Month: August 2017

  • K Ridge Smartened Up and First Fitting of Metal Elbow!

    This morning, we planed the top and bottom edges of both part of the K Ridge Rafter. We wanted to make sure that these surfaces are clean and smooth to get maximum contact area to the metal strip (coming later on) and the wood and have plenty of glue connection to maximise strength. We also planed the middle joint to clean up bumps etc. caused during the manufacturing process.
    After struggling to get both parts laid flat on the work bench, pushing one end right into the shelf to the wall – phew and the other end sticking half way out the main workshop doors on a roller support leg! We managed to join them together so we could lay down one of the metal bracket piece that makes up the elbow joint element.
    We then put in pilot holes where the bolts are going to go, and using a portable drill press and our electric powered drill, we drilled 10.5mm holes through the flanges, all eight of them. after that, we managed to get both metal bracket pieces bolted together and tightened up.

    K-Ridge-Metal-plate-Test-fit-1

    K-Ridge-Metal-plate-Test-fit-1

    K-Ridge-Metal-plate-Test-fit-2

    K-Ridge-Metal-plate-Test-fit-2



    It is only a half day of work today because of other commitments so tomorrow, we will have to resume work outside as we just don’t have enough room inside the workshop! The other part needs to go in and have its own test fit too. Then the long narrow metal strips (5mm thick) will go along the top edge and bottom edge and bent at the elbow joint corners. Having done all this, everything is glued up and screwed and bolted all back together again!

  • K Ridge (Part 1 and Part 2) Completed

    Today, we cut down to the required lengths the LVL timber pieces with the appropriate angles on their ends for both parts of the K Ridge Rafter. This one has an elbow joint half way along as it follows the shape of the roof going over the extension at the back of the house. The elbow joint is reinforced with a solid metal brackets, two of them, to sandwich the rafter in between and bolted together when it is assembled and installed.

    Ridge-K-Both-Parts

    Ridge-K-Both-Parts


    These two parts are fairly usual in their construction with noggings and the polystyrene foams inserts etc. so work went very well and we now have two completed sections and they will dry (the glue) overnight before we tackle the next task of fitting the metal brackets into place and drill clearance holes for the bolts tomorrow and making sure we get it all aligned up good and proper!

  • Preparation for Next Set of Rafters Starts

    These last two days has seen the start of the building the next set of rafters. The metal brackets pieces were painted to give them a semi protection against rust while they are exposed to the weather to until the roof is on!

    Splice-plates-painted

    Splice-plates-painted


    Then we sliced up some polystyrene foam blocks to make the inserts for the K Ridge and the O Ridge elements (including the angled bits going down to the walls). and finally, to finish off the first day yesterday, we measured the diagonal distances from the K wall corners and middle location, back to the central point on the steel I-Beam and analyse this against the drawings. It turned out to be pretty close, only 10mm offset for the two outside corners and 19mm offset in the middle of the K wall. This is close enough for us to continue to build the K Ridge and if there is any adjustment needed to be made, we can slice off little pieces off the beginning of the K ridge during installation.
    Today, we sorted out all the plywood strips we had already made, also took all the “waste” plywood strips and moved them into our garden shed for storage and easier access. We spent all day slicing up more plywood sheets and other strips to generate all the webbing we will need to complete the remaining Special LVL Rafters, as follows:

    • 9 x 400mm wide
    • 6 x 413mm
    • 12 x 423mm (already done previously)
    • 18 x 455mm (taken from 20 strips left-over pieces)
    • 4 x 477mm (two already made with a further 2 today)
    • 4 x 508mm wide and that’s it!

    We tidied up the pile of these plywood strips and put all the ones that will make the O Ridge series of rafters and stored them in the garden shed. Also, we brought in four lengths of our LVL timber pieces, 3 x 4190mm and 1x 3500mm lengths. We got our template back into shape again and started with our first rafter, the K Ridge. This 477mm wide object has 4 strips of the webbing and sliced a shallow angle cut (only 10.5 degrees) on one end of the plywood. This end will be push into the metal bracket and joined onto the second part of the rafter, the K Angled, which goes down at a 45 degree slope to the wall.
    Tomorrow, we will cut the LVL timber and then sand to get them ready for gluing and nailing.

  • Ripped Up Neighbour’s Hedge!

    After lunch today, we helped out our neighbour by driving our Mini Digger up the Loke and then proceeded to rip and grub out their Hedge fronting the Loke.

    Neighbors-Hedge-grubbed-up

    Neighbors-Hedge-grubbed-up


    It was very rewarding for us, especially for the fact that we haven’t used the mini digger for months and months, but the machine started first time! It took only about 30 minutes to do the job!

  • O ridge Metal work Finished

    The metal splice plates for the O ridge have been welded together.  More care was taken to weld them in short stages and swapping from one plate to the other resulting in almost no warping of the plate.

    Ridge-O-Splice-plates-welded

    Ridge-O-Splice-plates-welded

    Now we have to make the wooden parts of these beams…

  • K Ridge metal work Finished

    The parts of the metal work for the K ridge were welded together, after they were finished it was noticed that the big metal plate had been distorted by the heat of the welding. We will have to investigate how to reduce this for the O ridge plates!

    Ridge-K-Splice-plate-welded

    Ridge-K-Splice-plate-welded

    Tomorrow we will make the parts for the O ridge and maybe start welding them.

     

  • K Ridge metal work started

    After finishing the construction drawings, fabrication of the metal work started with drilling 64 holes in the flange reinforcement strips.

    Flange-reinforcement-drilled

    Flange-reinforcement-drilled

    Then the two side plates were cut out and drilled for bolts.

    Splice-plates-cut-and-drilled

    Splice-plates-cut-and-drilled

    Tomorrow the sockets for the adjoining  rafters will be welded on.

  • Workshop Switches Over into MetalWork Department

    Today, we did two jobs on the fly. One was on the computer to organise, sort out and prepare diagrams for the steel bracing support unit, and the other job was to tidy up the workshop and bring in the various steel strips from the shelves outside under cover. The steel had to be sanded to remove the little bit of rust on the top most strip of the pile, so using the orbital sander with lots of emery cloth discs to go up and down each strip to remove as much of the rust as possible.

    Steel-strips-derusted

    Steel-strips-derusted


    The Steel Bracing Unit that holds and reinforces the K Ridge element (this is the section of the house with the extension at the back over the Bedroom 2). The picture below shows the 3D diagram of this module.
    K-Ridge-Splice-Plate-1

    K-Ridge-Splice-Plate-1

    K-Ridge-Splice-Plate-2

    K-Ridge-Splice-Plate-2



    Tomorrow, we carry on with the preparations and soon will be slicing up these steel strips into the jigsaw pieces to then be welded together.

  • Vaccum System Version 2.0

    Yesterday, the new filter separator module was created using 4 layers of 18mm OSB board with a large circle cut out in a increasing diameter at a sloping angle. Then an inlet 50mm hole was drilled at the tangent of these circular chamber so the air would come in and fly around the circle and make the rubbish to be flung outwards and downwards into the main rubbish collection area. A pipe up the middle of the lid would extract the air, being pulled by the motor unit and second filter chamber.

    Vacuum-system-Mk-2

    Vacuum-system-Mk-2


    Then this morning, the final hook up job was done to connect the pipework to the new second generation of the filtering unit that we copied off the web. It seems to be working quite well but after doing a major clean up around the whole workshop, the amount of dust in the paper filters was quite significant and was reducing the power of the air flow. This is a disappointing result and we need to go back to the drawing board. But at least, it is working as a vacuum system so we will use it for now and will have to empty the second chamber more often.

  • Vacuum System Being Repaired

    This afternoon, for something different from rafters, the Vacuum System was taken apart, well half of it was at least. The broken first stage filtration unit. The box was reinforced with edge strips and cross bracing supports. The power of the vacuum is such that when the system is going and someone causes a blockage, then the force pressing on the sides of the boxes is about 4lb per square inch and when the area of the side of the box is 24 inches one way and 24 inches high, a total of 576 square inches and so when you multiply the force (that 4 inches per square inch) together, you get as much as 2300 lbs of force squeezing into the sides! That is nearly a ton of weight! Eek! Plywood is strong but after repeated pulses of being hammered with that kind of force now and again when the nozzle gets blocks, it is not surprising that the wood suddenly snapped!
    The other aspect of this repair work is that the vortex separator is just not working and we suspect that our power of our vacuum motor unit is way over the top for that particular size and shape! We have been researching on the web and surprisingly, there are many designs out there and we are going to try making our own homemade centrifugal spinning chamber to separate the “dirt” from the air. Very Fascinating stuff, this whole field of Rubbish separation and filtration, without the need of paper or cloth filters and hence maintaining full power at all times!