Category: Delivery

All the deliveries we get.

  • Insulation PU Foam Seconds Arrives on Forty Pallets!

    On Friday, saw the arrival of the huge load of “Seconds” PU foam boards, all the way from South Wales where an outfit takes spoiled foam boards from the nearby factory and processes then and resells them to anyone who wants them. We wanted it all including the bad parts! By buying everything it makes it slightly more expensive than glass wool, nearly twice as expensive but it is so much easier and nicer to handle than the dreaded glass wool! Plus also, for our walls, the rigid boards are much more reliable and holds its shape vertically in the walls, compared with glass wool, especially the deep amount we are aiming for, over 300mm thick and we didn’t want the wool material collapsing under its own weight after a decade or so. So we found this outfit that packets this spoiled PU foam boards. This time, we wanted as much as he had and could fit on the lorry. We got forty pallets, each measuring roughly four feet by 4 feet and 4 feet high. There were 28 pallets loaded into the main part of the lorry, plus an additional 12 pallets loaded on a second trailer linked to the main truck.

    Insulation PU Foam Seconds Arrives on Forty Pallets!

    Insulation-delivery-truck-and-trailer


    It was slightly more complicated because the driver didn’t want to drive down our Loke and also didn’t want to abandon his trailer module in a layby up the road (was afraid that it would be blocked in). So we took our mini-digger with our new Fork Lift Attachment for our Mini-Digger up the Loke to the main Beccles Road and unloaded all the pallets up there and transported them down on our large flatbed trolley. We had the fabulous assistance from all our neighbours, helping to load two pallets on the trolley and getting that down to our property. That was twenty separate trips in all! Phew!

    We landed the pallets all over the place in a random manner, just to get them out of the way and clear the Loke as quick as possible. It took us over two hours to unload the lorry and a further hour to finish transporting the rest! Double Phew!

    Insulation PU Foam Seconds Arrives on Forty Pallets!

    Blocking-the-loke-with-Insulation-1

    Insulation PU Foam Seconds Arrives on Forty Pallets!

    Blocking-the-loke-with-Insulation-2


    This load of insulation boards will be sliced up and fitted into and between the legs of our wooden walls, filling it up to a depth of around 200 to 240mm deep, and then the rest will be filled up with glass wool. About three quarters of this load of foam boards will be used up in filling the walls, the rest will be used to start the job of filling the roof rafters and we do need another lorry load of seconds again to get that particular job done too!!

    Insulation PU Foam Seconds Arrives on Forty Pallets!

    Big-Piles-of-Insulation-1

    Insulation PU Foam Seconds Arrives on Forty Pallets!

    Big-Piles-of-Insulation-2

    Insulation PU Foam Seconds Arrives on Forty Pallets!

    Big-Piles-of-Insulation-3


  • Second Delivery of CLS Timber Arrives

    Our remaining timber arrived Thursday yesterday late afternoon. There were 348 planks in this second delivery, adding with our previous one of 99, we now have 447 planks of 63mm by 38mm CLS untreated soft wood, each measuring 4.8metres long.
    We spent the last hour of Thursday and several hours on Friday morning, moving the entire load into the house and storing them all down in our Great Room.

    Second Delivery of CLS Timber Arrives

    Lots-of-wood-ready-to-use


    We are missing one plank plus also one of the pieces was seriously damaged so we have requested replacements

  • Untreated 63mm by 38mm CLS timber Arrives

    We had our delivery of fresh timber arrive today, this morning, but it turned out to be only fraction of what we ordered.

    Untreated 63mm by 38mm CLS timber Arrives

    CLS-Delivery-20201120-1

    Untreated 63mm by 38mm CLS timber Arrives

    CLS-Delivery-20201120-2



    There was some confusion back in the builders merchant yard and we only got 99 planks. We were expecting 448 planks, which supposed to be a complete pallet load. We are chasing them up!!

  • Ten Concrete Beams Arrives

    Suddenly at a bright early hour, our concrete beams, all ten of them, arrive! We had to parked them on our driveway in such a position so we could then transport each beam inside the house through the Side Door, without hitting problems like trying to turn a 4metre long object around a sharp 90degrees turn! We also had to keep the driveway clear to allow our car out too! Phew!

    Ten Concrete Beams Arrives

    Conctete-Beams-Delivered


    After doing other chores and tasks in the morning, we started the heavy duty of moving these beams into the house. We bolted two large castor wheels to a slab of timber, already predrilled with the holes because these 2inch by 6inch short planks were used several years ago when we were moving the huge steel RSJ beams!
    But this time, we moved the 120kg concrete beams, once at a time, by clamping the wheels to the beginning of the beam and clamping a long wooden handle to the other end to allow us both to lift it up. Dragging the beam over to align with the Side Door, we proceeded to push each beam into the house, down the ramp and slipped past the various obstacles and parked them half way down in the middle of house, next to the metal roof legs.
    Ten Concrete Beams Arrives

    Beams-carried-inside


    It took us all afternoon to move the ten beams, being careful not to overtax ourselves and not to cause any damage to our house! The big challenge will be when we need to hoist them up and put them on our Entertainment Room concrete walls to form the roof! That’s another day’s Job!

  • Concrete Blocks Arrives

    The first load of new building material arrived today. 576 dense concrete blocks arrived with a ton bag of soft sand, eight bags of cement, two large paving slabs and one concrete lintel.

    Concrete Blocks Arrives

    Concrete-Blocks-and-Sand


    The remaining 74 blocks will be delivered soon, along with the 10 concrete beams. We are glad that we beat the lock-down deadline!

  • The Last Four Pallets of Slates Arrive

    Sometime during the afternoon, we had the delivery of the remaining four pallets of our slates and they were unloaded alongside our Loke, following the line as we intended, but alas, one of the pallets was dumped on top of two others!

    The Last Four Pallets of Slates Arrive

    Last-of-slates-delivered


    We did not want this, as we wanted to be able to take a handful of tiles out from each crate in turn so the roof would get a more random pattern, just in case, one crate would be loaded in the quarry from one spot in the slate mine and by the eleventh crate, could be using another part of the mine with slightly different colouration and texture. Hence, as recommended by experts, to take a few tiles from every crate, to mix it up a bit, and get a more balanced finished on our roof.

  • First Batch of Slates Arrive

    We had a delivery of the remaining timber battens, 720 metres of 38mm by 25mm sized lengths, but actually, we only got 714 metres so they short-changed us by 6 metres (but we did get extra of the larger battens) !

    First Batch of Slates Arrive

    The-smaller-roofing-battens-have-arrived


    We now have all our wooden battens, ready for our roof.

    We also had the first batch of our Slates , seven pallets, in total, containing over eleven thousand standard sized and 750 extra wide ones.

    First Batch of Slates Arrive

    Slates-being-delivered

    First Batch of Slates Arrive

    First-7-Pallets-of-slates



    Each pallet has over 1800 slates in 3 layers. We are expecting a further four more pallets of standard size in a few days.

  • Fence broken by delivery driver

    We had a delivery from UK-Mail today and the driver hit our fence post and snapped it off! He appeared to hit the post and break it off as well as flattening a few road cones placed by the fence to warn drivers that it was there! We have contacted UK Mail and will wait to see what they say about it.

    Fence-post-snapped-off-by-delivery-driver

    Fence-post-snapped-off-by-delivery-driver

    Fence-torn by delivery driver

    Fence-torn by delivery driver


  • Oak Timber Arrives!

    This afternoon, in the middle of our lunch hour (about 1:30pm), the Oak Timber arrived!! There were ten packs in total, in four stacks  on the back of the lorry. Also, on the back of the lorry, was a fork-lift truck which came down two steep ramps off the end! We were lucky that the driver was confident to reverse the lorry back down our Loke and avoided causing major traffic hold-ups on the A143 Beccles Road !

    Oak Timber Arrives!

    Oak-Deilvery-First-Pallet-Unloading-

    Oak Timber Arrives!

    Oak-Deilvery-The-Forklift


    The forklift the moved the packs to the cleared area by the Storage hut.

    Oak Timber Arrives!

    Oak-Deilvery-All-Delivered


    The pallets were quite neatly organised, each one having the timber of similar dimensions so we could check off against what we ordered. The initial spot check seems to show that we have got a lot larger volume of Oak than stated on the delivery note. This doesn’t means that we got more planks of Oak, just more volume. And in fact, after processing three pallets, measuring every single one and moving them to our sheltered storage area, it seems that most planks are thicker than advertised!
    Oak Timber Arrives!

    Oak-Deilvery-First-3-packs-onto-rack


    We had a cordless keyboard and a cordless speaker sitting outside on one of the shelves on the storage rack (connected to one of our desktop computers inside), and as each plank was measured using a digital calipers and steel rule, the data was typed into a spreadsheet and then moved and sorted on separate sections on the rack.
    We will resume on Friday with the sorting out the other seven pallets and get all the data into the database so we can cross reference any piece and mark it as being used and record what left-over there is, to be used somewhere else in other parts of the house.