Category: Build Progress

  • Laser Level Check and Final Adjustments of Cellular Framework of Floor Slab

     This afternoon, we went around checking the height of all our cellular framework that divides up the Floor Slab. It is rather satisfying that we didn’t get more than 10mm up or down and mostly within 5mm of required height all over the Floor Slab’s framework.

    We made some adjustment to one that were a little low (by propping up the framework on flat pieces of hardboard) and gently thumped down the highest points so we ended up with nothing more than 5mm out anywhere.

    Checking Cell Heights

    Checking Cell Heights

    As the picture shows, we used the laser level equipment to analyse the absolute height, by putting the sighting pole on top of all the concrete blocks lying on all the “T” junction points.

    We also wrapped a double layer of plastic around the buckets that are in the two sump areas so that we will have a fighting chance to get these buckets out of the concrete after it has set!!

  • Building Inspector Approves Preparation for Floor Slab!

    Our Building Inspector came along at lunch time and spent a few minutes looking over our DPM plastic, sticking up pipes and how it was all stuck together.

    Building-Inspector-calls

    Building-Inspector-calls

    He said it was very thoroughly done and he approves!! Yippee!

    P.S. He forgot to tell us he had visited and approved, we were at lunch!

  • Shopping List for Steel Bits and Pieces

    This morning, a shopping list is being made up containing the Steel parts that forms the Central Structural Framework that holds up the whole roof complex. There are RSJ, box beams and lots of plate materials.

    We will start the construction of this framework when the Floor Slab is poured and had time to cure a week or so. It will be a case of having our scaffolding out and with strong rope and winches, to lift up these steel parts into place on top of their steel legs etc. a real case of a jigsaw being put together!!

  • Concrete Deflector for Top of Perimeter Walls

     We finished off the day’s work by building a deflector to control  the sloshy concrete being poured onto the top of the Perimeter Wall. The walls has hollow columns and they are all being filled up with the same ready mixed concrete being poured for our Floor Slab.

    Tool-to-aid-filling-the-columns

    Tool-to-aid-filling-the-columns

    The Concrete is going to be pumped using a big 30 metre boom arm coming from a massive diesel powered engine and the controller will move the wide diameter tube over the hollow columns by remote control, so we made this deflector to help him aim better!

    It is made of OSB boards and CLS timber, to make a 45 degree angle slope at the back and hooks to allow the tool to sit on top of the concrete  block walls without tipping off but allow it to move along. We also put two movable side hooks so one can lift these hooks when we come to a corner of the wall.

  • Day 2 of Assembly of Cells Framework in Floor Slab

     We completed the Assembly of the cellular framework in the rest of the Floor Slab, namely the Entertainment Room, Bedroom 2 and then Bedroom 3 and Utility Room.

    Floor-slab-Cells-Day-2

    Floor-slab-Cells-Day-2

    We then went around pinning into place all the fluffy expansion strips onto the framework where the 5 Energy Modules are, plus some extra pieces to aid possible concrete expansion when the whole Floor Slab warms up. That didn’t take so long and we finished up by putting concrete blocks on every “T” junction of the framework to weigh it down against the buoyancy when the heavy liquid concrete gets poured in. We calculated that the weight displaced by the OSB 100mm high strips will be approximately 3kg per every metre plus another 2kg displaced for the fluffy strips so in some lengths of the framework, it could add up to 15kg from junction to junction. We put plenty of concrete blocks weighing 20kg each on every junction so the total weight from all these blocks should counteract the uplift from the liquid concrete.

  • Floor Slab Cells Assembly – Day 1

     Today, we started assembling the wooden dividers which go across the whole Floor Slab from the sections we made last week. We have done the Great Room and the section that includes the Kitchen and Bedroom 1.

    Floor-slab-Cells-Day-1

    Floor-slab-Cells-Day-1

    It is working out reasonably OK, without too many difficulties, apart from sometimes the concrete foundation strip having a lumpy edge so we have to cut into the OSB strip a little bit to make it fit like a jigsaw. The fluffy expansion strips will be done later when we have completed all the wooden cells.

    Floor-slab-Cells-Joints

    Floor-slab-Cells-Joints

    We carried on with the front extension section and tomorrow, will continue across from the Hall and Entertainment Room, towards the back and Bedroom 2 and then over to Bedroom 3 and finally the Utility Room.

  • Floor Slab Dividers Cut and Ready

    While it was wet outside, we continued with making pieces of the cellular framework matrix that will divide up the Floor Slab into lots of rectangular regions so that no cracks (hopefully) will form when it cures and then gets heated up and cools down again and again and again!

    We put together a heap of readymade strips of various lengths (using the OSB 100mm wide pieces we produced the other day), plus another heap of strips ready to trimmed and fitted in place during the installation process.

    Slab-Matrix-parts

    Slab-Matrix-parts

    Monday, we will have to sweep the water off the plastic if it is still there, and then start assembling the dividing framework right across the slab, and then insert the fluffy expansion boards in and around the appropriate areas.

  • Day 4 of Setting in the DPM over Ground

     Today, while we waited  for the rain shower to clear up, we sliced up loads of strips of OSB left-over from our foundation shuttering, down to 100mm wide, and these will be used for forming the cells all over the Floor Slab to make sure that the soft fluffy expansion boards are held into place solidly, plus also make sure that no concrete is allowed to be more than 3metres in a single piece to avoid nasty cracks from appearing in jagged and random places when it cures but also in changes of temperatures over the seasons.

    We also sliced up more old shuttering boards into 50mm wide strips, after lunch, and these were used to mail up the flappy loose ends of the DPM up the walls.

    Edges-nailed-and-Conduits-sealed

    Edges-nailed-and-Conduits-sealed

    Then, we mixed a wheelbarrow load of dry concrete using 3 builder’s buckets of sharp sand ballast and left over cement and patted blobs down and around each and every item sticking up through the DPM plastic. There were 4 sewage pipes, 32 temperature probe conduits, 5 huddles of pipes, wide tubes and more conduits, some more water filling conduits as well and finally, the dozen electricity, water air and vacuum pipes and conduits to and from the Garage!!

    Sewage-pipe-sealed

    Sewage-pipe-sealed

    A-tank-connection-cluster-sealed

    A-tank-connection-cluster-sealed

    Utilities-sealed

    Utilities-sealed


    The next job is to use those 100mm wide strips and form the matrix of cells all over the ground. We have started the ball rolling for the “day” of the poring the slab to be Wednesday 5th October, but it still depends on our Building Inspector coming and approving our work and also for the concrete people to come back from Holidays to answer technical questions on whether we need some special additives to be included to make the concrete more suitable for coping with wide temperature fluctuations during the seasons as we have our Energy Modules being heated up during the Summer and then cooling down during the Autumn and Winter.

  • Day 3 – DPM All Down and Ready for Floor Slab .. Almost!

    Today, we finished off laying down the plastic sheeting over the ground. We completed the strip over the Entertainment Room and Bedroom 2 which was fairly difficult with the array of pipes etc. looming out of the ground! The last section was then levelled and scraped flat again (after the petrol compactor had whacked it down a week ago), and we put out the last strip of DPM across Bedroom 3 and the Utility Room. The corner in the Utility room was particularly complicated with dozen pipes and conduits sticking up including one tunnel as well!
    We also went around with our 100mm wide silver duct tape and sealed all the overlapping joints on all the DPM plastic sheets we have put down.

    Day-3-DPM placement Sump point

    Day-3-DPM placement Sump point

    Day-3-DPM-placement-Utility Conduits

    Day-3-DPM-placement-Utility Conduits

    Day-3-DPM-placement-finished

    Day-3-DPM-placement-finished



    Tomorrow, we will mix some light grade concrete and put a blob down at every single intrusion through the plastic where pipes and conduits had to come up so that any slits and cuts in the plastic are covered up nice and solid to avoid the very liquid free flowing concrete from sliding under the plastic and ruining the performance of the Floor Slab. No Thank You!

  • Day 2 of Laying DPM down for Floor Slab

     We carried on with the task of laying the Damp Proof Membrane (DPM) plastic down on the ground inside our perimeter wall of our house. We now have completed and reached up to the edge of the Entertainment room and half the Bedroom 2 at the back. We had to put down more sand to flash off these sections and scraped it level, which took all morning to do.

    Day-2-Laying-DPM-1

    Day-2-Laying-DPM-1

    Day-2-Laying-DPM-2

    Day-2-Laying-DPM-2


    We had no rain today which was nice, but it was rather windy and had our plastic sheets flapping in the wind a bit so we put down lots of concrete blocks on the edges to hold everything in place! tomorrow, we resume and do the last 2 strips, but after we go and buy another roll, our 4th from Jewson’s, and we will only need about 5 metres off this roll to finish the job – Oh Well!