On several days over the previous couple of weeks, our Loke has been scraped down the middle to remove 2.5metres wide strip of old surface and grass plus dirt. That was taken away by a bloke with a grabber in his 15ton lorry.
We then buried a pipe under the middle of the loke to act as a conduit for any future needs.

The Loke Scraped, Hardcore Laid and First section of Grid Completed with Crushed Recycled Asphalt

Loke-scraped-clean

The Loke Scraped, Hardcore Laid and First section of Grid Completed with Crushed Recycled Asphalt

Conduit-placed



Then twelve tons of crushed concrete arrived and distributed into the 25 metre strip, levelled and crushed down using our mini-digger.
This week, we had a delivery of the recycled crushed asphalt material, just 4 tons to start off with. Then, ourselves with our neighbour, did another scraping using a wide CLS timber with pieces of plywood screwed to it to form the careful shape we want to finish off, guided by a taut string and smooth out the rectangular in front of the neighbour’s first gateway. The special shape is with the two parallel tracks to have a slight angle to them so any rainwater will be encouraged to flow into the centre channel and then flow down the Loke without spilling into anyone’s garden.
The Loke Scraped, Hardcore Laid and First section of Grid Completed with Crushed Recycled Asphalt

Loke-after-hardcore-and-first-grids


Then a grid of twelve by five modules was clipped together and positioned 500mm away from the gate posts. The small gap was filled in with additional line of these plastic 40mm high grid modules, but with their width trimmed down to fit. The whole area was then loaded up with the crushed asphalt and then raked all over, with plenty of thumping using our lighter-weighted electric compacter to vibrate the material to settle down into each little cells (each measuring just about 70mm square and seven of these cells on a side to form the overall 500mm grid modules).
The Loke Scraped, Hardcore Laid and First section of Grid Completed with Crushed Recycled Asphalt

First-set-of-grid-placed-and-filled


We will go back in a few days time to put down more “fines” to top up any cells that has settled more than others. The next task is to form the two tracks coming down the Loke, connected to this initial finished area and this will take us to the second rectangular section in front of the 2nd gateway. We will have to order more recycled asphalt material, probably another 4 tons.

By Shaun

Leave a Reply