaper.

  • The Last 8 Oak Covers Created and Installed

    Following the initial progress we made on sorting out the Oak timber last Saturday, we resumed to produce the Octagon Covers for our seven inside corners to hide the plastic downpipes plus the special cover to hide the downpipe just right of the Side Door.
    All the steps and methods were essentially the same as last week’s work on the nine outer corners, apart from the edges didn’t need the 45degree slopes.

    The Last 8 Oak Covers Created and Installed

    Internal-Corner-pieces-ready-to-install


    The installation process, on the other hand, was different this time, because every corner is slightly different and we had to custom fit each one. The procedure was to put up the octagon cover into place and then measure the gap between the surface of the oak to the plywood support strip inside. Every corner is slightly different so we had to slice off a variable amount each time using our battery circular saw, following a drawn line along the long edge.
    The Last 8 Oak Covers Created and Installed

    Cutom-fitting-a-corner


    Then we marked off a regular set of screw holes approximately every 200mm. Four of these holes were the real ones with full clearance, and the other ones just had pilot holes to grip the screw in place as there is nothing behind the oak.
    None of the eight pieces had their height adjusted so we got that one correct!
    The Last 8 Oak Covers Created and Installed

    The-MN-Corner-before-covering

    The Last 8 Oak Covers Created and Installed

    The-MN-Corner-after-covering



    So that concludes the task of covering all the corners with the ends of the Larch cladding and the pipework, all 17 of them! Phew!
    The Last 8 Oak Covers Created and Installed

    Some-completed-cladding

  • Oak Covers Created for Nine Outside Corners

    The last 9 days or so have been spent on processing a pile of Oak timber pieces and generating nine finished covers to hide the cut ends of the Larch cladding.
    The rough oak planks were 3metres long, 29mm thick and a range of various widths from 100mm to 180mm. We wanted to end up with 27 planks, split into 2 sets of 90mm and 110mm widths and all at least 2800mm long (the longest length going up a corner).
    The first job was to ‘straighten’ each planks by slicing one edge using our track mains powered circular saw. This removed any wobbles and bends. Then after that, using the main table bench circular saw this time, and using the 2.4 metre fence to guide and control the width, we sliced these 27 planks into the 2 sets we needed.
    So the next task was to set up the planer with its two input and output support tables, rigged up to our high air flow rate vacuum system to draw away the shavings and then proceeded to smooth off one side of all the planks. We do multi passes on each planks until we judge that there is enough of the surface planed to ensure that it will work reliably during the thicknesser stage. It is a compromise because we may find ‘more’ room to plane the other side and achieve at least one completely smooth finish. Any rough spots can be left hidden on the inner side of these Corner Covers.
    As mentioned already, the second stage of the planing process was the thicknesser, and we worked our way through all the planks, flipping some over to remove more of the rough spots and eventually, we finished up with 18 smooth 110mm wide pieces and 9 90mm wide pieces.
    Now after tidying away that machine, we brought out the table bench saw again, this time with the saw blade set to an angle of 45degrees and sliced the 18 planks (the 110mm wide set) to end up with one edge with a slope and a flat face of 90mm wide. This now matches up with the other set of 90mm planks.

    Parts-for-the-outside-corner-covers-Planed-and-Sawn

    Parts-for-the-outside-corner-covers-Planed-and-Sawn


    The next piece of machinery to come into play, is our router with the special 22.5° tongue and groove cutter bits, to create the joints to allow us to lock together the three planks (2 of the 110mm wide ones, fitted on to the 90mm middle piece) and form the half the octagon Corner Covers. We sorted out all the planks, checking for maximum length of finished surfaces and arranged 9 sets of three planks. We then knew which edge to cut and in the proper order. The last quick router task was to trim a small quarter rounded edge along the sharp 45degree slope to avoid future splinters and cracking.
    Parts-for-the-outside-corner-covers-Joints-made

    Parts-for-the-outside-corner-covers-Joints-made


    The final sawing job is to slice little angled off both ends of each plank, the bottom ends (nearest the slates) had a 30degree angle and the top ends had a 45degree slope. But the precise length of each set of the three planks had to be measured from the real world (we walked around our house and measured all nine corners and wrote down the numbers.
    Oak Covers Created for Nine Outside Corners

    Sample-Outside-coner-section


    At last, we could, and did, stick together each set (using Polyurethane glue) for the joint and we used lots of duct tape to pull together the tongue and groove joints and held the shape tight while the glue cured.
    Oak Covers Created for Nine Outside Corners

    Piles-of-glued-up-Corners-1

    Oak Covers Created for Nine Outside Corners

    Piles-of-glued-up-Corners-2



    Then it was time to install them! Hurray!
    We started with the six easiest corners and thought we would tackle the nearest corner (the ‘OP’ one) to the Great Room which is where we are working these days, but only to discover that the wall along the ‘O’ section does a funny little wiggle at the bottom. The batten that holds up the Larch cladding had been bent outwards by the concrete blocks, without us spotting it. This meant that the Oak Cover has a large increasing gap between the Larch planks and the Cover piece (the Oak being nice and straight of course!). After skipping that corner to do the opposite corner, the ‘NO’ corner, which turned out to be much closer and even, we decided that we would make adjustments to the Larch cladding planks, rather than living with the gaping ‘hole’. So we undid the screws and pushed in ever increasing thicknesses of plastic spacers behind each Larch plank and then retighten the screws back down again. We use a long spirit level as our straight edge to achieve the proper and correct adjustment.
    Oak Covers Created for Nine Outside Corners

    Straigtening-the-OP-Corner-1

    Oak Covers Created for Nine Outside Corners

    Straigtening-the-OP-Corner-2



    With this done, we now can go and make lots of wooden spacers to go behind the Oak Covers to allow plenty of air to circulate and keep everything dry and clean, to avoid any potential wet rot etc.
    We decided to buy round wooden poles, and found a set of Eucalyptus broom handles on the web, an inch in diameter and about 1.5metres long. We got our drill press machine out and rigged up a little holder to hold short lengths of the round rods, and drilled a centralised clearance hole down the middle. We then slice the rod up into lots of 5mm thick discs, thus made our spacers with a predrilled hole, ready for going between the Oak and the Larch and screwed down.
    Now the next task was to find an old waste length of oak strip and mark off distances of 200mm up the length and guide us to try and keep an regular spacing for the fixing screws. But before that, we snapped together a metal placement template for the drilling of the clearance holes in the Oak, positioning the template on the 45degree slope and get consisted alignment up all the Corner Covers.
    So the procedure for putting up these Covers, was to drill the first clearance holes at the bottom, 75mm off and then screw it on to the corner. Then using the marked guide stick, drilled clearance holes at approximately every 200mm, only making adjustments to ensure that the fixing screw sinks into solid portions of the Larch timber. Then taking the Cover piece down again, taking it indoors and glue on our little wooden discs using 5 minute PU glue. While that was curing, we took out the next corner to repeat the process of doing the clearance holes. After that, the Oak Cover piece would go back outside to lay on a set of trestle tables and proceeded to get a thorough coating of the timber oil treatment, on both sides but most especially the hidden interior side. While that was soaking in and dripping excess off, we got on with the third corner in doing the clearance holes. Eventually, the oil had soaked in enough for us to handle it and actually install the first corner piece which we did!!
    Oak Covers Created for Nine Outside Corners

    Corner-with-spacers-attached

    Oak Covers Created for Nine Outside Corners

    The-Staight-OP-Corner



    As you can imagine, this logical collection of programmed steps was repeated several times over until we got all nine corners done.
    Oak Covers Created for Nine Outside Corners

    The-AP-Corner-cover


    The last three corners, two on the Front Porch and one on the Side Porch, had a little adjustments made to the tops of their covers, to allow us to go around the main support beam sticking out the house, and for the Side Porch, an additional adjustment to clear the diagonal metal bracing arm too.
    Oak Covers Created for Nine Outside Corners

    Shaun-tightening-the-last-screw

    Oak Covers Created for Nine Outside Corners

    The-EH-Corner



    This is the complete process of taking rough sawn oak timber and ended up with nine finished Oak Covers, all in about 9 days. Not Bad!
    Now we repeat the whole process over again, but this time, for the Inside corners, to cover up the plastic downpipes plus our odd one in the middle of the ‘H’ wall. But that is another story and next week’s work!! Actually, We have already started the process and we have got out all the 2.6metres oak timber pieces and sliced them up into the required 26 planks, and even got most of the planing done too! More in Next week’s blog report!

  • All Walls Done At Last! L, M and N Sections Completes the Cladding Job!

    We Have Done It! The whole house is now fully clad with our Larch timber!
    It took only a day and a half to finish off the last bit, the “L”, “M” and “N” sections, our alcove, around the back of the house. We could cut most of the wood in one go then it was quick too put up.

    All Walls Done At Last! L, M and N Sections Completes the Cladding Job!

    Most-of-the-wood-for-the-Alcove


    We used a higher scorch level for these planks to see what it is like and also to capture more heat in the cooler seasons. If we don’t like it, we can scrub the surfaces with a wire brush to tone down the darker colours, and of course, reapply the fire retardant treatment again.
    All Walls Done At Last! L, M and N Sections Completes the Cladding Job!

    The-finished-LMN-Alcove


    The final job was to unscrew the top 6 rows of timber on the very first section we did a month ago, and we painted the exposed “pink” battens black. We realised that one could see up between the planks and see the lighter colour and hence we had painted all the other battens around the house, except for the “P1” section next to our patio area and Conservatory.
    Then, we moved all the excess timber to our long term storage area, the swimming lane, sorted into width. Both sets of treated Larch planks are now all together, ready for the time when we will clad the garage.
    All Walls Done At Last! L, M and N Sections Completes the Cladding Job!

    The-left-over-Fire-Treated-larch-1

    All Walls Done At Last! L, M and N Sections Completes the Cladding Job!

    The-left-over-Fire-Treated-larch-2

    All Walls Done At Last! L, M and N Sections Completes the Cladding Job!

    All-the-spare-larch-stored



    The rest of the week was spent tidying up inside the house and upgrading the electric feed from the garage to the house to provide a more heavy duty service (we only had an 13A extension lead before). We will want to use more powerful machines now that we are going to be working inside the building.

  • Big Complex H wall Now Complete Plus I, J, K and O all Done Too!

    By Monday lunch time, we had finished off the last triangular piece of the wall above the Utility’s window and door, the gable wall of the Porch.

    Big Complex H wall Now Complete Plus I, J, K and O all Done Too!

    H-Gable-is-finished


    We then moved all the platforms and equipment around to the back of the house to start working our way along seven remaining sections to be clad in the fire-treated Larch timber.
    By Tuesday, we had finished the “I” wall section but we had to divert our effort to replace the caterpillar tracks on our mini-digger, see Replaced Caterpillar Tracks on mini Digger
    Big Complex H wall Now Complete Plus I, J, K and O all Done Too!

    I-Compete


    We got back to work, Wednesday afternoon without any further interruptions (including missing all the rain on Saturday!) and zoomed along to get the “J”, “K” and “O” walls all finished and everything. We even managed to get the first row on the three walls that makes up our neat little alcove, the “L”, “M” and “N” sections. We also put up the marks on each battens that tells us where to put each larch timber piece going up the wall.
    Big Complex H wall Now Complete Plus I, J, K and O all Done Too!

    J-finished

    Big Complex H wall Now Complete Plus I, J, K and O all Done Too!

    K-Finished

    Big Complex H wall Now Complete Plus I, J, K and O all Done Too!

    O-fully-clad

    Big Complex H wall Now Complete Plus I, J, K and O all Done Too!

    Base-row-on-LM-N



    Hopefully, next week on Monday and Wednesday, we will get the Alcove all finished and that will be it!

  • Cladding Second Stage – The Fire Treated Larch Timber for the Back of the House

    We started the new week by moving the remaining oiled standard planks to storage in the swimming lane.

    Cladding Second Stage - The Fire Treated Larch Timber for the Back of the House

    Oiled-Untreated-planks-stored-in-Swimming-lane


    Then we started processing our second set of Larch timber that had been dunked in the Fire Resistant treatment a couple of weeks ago. The first job was to remove all the iron stains that we accidentally put on during the dunking process. We had applied the Oxalic acid to each and every stain and then later washed them with fresh clean water to remove as much of the acid solution (which had turned the surface yellow – this fades slowly away).
    Cladding Second Stage - The Fire Treated Larch Timber for the Back of the House

    Planks-after-Acid-treatment

    Cladding Second Stage - The Fire Treated Larch Timber for the Back of the House

    Then-cleans-and-sorted-by-Size-and-Scorch



    But also we decided that we would drain and dismantle our dunking tank assembly. We don’t need it anymore, so we recovered about 35litres of the oil, the second bottle is more “coloured” but the first one is looking quite clean.
    Cladding Second Stage - The Fire Treated Larch Timber for the Back of the House

    Deconstructed-dunking-tank


    Then we got on with the task of mounting planks on to the walls, which we started where we left off, on the “H” wall (the right side of the house going alongside the Garage).
    But we also suddenly remembered that we needed to paint the top of the battens black so anyone looking up the wall, and up the gap between planks, cannot see the “pink” colour, just darkness.
    Cladding Second Stage - The Fire Treated Larch Timber for the Back of the House

    We-started-on-the-H-wall

    Cladding Second Stage - The Fire Treated Larch Timber for the Back of the House

    then-remembered-we-needed-to-paint-the-front-of-the-battenms-black



    The “H” section of the house includes the Side Door Porch, which is being held up with reinforcing diagonal arms, attached about six feet up the wall. This means that some of the planks had to have notches cut out to fit around these aluminium arms.
    We got the second half of the “H” wall all finished, right up to the rafters, and we got as far as the first couple of rows going up inside the Porch’s gable wall section over the Utility Room window and the Side door. It was quite fiddly working around the projecting wooden beams that holds the Porch roof up, including the more awkward process of moving around on the platform and avoiding the metal arms too. We had to keep coming down to cut our planks and slice the lap joints etc. so it was a bit slower in putting up the pieces.
    Cladding Second Stage - The Fire Treated Larch Timber for the Back of the House

    then-we-got-to-the-top-of-the-windows-on-Thursday

    Cladding Second Stage - The Fire Treated Larch Timber for the Back of the House

    and-most-of-the-rest-done-by-the-end-of-the-week



    Next week, we should get the last remaining triangle section finished and then we can move around to work along the back of the house. We might even get that done by the end of the week 😉

  • Front Porch Wall is Clad plus also Walls D and E too

    Upon the resumption of the new week, we got on with the task of cladding the Front Porch wall, the “C” section that has the main house door and Entertainment Room’s window. It is over 7 metres long and disappears up to the apex of the porch roof, some 5 metres high.
    By the end of Monday, we got all the lower section of the wall covered in our Larch cladding timber, with different randomised planks on each side of the door and the window.

    Then over the next three days, using our existing high level platforms (we had to raise a shorter one by extending it’s legs by temporarily clamping on a set of the old tall legs), we slowly covered the rest of the wall. It was cramped at times, especially near the top, working around all the piles of timber, ladders and tools, it was a tricky and slow work.

    Front Porch Wall is Clad plus also Walls D and E too

    C-Wall-Platforms-to-work-on-gable-wall

    Front Porch Wall is Clad plus also Walls D and E too

    C-Wall-Day-2

    Front Porch Wall is Clad plus also Walls D and E too

    C-Wall-Day-3

    Front Porch Wall is Clad plus also Walls D and E too

    C-wall-Day-4



    These cladding planks are the original finish (no burnt surfaces, apart from the gentle band of colour at the bottom and tops of the windows and doors), we had to go all over the surface, wiping the dust and finger prints off. Sometimes, a bit more effort and the use of some sand paper was require, to bring back the clean look again.
    Front Porch Wall is Clad plus also Walls D and E too

    C-Wall-Finished

    Front Porch Wall is Clad plus also Walls D and E too

    C-Wall-Finished-2



    After that, we tidied away the three platforms and then continued on the next and last two wall sections, “D” and “E” to finish off all the walls that make up the “front” of the building that don’t need the fire-treated timber. We were looking at the finished C porch wall and decided that the darker band running underneath and over the windows should be toned down. We therefore proceeded to unscrew the high scorched planks off the “A” wall to scrub them more vigorously and put them back.
    Front Porch Wall is Clad plus also Walls D and E too

    Dark-planks-Before-Scrubbing

    Front Porch Wall is Clad plus also Walls D and E too

    Dark-planks-After-Scrubbing



    Following this new thinking, we also decided to only use scorch level “2” and level “3” to form a narrower band on the “D” and “E” walls, to make the darker bands less of a statement.
    Front Porch Wall is Clad plus also Walls D and E too

    D-Wall-Complete

    Cladding on C,D & E

    Cladding on C,D & E



    This concludes the work on the first half of putting up the Larch timber on our walls. The next job is to sort out our second set of timber, remove the rusty iron marks, scrub the darker scorched planks to tone those down and then dunk all of them into the oil bath. That would be next week’s list of jobs to do.

  • Larch Cladding Progresses, P2, A and B Sections all Finished

    We resumed work on putting up more Larch cladding planks on to the wall sections “P2” and “A”, coming around the Great Room and along the front of the house.

    Larch Cladding Progresses, P2, A and B Sections all Finished

    Cladding-EOD-Tuesday


    It is just a repeat of the standard placement of each Larch piece, according to the scorch burn level and the randomised widths, and getting them cut and sometimes connected together with a lap joint.
    The middle of the “A” section has a fence support post so it was a case of making sure the randomised planks came to the same pattern at the top for the final two rows. We only had to manually swop over two planks in the spreadsheet and we were also lucky that the combined height arrived almost exactly to the height of the fence break, thus avoiding having to reorder the list!
    Larch Cladding Progresses, P2, A and B Sections all Finished

    Cladding-EOD-Wednesday


    On Thursday, we did discover something that was concerning us and it happened during a heavy rain fall (we had 6mm of rain in 10 minutes flat!!) and we watched the rainwater fly off the roof and missing our gutters. This was in the valleys of the roof and the sheer amount of water that had collected was enough to make it shoot down the valley and the angle meant that it shot over the edge of our gutters. We had noticed to how wet these corners were after a rain shower and we thought that we might have had a leak or something. But now we know what has happened and we can now build a solution which is to construct a barrier of some form, to catch the flying stream of water and deflect it downwards into the gutters instead. That is good!
    By the end of the week, we have completed the “A” and the “B” sections and have moved onto the more complicated “C” Front Door Porch section that goes up four and half metres, up in the apex of the roof that hangs over the Front Door and Entertainment room.
    Larch Cladding Progresses, P2, A and B Sections all Finished

    Cladding-EOD-Thursday

    Larch Cladding Progresses, P2, A and B Sections all Finished

    Cladding-EOD-Friday



    We needed to make sure that the first row of the Larch timber, a large width with a scorch level of 1, was positioned at the exact level so when we have reached the top of the doorway and the window, they all aligned up together and smoothly allows the next full row to blend in seamlessly. We used our laser level gadget that produces a sweeping red line, right on the horizontal level, to provide the necessary synchronising factor to achieve this goal.
    Larch Cladding Progresses, P2, A and B Sections all Finished

    Cladding-EOD-Saturday


    We will continue next week, while dodging the short sharp showers and hopefully we will get the rest of the front of the house clad. Then we can turn to our Fire Proofed Treated timber, clean the iron marks off and dip them into the weather protection oil and then proceed installing the other half onto the walls along the side and back.

  • Templates Created and Larch Planks Starts Going up on Walls

    At last, we can actually see the Larch cladding timber going up on our walls this week! But first, we made a couple of templates; a lap joint cutting guide to produce a 50mm wide half lap joint for two pieces running on the same row, so we could screw both “ends” of the two planks into the single upright batten.

    Templates Created and Larch Planks Starts Going up on Walls

    Lap-joint-jig


    It uses our two battery powered circular saws; one to rip across the end at 50mm deep cut and just shy of half way through the thickness (10mm out of the overall 20mm thickness) and the other saw to cut across the face at 10mm deep to complete the removal of the piece. Then we flip around the second plank (end over end; rather than edge over edge) and repeat the process using the same template. This produced two mirror image cut away ends that merges together almost seamlessly.
    Templates Created and Larch Planks Starts Going up on Walls

    Cutting-accross-the-end-

    Templates Created and Larch Planks Starts Going up on Walls

    Cutting-across-the-face

    Templates Created and Larch Planks Starts Going up on Walls

    Makes-two-half-laps

    Templates Created and Larch Planks Starts Going up on Walls

    Which-come-together-neatly



    The second template tool were three metal plates with guidance holes drilled into them. There are three versions; one for each plank width. These helpful guides will keep our placements for the mushroom headed stainless steel screws at a regular and consistent location when fixing all the cladding planks up on the walls and their battens.
    Templates Created and Larch Planks Starts Going up on Walls

    Fixing-hole-drilling-jig


    Skipping pass some external interruptions we had this week, we went to the far back left corner of the house, to the Great Room wall section, P1, to start there. The wall is 4800mm long with a large window in it so we can learn how to proceed, setup working platforms (two trestle tables joined together using two CLS 63mm planks and covered in plywood left-over pieces) and carefully see how we put up each plank in turn. The spacing between each row of cladding is achieved using a 9mm thick plywood for the bottom row against the slate ribbon and a 6mm piece of MDF to separate each row going up the wall.
    Templates Created and Larch Planks Starts Going up on Walls

    Cutting-bench


    We decided to start at the bottom of each wall, with the widest Larch timber (burnt to a level 3) and then followed by the 2nd row of a medium plank (with a burn level of 4 – darker) and then finally the darkest (burn level 5) plank using a narrowest plank to meet up with the window sill. We arranged it so that the joint between this row and the fourth row is just hidden by the Oak sill itself so we had to remove s small area (the upward slope) of the Larch timber and it all fitted very well.

    Then we got our spreadsheet and randomised the order of the 12 planks that go between the bottom and top of the windows, to mix up the three different widths, to make it more interesting and more variations around the house. We decided that we would mark on the batten on either side of the window, the exact placement of each row so we can be reasonably assured that our last plank will align to the top of the window in a consistent manner. This in fact exactly what happened and we now have both sides of the window populated with planks spaced apart by an average of 11.5mm over 15 planks.
    As we got higher and higher, we realised that we needed a better means of working and reaching up that high so we took one of our three large platforms and chopped the legs down so it provided enough height to enable us to reach up inside the eves.
    Templates Created and Larch Planks Starts Going up on Walls

    Lowered-working-platform


    We finished off the main area above the window and stopped just short of the rafters. We left the gap between each rafter exposed to see if it really needed filling or not.
    Also we noticed that we could see the “pink” battens plus also the gap between the Larch planks were much more obvious higher up because we are looking upwards and able to “see” up the slope between the rows of Larch.
    Templates Created and Larch Planks Starts Going up on Walls

    The-clad-P1-Wall

    Templates Created and Larch Planks Starts Going up on Walls

    You-can-see-the-Pink-batten-between-the-planks



    So we spend a couple of hours painting the top 500mm of the pink batten along the front of the house, including all under the front door porch area with black paint we had left-over and we will also close up the gap of the upper rows to reduce the impact of the joints.
    The final day Saturday, was a rain washed out day so we got on with another job, fitting the filter modules and sterilising unit together, along with a submerged pump to our rain water underground tank. See Rain Water Underground Tank Brought Into Operation.
    Next week, weather permitting, we will resume putting up more cladding on the walls but if disrupted by bad weather, then we will do some preparation work to produce more Oak decorative coverings for the corners of the building.
    Templates Created and Larch Planks Starts Going up on Walls

    So-we-painted-the-top-of-the-battens-black

    Templates Created and Larch Planks Starts Going up on Walls

    Right-up-the-porch-wall-


  • First Set of Larch Timber Dipped in Fire Retardant Liquid and Second Set Dipped in Oil

    This week, we finished waterproofing our dunking trough, with two layers of thin plastic sheeting we found in the shed and then covered over with a left-over length of our roofing membrane material to provide a scratch resistant surface as we dip each plank in and out.
    Then we made five spikey drain support strips, spaced apart 1.2metres so we could do every length we had from 3mtres to 5.7metres. Each strip was 1.2metres long and we used forty 100mm standard nails, hammered through the batten via pre-drilled clearance holes, spaced apart by 25mm and this would allow us to handle 39 planks at a time.

    Dunking-tank-ready-for-use

    Dunking-tank-ready-for-use


    The first job was to pour in our Flame Retardant treatment .. no actually, it was to pour in a large trug of water first, about 30 litres and leave it for an hour to make sure we don’t have a leak. We can afford to lose some tap water but not our Flame Retardant Liquid which costs £1000 for three 25litre bottles!! Link to the product
    But we needn’t had feared .. we had No Leaks! Phew!
    So we poured in two bottles of the fire stuff and started dipping. We measured the level in the trough at the beginning and it was 42mm high for 50 litres.
    We began with the widest planks first, the 150mm width and all 4 metres long.
    It was not too bad a process, dip one in, rotate in the liquid to ensure a full coating and then lift out to drain and repeat.
    First-batch-of-planks-Fire-Treated

    First-batch-of-planks-Fire-Treated


    We had started in the afternoon as the morning was spent making the spikey draining prongs. But we wanted to get all 300 planks dipped so that they could and should dry overnight before they get their second and third dunk. It was a very, very long afternoon and we finished just gone 7pm ? Phew!
    Fire-treatment-Day-1

    Fire-treatment-Day-1


    But shock! Horror! We suddenly realised that our nails were corroding and leaving black lines on our nice Larch planks! Oh **** and double damn! The Fire Treatment liquid was water based and we found that the fire proofing chemical was speeding up the whole rusting process! So we needed to clean the nails, dry them off and spray them with black metal paint to protect them. That was done at 9pm! Oh Boy!
    In the morning, Stephen found on the web a solution to remove rust marks from timber by using a solution of Oxalic acid to dissolve the iron oxide and he was all ready to order the necessary chemicals when mum said “look under on the shelf in the kitchen and you will find a fifty year old bottle” and apparently, it was a common laundry solution in getting rid of rust marks on clothing! So making up the required solution, we rubbed the rust marks on the timber .. and they disappeared .. to only leave a bright yellow smear over the spot!! Big Sigh!! What Now??! Roll eyes upwards!!
    Black-Iron-marks-on-the-timber

    Black-Iron-marks-on-the-timber

    Treated-with-Oxalic-acid

    Treated-with-Oxalic-acid

    Marks-are-gone-but-

    Marks-are-gone-but-

    it-leaves-a-yellow-stain

    it-leaves-a-yellow-stain



    It must be the fire treatment chemicals doing it! Oh Boy! We took some scraps of Larch timber and dipped them into the treatment, wiped them with the rust remover to get the yellow smear and then left them outside in the sun to see if they will bleach away. We were also thinking about sanding the surface or wire brushing it or something to get rid of the rust marks etc. That would have to be done later on.

    In the meantime, we resumed the dipping process, but in reverse, taking the planks from the drying pile (yes the planks were all dry!) and gave them their second dunk. By lunch time, we had done all the long narrow planks and to our frustrations, we saw that we were leaving black marks on the planks in addition to the rust marks and realised that the black paint we put on the previous night had not survived for some reason. We threw Our Hands Up In The Air!!! Arrgh! So after lunch, We replaced all the draining prongs with 90mm galvanised air-gun nails and made five replacement draining supports, but spaced apart by 30mm this time, affording us to handle 33 planks instead of the 39 before.
    So, mid-afternoon, we resumed again, dipping all the remaining planks and finished nearly 7pm again!! Were We Whacked!!! Gee Wizz!

    Fire-treatment-Day-2

    Fire-treatment-Day-2


    The third day of dipping, we had some good news to start off with, we saw that the yellow smear had disappeared completely! Hurray!! It seems that the yellow chemical was not very stable, at least, the test pieces we left outside in the sun had lost their yellow!! Yippee!
    With a lighter heart, we got on with the final third dip, putting our third bottle of the treatment in the trough and got on with the dunking process.

    We had been measuring the liquid level each day and we could see that we were using about 20mm of liquid for each dipping session and that was good. by the end of the third day, we had just a few millimetres of liquid left in the bottom of the trough, we had to wiggle the planks and flip them over several times to make sure they were fully coated.

    Fire-treatment-Day-3

    Fire-treatment-Day-3


    We then vacuumed out the remaining liquid, using a fine cloth filter to remove as much of the brown particles that had come off the darker burnt timbers and we manage to rescue about 6 litres, still slightly brown colour but at least, we have some ready to coat on any timber piece we want to make sure it is fire treated.
    That was the end of the third day on Thursday!

    So on Friday, it was the turn of the second pile of Larch timber that is earmarked for the front of the building and didn’t require the fire treatment process and just the oil solution. We poured in two of our four bottles of decking oil into the trough and got on dipping another 300 planks (just shy of 300 actually). It was a bit more slippery! But all were dunked in oil and stacked up over near the front of the building, ready to go outside to be mounted up on the walls.

    Oiled-planks

    Oiled-planks


    That was easy! Sigh!
    The last day was spent doing a major tidy up job in the workshop, taking out the ill-fated nails, putting tools away and sweeping the whole place. We then install the Sun Shield on the corridor and lastly inspected our water tank we got on top of our garage roof. It hadn’t been inspected for several years so while we were up there, we took a look and it was all fine.
    So that concludes our rather adventurous week!! Phew!