Category: Timelapse Movies

  • “G” All Finished and “H” Half Way There

    We resumed the work of covering our roof with plywood boards and we got the last complex rhomboid shape made and fitted up to finish off the “G” roof segment. Then, carried onto the “H” roof section and put up another six sheets of plywood, half of them had angled cuts on the end to fit into the valley. Working on this roof section, is just that little bit more tricky as the angle of the slope is 40° and our boots doesn’t quite have enough grip by themselves so we are having to put up double number of “foot-rails” to support us and keep us safe!!

    Roof-boarding-Day-9-G-done-and-H-Started


    Tomorrow, we should see the “H” finished off and we can then start working along the back of the house and using our fixed working platforms too.

  • “F” and “G” Areas Almost All Covered

    With a slowly improving day with the Sun breaking out, we moved the mobile platform around the corner to start work on the “F” section of the roof. This is a relatively small area to do and we had almost finished it before lunch at 1pm.

    Roof-boarding-Day-8-F-done


    That was quickly finished soon after lunch and we moved along a bit further to slide into position to tackle our smallest roof section, the “G” that forms the right hand side of the Side Porch roof.
    This had also a Downpipe Channel module which needed a lot of trimming to reflect the angles of the “G” and “H” planes of the roof. That took a little while to get that right like, for example, projecting the diagonal valley down to the oak side wall and marking the point and then sawing the angled cuts off. All came out just fine – Phew!
    Next, was measuring the various edges, but this was also one complicated process as we had a rhomboid shape to make, not a parallelogram which would have been slightly easier, but both left and right ends having different angles! But we found a way to do it and we have now done two rows up the “G” segment.

    Roof-boarding-Day-8-G-mostly-done


    There is just one more row to complete this section and then we can start work on the “H”, all for tomorrow’s work.

  • “D” & “E” Completely covered

    In better weather we completed the boarding of Sections D & E. We are getting better at cutting boards the correct size first time.

    Roof-boarding-Day-7-D-E-Completed

    Roof-boarding-Day-7-Inside-of-D

    Roof-boarding-Day-7-Inside-of-E



    We have now covered 140 square meters of roof which is 38% of the total in 7 days so we are on schedule to finish in about 20 days…

    Stephen fails to do a ‘Shaun wave’ @ 4:37

  • “H” Rafters Fully Manufactured and Ready to be Installed

    On this very wet and chilly Monday, we resumed work in our nice and warm workshop to finish off the manufacturing processes on our set of rafters to do the “H” section of the roof.

    We sliced the bevel ends on all the 13 rafters we had to do, some were the full sized ones (nine of those) using our Bevel Slicing Machine, and the others only had just the 89mm CLS cut (three of them). These last were done using our usual chop saw as you can see below

    Doing-compond-bevel-cut-on-H17

    Doing-compond-bevel-cut-on-H17


    This concludes the job of creating these rafters and as soon as the weather clears up later in the week, we will get them installed up into the roof structure. In the meantime, we will continue with preparation and assembly work to do the rafters for the “P” roof section over the Great Room, which is another 15 of them to do!

  • Floor Slab is Poured!

     What A Day!

    7 AM

    We started at 7am at the crack of dawn to clear away as much as possible the rain water still puddling on the DPM plastic by using our home made contraption, a blend of a vacuum cleaner extended upwards with a powerful water pump sitting inside it!!

    Pouring-the-floor-slab-1

    Pouring-the-floor-slab-1

    We got about two third of the area cleared before the first of the heavy vehicles arrived, the pump engine with its 30 metre boom arm (time was  8:21am) and soon after the technician chap also arrived in his van, closely followed by the first 6½ cubic metres of the special crushed granite with nylon fibre mixed in a high cement content and special emulsifiers to make a very liquid flowing mixture!

     9 AM

    We started on the Perimeter Wall, filling all the hollow columns using our (another) homemade deflector tool. It worked rather well, with only small amount of dribbling cement and small crunchy bits escaping outside rather than inside the wall. We managed to do almost all of it using the boom arm pumping the concrete, only missing out about 15 hollow cores because the boom arm couldn’t reach that far!

    Pouring-the-floor-slab-2

    Pouring-the-floor-slab-2

    That was also the end of the first load of concrete too! Most of it went inside and about half filled all the hollow columns.

     10 AM

    That was the slow bit done and now the pump could go much faster indeed, and when the 2nd lorry load of concrete parked itself next to the pump (this lorry and the 3rd lorry were already arrived and waiting up on Beccles Road!!), the whole content, another 6½m3 of it, came gushing out all in 10minutes flat!! The boom arm went around all over the place to try and load some concrete in each cellular region so the dividers won’t feel overstressed. The same happened to the third lorry load and by 10:30am they were emptied and gone!

    Pouring-the-floor-slab-3

    Pouring-the-floor-slab-3

    11am

    While we were waiting for the next two lorry loads of the concrete, we went around cleaning off the dribbles of cement and the crunchy bits off the bitumen coated exterior surface using the garden hose with the spray nozzle. Our technician chap helped by filling in the last 15 hollows columns in the far corner of the wall too!

    12pm

    Finally, the next two lorry loads of concrete arrived, the 3rd 6½m3 and a 3m3 and started filling regions right to the top. Then we were getting worried that we wouldn’t have enough as it was looking rather the strong possibility that we would need extra but we also were wondering why this was. Then, we discovered that we had overfilled the Great Room and in some places it was more than 10mm extra thicker. Oops! This encouraged us to slow down and be more careful with the 5th load of the 3m3 load.

    Pouring-the-floor-slab-4

    Pouring-the-floor-slab-4

    The technician chap was working hard in dabbling the concrete to make it smooth out and find a good level, and then spraying the surface with wax to slow down the evaporation.

    2pm

    After we had levelled and smoothed the regions that has been filled up, we than calculated to approximately what extra amount of concrete we needed to finish off the job. It came to 2½ m3 so we phoned the Norwich office to order that and of course having to wait again for it to come all the way from Norwich.

    3:45 pm

    Finally, the 6th and final load of concrete arrived and got the rest of the Floor Slab poured in, carefully making sure we didn’t overfill anything this time and it went well!

    Pouring-the-floor-slab-5

    Pouring-the-floor-slab-5

    4pm

    All Finished!! The pump Machine cleaned itself and dumped it hopper load of concrete that it sucked back up it pipes, on the plastic we laid there just for that purpose, and using wheelbarrows, we scooped up about 7 loads and took it over to the front door region to tip it in to finish off the very final bit of filling up. Then, we washed down everything and coiled up hoses and washed our boots and staggered back indoors!!

    Pouring-the-floor-slab-6

    Pouring-the-floor-slab-6

     

    The Movie

    Here is the time lapsed movie of our whole day compressed down to just a 20 minutes!!

  • Foundation Concrete Is Poured!

    Here’s the site  at 7:46 before we got started …

    Aug-15th-The-site-before-work-started

    Aug-15th-The-site-before-work-started

    Our day started at 8:30 am with the arrival of the concrete pump lorry (half an hour early) ..

    Concrete-lorry-arriving

    Concrete-lorry-arriving

    The pump operator Alan set up his equipment including orientating the lorry, putting out the support arms, priming the pump and putting down tarpaulin sheets to protect the Loke surface against splashes etc.

    The boom arm is made of 4 segments, each being 8 metres (26feet) long so stretching across to our outermost trench was no problem ..

    Pump-Lorry-with-Legs-Extended

    Pump-Lorry-with-Legs-Extended

    Pump-Boom-fully-extended-1

    Pump-Boom-fully-extended-1

    Pump-Boom-fully-extended-2

    Pump-Boom-fully-extended-2


    Then at 9:40 am, the first load of concrete arrives and our work commences in earnest! We started by the Great Room and went around all 4 sides, then around the kitchen and bedroom 1, then around the back of bedroom 2 and bedroom 3 going along pass the side door position, around the Utility room and turn along the front and finally around the Entertainment room. Our first two loads of concrete (each being 6 cubic metres) got that far so we had to order an some more concrete, we had a quick measure and estimated we needed about 2 cubic metres to do the large front extension area of the Entertainment and Hall sections and the two pads in the middle. But when we finished had rather a lot of left over so we could have cut down on the extra quantity to about 1.5 cubic metres and got away with it, but we had to make a quick decision and we didn’t realise that the pump itself had more concrete in it’s the hopper and pipes too!

    We poured the most of the extra into two of our ready made viaducts (which we had fixed ends on whilst the last load of concrete was being mixed) and slid in thin dividers to make square blocks that we might use in the garden (as stepping stones?) or act as weights . The rest was loaded into some ‘Trugs’ and will may be used as all weather seats?

    Excess-concrete-in-impromptu-moulds-2

    Excess-concrete-in-impromptu-moulds-2

    Excess-concrete-in-impromptu-moulds-1

    Excess-concrete-in-impromptu-moulds-1


    Then, we went around smoothing all the edges and especially the corners and junctions to make sure that there wasn’t any lumps sticking up. The air tunnel corner by the Utility room was especially tricky but with careful checking with a spirit level, we scraped and smoothed it out ok.

    Aug-15th-The-site-after-foundations-poured

    Aug-15th-The-site-after-foundations-poured

    Foundations-Poured-1

    Foundations-Poured-1

    Foundations-Poured-2

    Foundations-Poured-2

    Foundations-Poured-3

    Foundations-Poured-3


    We didn’t stop for lunch and had only a couple of water breaks during the time when the concrete lorry had to go and get more concrete. It was a long single session but there was not much choice in the matter when you are dealing with concrete !!

    Here is a time lapse of the days work (it’s high resolution – press the full screen button at the bottom left of the movie to see)

    This is a major step forward for our house building project, having the foundations actually poured and setting! We are getting out of the ground at last!

  • Waste disposal

    Another of those inevitable expenses involved in demolition work is disposing of the waste. Now that the demolition is complete we have to get rid of all the waste. There is a lot of brick and concrete rubble and some general waste like carpets and other rubbish. The costs are not insignificant, a large skip for the general waste costs £135 (maybe 1.5Tons or £90/Ton) and the rubble costs £144 a lorry load (about 13 tons). But the metals make you money, disposing of the mesh from the rendering made us £30. The video show that it took 5 lorry loads to clear the rubble (£720! For about 60 Tons or £12/Ton). All those are cheap compared to disposing of the Asbestos cement panels from the house which cost £1037 for just 3.3 Tons (£315/Ton)! So all in all waste disposal has cost us 1037+720+135-30=£1862.

    Grab lorry removing rubble.

    Grab lorry removing rubble.

  • Chimney Demolition

    We have now demolished the chimney stack, which was the last of the demolition tasks! We looked at the structure of the cimney and it was obvoius that it was originally designed for open wood burning fires, but was later retrofitted for burning coal.



    The actuall demolition was quite easy using the mini-digger, as you can see from the movie.


  • More demolition of the remaining structures.

    Shaun has carried on his good work and demolished the outside loo and a old greenhouse.

  • Days 6 to 14 of House demolition Time Lapse movies

    Here are a few more days of timelapse movies for your delectation…