Category: Timelapse Movies

  • Work Continues on Construction of First Floor and Its Floorboards

    We resume the week by collecting up the sand we had spread across the kitchen to dry and sieved it through the finest mesh we had and lugged up six trug full of fine sand, to pour into our sand box surrounding the air duct pipe coming out of the Entertainment room. We estimated the amount almost exactly correctly .. Wow!

    Work Continues on Construction of First Floor and Its Floorboards

    Box-full-of-sand


    Then filled in the space between the joists with 200mm thick glass wool, we did this now because we won’t be able to access this space after the floorboard goes on. The glass wool is there to provide some additional sound dampening effect between downstairs and upstairs.
    Work Continues on Construction of First Floor and Its Floorboards

    Sound-insulation-over-entertaiment-room


    After that, we had one more little job to do, that is to test for water leaks in the new sewage pipework running through the joists and we fitted our adjustable bung to the bottom of the stack at a convenience T-junction to block the pipe against the water. We started filling the pipework up using the garden hose but suddenly the rubber bung lost its grip and flew down the pipe and splash water all over the place! But fortunately, we had tied a piece of string to the winding wing nut mechanism of the bung and it stopped it from completely disappearing deep down in our sewage pipes. But unfortunately, we couldn’t reach it by hand and pulling the string didn’t work either so we had to cut into the vertical stack to dismantle the T-junction piece which allowed us a better access. After rescuing the bung, we reapplied the bung but this time, much higher up at the top of the stack and poured in the water .. and after all that, we had no leaks! We put in a new piece of 110mm pipe to replace the one removed and using a inline slip connector, we got everything back together again. That was a unwanted diversion! Phew!
    Then we drilled hole through some joists and installed a waste pipe from Workshop 3 to the bathroom.
    Work Continues on Construction of First Floor and Its Floorboards

    First-floor-wate-pipes


    Oh yes, we glued and screwed down a restraint bar between the middle pair of the steel Skylight legs as required by the structural calculations and instructions. It is a 5mm thick metal bar, 50mm wide and 2.4metres long and it is bolted to the steel legs on sticking out tabs that we welded on the legs years ago which we had designed to line up to the surface of the floorboards and hey presto .. there was only a 3mm or 4mm alignment error! The floorboards were slightly too high so we just put in a couple of steel washers on the bolts and everything came nicely together.
    At last, we could resume laying down the tongue and groove chipboard and we proceeded by continuing around the stair hole where we got to last week and completed a dozen more rows, making several adjustments to clear obstacles like air ducts, steel skylight legs and arrive at the next major transition point in the house design.
    For safety reasons, as soon as we done around the stair hole, we screwed down a ring of CLS timber and mounted a hand rail to protect us from falling down the open gap in our floor.
    Plus also, we installed the second restraint bar between the third pair of the skylight legs like before.
    The last section of the first floor, situated over Bedroom 3 and Utility rooms, had a line of noggings put down the middle to do the usual job of stiffening up the wobbly joists and then we proceeded to finish off all the remaining floorboards.
    The next job was to install the four restraint bars around the thick skylight leg that is holding up the far end of the Skylight, the structural calculations requires this leg to be restrained too so we put on the prepared metal strips in the four ordinal compass directions, with the longest one pointing towards the external wall. These were again glued and screwed to the floorboards and bolted to the steel leg itself.
    The final task of the day, and of the week, was to tidy up everything off the flooring, all the tools, cut off pieces etc and sweep all the sawdust and glue fragments too.
    Work Continues on Construction of First Floor and Its Floorboards

    The-complete-first-floor-1

    Work Continues on Construction of First Floor and Its Floorboards

    The-complete-first-floor-2

    Work Continues on Construction of First Floor and Its Floorboards

    The-complete-first-floor-3

    Work Continues on Construction of First Floor and Its Floorboards

    The-complete-first-floor-4

    Work Continues on Construction of First Floor and Its Floorboards

    The-complete-first-floor-5



    Work Continues on Construction of First Floor and Its Floorboards

    The-complete-first-floor-6

    Work Continues on Construction of First Floor and Its Floorboards

    The-complete-first-floor-7

    Work Continues on Construction of First Floor and Its Floorboards

    The-complete-first-floor-8

    Work Continues on Construction of First Floor and Its Floorboards

    The-complete-first-floor-9

    Work Continues on Construction of First Floor and Its Floorboards

    The-complete-first-floor-10



    This concludes the construction of the First Floor, its joists and its floorboards. We have about 19 sheets left from our original 150 sheets we ordered. We didn’t have much in the way of cut-offs as we managed to re-use many pieces again. We are planning to use these 18mm thick chipboard material to make our return air ducting channels that goes around the edge of the house on our freshly laid first floor, but that is for later on.

    and for your enjoyment the whole month in a few minutes…

    Next is to install the glass wool into the walls downstairs and put on the vapour barrier membrane and that will clear away the pile of glass wool rolls, at which point, we can build the staircase, if we can get hold of some nice quality plywood material to make the steps and risers. There is a world wide shortage of this kind of wooden material due to the Covid and high demands in USA! Phew!

  • Fiddly Hidden Elements Completed in First Floor Joist Space

    This week was a chop and change kind of week, working on lots of different elements that needed to be done before we can continue in laying down the floorboards across the first floor joists. One of the last remaining tasks from last week was to glue and and nail the final four long I-Beams into place (these are going down the long hallway from the central part of the house and heading rightwards to the Utility and Bedroom 3 rooms) and put in the noggings to secure them at the ends. Talking about noggings, we looked at the structure of the first floor and counted how many more noggings we would need which came to some where around of figure of 60 individuals. We had 16 still left over from the last grand nogging creation so we sliced up three I-Beam left-overs, about 3metres each and then sliced up one complete 10metre I-Beam, to generate additional 44 noggings.
    With this done, our slicing machine have mostly finished all the bulk work so we dismantled the working area under our Front Door Porch, tidied away all the equipment and moved the slicing machine into Bedroom 1 for any odd jobs. Then we moved the final two 10metre I-Beams over to our Swimming Lane storage area for the long term (we will find something for them we have no doubts!!), folded up the tarpaulin, moved twelve concrete blocks and tidied away the wooden bearers. The front of our house is all clear again – hurray – Smile!

    So having done that, we could resume laying down floorboards but only a couple of rows. It took us almost an entire afternoon just to do one row, because it was the transition of entering into the larger space plus also there was two metal legs of the Skylight to navigate around too and we reached the next challenge. This is where we needed to install additional hidden elements that lives inside the joist space as follows ..
    The Cold Water Header tank Support lintel being the first one, we had made provisions during the construction of the walls by putting triple posts in the location where the ends of the steel lintel will sit so we just needed to hoist up the steel lintel. This steel object is another one of our left-over piece, this time, it is a 2.1metre large fat steel leg measuring 160mm wide by 80mm thick. These steel elements are supporting the Skylight hanging over the Great Room and we got three of them lying around in the Garage so it is ideal to be used as a lintel to support the large header tank and transfer the weight down directly to the concrete floor and not into the first floor structure. It weighed about 60kg so it took a bit of lifting from both of us to haul it up to the first floor. We then chopped eight pieces from a 2by6 timber to form short stumpy legs to lift the steel tube up so it is flush with the tops of the joists and the floorboards when it finally get laid. These stumpy support posts were 160mm tall and after slicing tiny bits off to get everything level, we glued the two set of four to form the two pillars and we stuck down the freshly scrubbed steel lintel into place. Finally, then we put small pieces of noggings down on either sides of the steel to make sure it is locked into place and won’t fall over or twist under the load of the header tank.

    Fiddly Hidden Elements Completed in First Floor Joist Space

    Water-tank-support-supports

    Fiddly Hidden Elements Completed in First Floor Joist Space

    Water-tank-support-all-level

    Fiddly Hidden Elements Completed in First Floor Joist Space

    Water-tank-support-installed



    The next job was to connect a waste water pipe that we will need for the upstairs bathroom’s basin and shower. But we discovered that the boss adapter we had already previously connected together into the large diameter waste pipework was a different size hole and we didn’t have any fittings that would fit reliably. It looked like a 50mm diameter boss socket but it was a case of a different manufacturer and their idea of what standards to adhere to. We tried all sorts of different solutions, rubber adapters and the like but O Boy we failed to get anything to work. So we had to block off the hole by making a circular disc of plastic and use PU sealant to stick this disc into the boss connector and seal it up. We fortunately had the luck to use another pipework piece, a right angle element that had more of these boss connectors but manufactured by someone else so we moved over to use that one instead. we had a particular adapter that fitted very well so we solvent welded the 40mm water pipe diameter adapter into the boss socket, after we had drilled a 40mm hole and then slide in a two and a half metre length of white pipe, ready for further connections to the basin and shower units later on.
    Fiddly Hidden Elements Completed in First Floor Joist Space

    Plugged-up-waste-boss

    Fiddly Hidden Elements Completed in First Floor Joist Space

    Watepipe-for-shower-and-basin



    After all that palaver, we moved over to the front of the house over the Entertainment room to design and build a air ducting channel that fits in between two joists so it can run underneath the upstairs Study room. This air channel is the waste air being collected by all the ground floor rooms at the front of the house like the Kitchen, Entertainment room and the Great Room and the Conservatory too. Normally, our waste air ducting will run on top of the floorboards on the first floor running around inside the triangular void spaces but we didn’t want to have to introduce four sharp bends in the air flow to just avoid crossing the upstairs Study and also have a permanent square boxing running around this room too. So, we routed the air ducting downwards to squeeze in between two joists for a short distance before rising again and heading off to the Utility Room for processing. We used a mixture of 30mm and 35mm thick PU foam boards that has the shiny aluminium paper coated all over them. It is quite smooth so will provide very low air resistance and it has two gentle slopes to avoid the sudden change of direction. The pieces were hooked and glued into place to create a square channel. The rest of it will be done later on when we build the remaining waste air channels.
    Fiddly Hidden Elements Completed in First Floor Joist Space

    Air-duct-over-entertainment-room

    Fiddly Hidden Elements Completed in First Floor Joist Space

    Air-duct-inside



    The final piece of work that we needed to do before the floorboards were laid, cutting off our access to this joist space (because the Entertainment room has the concrete ceiling, cutting off access from below. This was to install the air extraction pipework for the aforementioned Entertainment room. All the extraction pipework will be 100mm metal ducting with metal sweep corner pieces etc. and we connected together one 90degree bend to a short straight piece, then a 45degree bend to raise the ducting above the floorboard and left a short length sticking out. All this is done inside the space between the joists that lined up with the hole we left behind in the concrete block ceiling but we didn’t leave it at that point. We wanted to make sure that any sound waves being generated inside the Entertainment room were dampened and not leak out through the air ducting pipework and infect the Study sitting over the top. To this goal, we built a box out of left over pieces of chipboard floorboard pieces and glued this box down to the concrete surface and laid the metal pipe along inside and glued this in too.
    Fiddly Hidden Elements Completed in First Floor Joist Space

    Sound-resistant-box-for-entertainment-room-duct-installed

    Fiddly Hidden Elements Completed in First Floor Joist Space

    Sound-resistant-box-for-entertainment-room-glued-in



    We will fill this box up with sand but it needed to be dry first so we filled three trugs full of sand from our sand bank outside our conservatory and spread it all over the kitchen floor to dry off, blowing our giant fan over the top to assist this process.
    Fiddly Hidden Elements Completed in First Floor Joist Space

    Drying-sand


    One of the last things we were doing towards the end of the week, was putting more noggings across various collections of joists, some over the Entertainment room, some over Bedroom 3, some over hallway outside the Cloakroom, all to anchor the first floor support joists and stiffen them up.
    By the end of the week, we had done lots of different “little” tasks, had only put down two more rows of floorboards but that building a house for you. There are certain jobs that depends on the completion of other jobs. it is very important to do each one in order .. or else!
    Here is a picture of our first floor with all the piles of chipboard boards waiting, a table of tools and working area.
    Fiddly Hidden Elements Completed in First Floor Joist Space

    First-floor-end-of-week-3-1

    Fiddly Hidden Elements Completed in First Floor Joist Space

    First-floor-end-of-week-3-2

    Fiddly Hidden Elements Completed in First Floor Joist Space

    First-floor-end-of-week-3-3


     

    We resume on Monday with these little jobs!! Phew!

  • I-Beams Arrive!

    In the morning we prepared an area to store the beams next to the house.

    The lorry arrived at 1:25pm with the 66 special I-Beams on a open flatbed vehicle, in two packs covered in plastic. The driver thought he could reverse down our Loke and save a lot of effort but after attempting to come in both directions and failed to get enough room to straighten up. In fact, he couldn’t hear the shout to stop and unfortunately bumped into the garden wall of the house flanking the entrance to the Loke and knocked a section down. We excused the driver and we said that we would repair the wall ourselves (we confessed to the house owner who is a nice chap).
    So the lorry parked straight on the main road and we unloaded the I-Beams one by one off the back and placed them into the Loke to minimise the unloading time and then let the driver go off.
    It was 2:50pm at this point, so we had a half an hour rest plus to quench our thirst too!
    Resuming at 3:30pm, we got our trolley loaded up with 22 pieces and started down the Loke. But soon discovered that the dolly module was struggling to get over the little ramp and was creaking and wiggling alarmingly. We put on four more giant clamps to help stiffen up the load points and carefully got over the ramp.
    That was exactly a third of the total and it was clearly overloading things. So we reduced the quantity and put only 15 pieces for the next three trips. The ratchet straps were doing a good job of keeping everything tied down and stopping the load slipping.
    Once we got the load down to our place, we transferred it over to our temporary storage location just inside the fence (we released the wire mesh and rolled it up and pulled out two posts) and place each I-Beams into an ordered piles on two 2by6 planks supported by two concrete blocks.
    After unloading the final 15 I-Beams, we covered it all up with a fresh tarpaulin as the material they supplied was ripped rather badly during the unloading process.

    I-Beams Arrive!

    All-66-beams

    I-Beams Arrive!

    Beams-wrapped-up



    We finished everything at 7:30pm and we were knackered!!

  • Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    This week it is the turn of the Concrete Beams and hundreds more of the concrete blocks to be hoisted up and laid out to form the roof of the Entertainment Room’s internal sound proofing shell.
    The first job was to construct a lifting hoist location where each individual 120kg beam is lifted up and swung around, to get pass the skylight metal leg and lowered down to the top of the concrete wall.

    We got three of our shorter metal scaffolding modules, plugged them together and then clamped the whole thing to the wooden wall. Then we got our metal hoisting arm up (only just fitted, avoiding the skylight) and then attached the electric winch.

    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Setting-up-hoist

    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Hoisting-a-beam-up



    We first lifted two beams up and got them positioned over the far end of the room, near the window. This allowed us to then set and position the second of our heavy duty angle iron piece, with clearance holes drilled into it and then glued and screwed on to the wooden legs of the external wall.
    Then we sliced up one of our paving slabs down the middle to give us two similar pieces, 900mm long by 300mm wide, plus a small bit left-over from the previous time of using the paving slabs at the bottom of the window, to make a filling in piece measuring 240mm wide by 300mm deep. Then, we glued on half bricks on the edge of all three pieces so that they can sit on the concrete beam and form the lid over the window, sitting on the metal angle iron and the beam. We wanted to raise this “lid” higher to maximise the space above the window to ensure that we had enough room for our mechanism for controlling the automatic window blinds. We glued these composite pieces using regular PU glue to stick them into place.
    On Tuesday and Wednesday, we proceeded to lift up the remaining eight beams and 162 blocks, plus 5 further blocks sliced down the middle to form the finishing piece in each row.
    We used spray PU foam to act as a glue and space filling at the same time on each block as we inserted a block along the beam. Not forgetting the two driveway 50mm thick concrete bricks were placed at the start and end of each beam to fill in the gap between them sitting on the wall.
    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Gluing-blocks-in-with-foam


    The last day, Thursday, we had to fill in the tenth row which was half the width so we sliced nine blocks in half to produce a filling in piece, measuring in a set between 190mm to 200mm wide and also cutting down two more bricks to fill in the final space on the wall.
    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-All-blocks-installed


    We had a half bag of cement powder left over so adding two buckets of soft sand, we mixed them together in a dry form, ready to vibrate in all the joints on the roof. But first, we nicked a quarter of it to make the normal mortar “muck” to stick down the last row of half blocks to the top of the wall and finishing off the whole roof.
    Then we proceeded to pour the dry mix all over the roof, brushing it over all the joints, banging and vibrating the roof using a piece of wood and club hammer and filled up the cracks between the blocks and beams. Finally, we went over the roof surface and sprayed a small quantity of water to help activate the cement and harden it up.
    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Grouting-the-blocks

    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Blocks-grouted


    The rest of Thursday and much of Friday was spent tidying up all the equipment, taking down the winch motor and its metal lifting arm, sweeping the floor and creating a “rubbish” bag down the bottom of the garden (using one of those large ton bags and four old metal re-bars to act as legs) and moved all the broken and sliced concrete block remainders, dismantle the various wooden templates and finally moved the cement mixer away from the Front door area.
    One thought that came up, was to get the ceiling battens installed now, rather than later on because we might forget to do it before we put up the First Floor Joists, which may impede our attempts in screwing up the CLS 63mm battens up inside the Entertainment Room. So Saturday was spent in doing that to get it all done and dusted before we forget and before we dismantled the wooden platforms too. We drilled six holes through each row of the concrete blocks (they are 6mm holes), just alongside each concrete beams, a total of 60 holes for the 150mm long screws to go through and grip the CLS plank of timber.

    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Roof-sprouts-screws


    We used 3.6 meter long 63mm sized pieces because they very nicely brought the surface of the ceiling just clear of the concrete beams, which makes it very easy to then screw and glue up the ceiling boards later on. We then screwed the wood up leaving a gap which we sprayed PU foam glue into, after which we tightened the wood up squashing the foam tight.
    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Ceiling-support-battens-

    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Ceiling-support-battens-glued


    So in just over three weeks, we constructed a complete concrete shell from start to finish! Not Bad! And it took only a little bit longer to build the wooden framework that surrounds the whole room. Very nice to see that all complete.
    The next job is to start bedding down the footplate (double layer of treated CLS planks) that makes up rest of the rooms onto the concrete floor.

  • Twelve Triple Glazing Units Arrives and All Are Installed

    Very very early Friday, with all the alarms waking everyone, we staggered up to get ready for the arrival of the glass which could arrive as early as 8am!
    What we are expecting is as follows:

    • Nine large units, each weighing 118kg
    • Two medium units weighing 75kg
    • One slightly smaller one weighing 65kg.

    We had our troupe here by 8am or soon after, under a very heavy cloudy sky and swirling winds. We passed the time having a much needed hot drink and fortunately, it wasn’t too long to wait. The van arrived at 8:47am.

    Twelve Triple Glazing Units Arrives and All Are Installed

    The-Glass-arrives

    Twelve Triple Glazing Units Arrives and All Are Installed

    12-Triple-glazing-units-waiting-to-be-unloaded

    Twelve Triple Glazing Units Arrives and All Are Installed

    The-edge-of-a-Triple-glazing-unit



    We carefully unloaded each unit, using four suction pad handles and transported each one on the adapted trolley to near each window position around the house. We put the glass on a narrow piece of polystyrene sheet to both protect the edge of the glass and keep it clean from the damp sandy soil.
    Twelve Triple Glazing Units Arrives and All Are Installed

    Preparing-to-lift-a-unit-off-the-van

    Twelve Triple Glazing Units Arrives and All Are Installed

    Moving-the-heavy-glass

    Twelve Triple Glazing Units Arrives and All Are Installed

    Unit-ready-to-install



    It took us 50 minutes to complete this task of moving well over 1.2 tons of glass. We had a much needed cup of tea and a slice of cake before resuming work!!

     

    Then this is the big moment, will the glass fit?
    And yes of course it did!
    All of them!
    We proceeded around the house, with one person inside taking off the wax protection paper off the sticky tape and four lifting up the glazing unit up and slotting it into the framework and then screwing several plastic beading clips against the glass to secure it into place.

    Twelve Triple Glazing Units Arrives and All Are Installed

    Holding-unit-whilst-tape-is-uncovered

    Twelve Triple Glazing Units Arrives and All Are Installed

    Glazing-clip-being-installed

    Twelve Triple Glazing Units Arrives and All Are Installed

    Glazing-clip-installed



    We started this process at 10:30am and got the last one done at 12:30pm.

    We all had another much needed break to recover and enjoy lunch!!
    So that concludes the installation of the Triple Glazing units, all Twelve of them! This makes us pretty much weather proof! Yahoo!
    The final step to do next week, is to fix well over 300 of these plastic beading clips, cut the oak beading strips to length, mitre the corners, add the rubber seals and slide them onto the plastic clips. After that, we need to finish off doing the oak “wings” that covers up the ends of the larch cladding on either sides of each window. At this point we will be finished Phase 4 (The exterior of the house)!

    Twelve Triple Glazing Units Arrives and All Are Installed

    Windows

    Twelve Triple Glazing Units Arrives and All Are Installed

    Reflections


  • M Section All Done and N Half Way There

    On Monday, we resumed work on the M section of the roof. The first job was to cut, trim and seal the fibre-glass trough module to fit the top of the valley and while the resin was curing, put up more slates. After lunch, the modified third piece of the valley trough was fitted and we then finished off the small triangular patch to complete the whole of the M section. This piece of roof has over 1800 slates on it. this now means we have covered approximately 30% of the whole roof.

    M-Complete

    M-Complete


    For the final couple of hours left on Monday, we swapped our tools over to begin nailing up the tile battens up on the next section, the N part.
    N-partial-battening

    N-partial-battening


    Tuesday saw the completion of the tile battens nailed into place and then we started on putting on the slates.
    But we spotted something very odd in our gutters.
    N-Gutter-Bulging-rubber

    N-Gutter-Bulging-rubber


    The rubber liner had “swollen” up in a bubble and when we had lifted up the metal mesh, realised that it was water underneath the rubber membrane, sitting on the oak. We had never noticed it before and we had to wonder where and how the water got into and behind all the layers of the breathable membrane up on the roof. Did this mean a hole somewhere? Did this mean a sealed joint wasn’t holding? Well, we got the vacuum cleaner out to sucked out the water and made sure that no more was lurking elsewhere.
    Then we got out our garden hose and emulated a very heavy rain shower by spraying water from the top of the ridge line and all the way down the hip, to make sure that all the breathable membrane was fully covered in running water. We then waited over lunch for any developments.
    After lunch, the verdict was no signs of any more water bubbling up behind the rubber. We can only put down this experience to a moment when we was putting up the membrane in the first place several weeks ago (by reviewing our photo gallery) and there is a possibility that one night, there was a short sharp shower and managed to allow a small amount (about 100millilitres) of rain water to slip behind the top line of membrane up the top of the roof, where the ridge line wasn’t covered until the following day.

    We will have to keep an eye on this but nothing materialised during our water test and beside, as soon as we have put on all the slates, it will be fully waterproof anyway.
    We put back the metal mesh over the gutters again and resumed the job of putting on the slates, starting at the valley end and working up the diagonal. We have also learnt our lesson about providing a fixed reference marks for the left end of all the rows by projecting up a vertical line and then measuring back from this one reference line, to all the starting points on the left end of each tile batten.
    N-slating-started

    N-slating-started

    Wednesday and Thursday were taken up with Stephen’s Birthday and meetings but on Friday we got back to putting up more slates and continuing up the valley.

    N-Slating-valley-slated

    N-Slating-valley-slated


    We managed to get the complicated valley all done and covered most of the N section with slates by Saturday afternoon. We had to stop because we ran out of room and we couldn’t get up and over on to the N section to complete the last few rows.
    N-Mostly-slated

    N-Mostly-slated


    So for the remaining of the afternoon, we got on with the task of putting the rubber liner inside the gutter on the next section, the “O” section, and put up one central counter batten. This central batten was special because we couldn’t just nail it into place as the underlining structure, at this particular point, has a thick steel plate that reinforces the rafters. This means that nails straight down cannot penetrate into the rafter and secure the counter batten into place. instead, we used glue plus nails and positioned the batten slightly offset to one side. We fired extra-long nails at a slanting angle to hit and grip wooden rafter, bypassing the steel plate on the front of the rafter.
    O-gutter-lined

    O-gutter-lined


    Next week, we will put up the breathable membrane, secured down by more vertical counter battens and then put all the horizontal tile battens right across the O section and we can climb this to complete the N roof, and also put another 500 slates on the O roof.

    And here’s this week time lapse…

  • Starting on M Section

    Today, at the start of a new week, under a wet cloudy chilly sky, we finished putting up the tile battens on the M section of the roof, all before lunch time.

    Battens-complete-on-M-1

    Battens-complete-on-M-1

    Battens-complete-on-M-2

    Battens-complete-on-M-2



    After lunch, we started putting up the slates, going up the valley and in the three or so hours of the afternoon, we managed 32 rows with two or three slates in each. It is a slow job measuring and fitting the slate into the angled valley, we got a good way up with about 19 rows to go.
    First-few-slates-on-M-End-day-6

    First-few-slates-on-M-End-day-6


    Tuesday saw the installation of the kerb flashing along the Skylight, made up of a strip of rubber and a line of aluminium strips in front, both mounted on wooden short batten pieces spaced out every 500mm (see 1:29 in video).

    Then in the later part of the afternoon, we finished off the valley rows and also finally, fitted the last couple of slates over on the I roof and the final ridge flashing slate along the J roof.

    Left-Valley-completed-End-day-7

    Left-Valley-completed-End-day-7


    All day Wednesday and Thursday morning was a complete wash out in terms of working on the roof but we did instead do some analysis of the task in doing the windows (see Sorting Oak Timber for Windows) so wasn’t a complete waste of time.
    Thursday afternoon, we resumed work on the roof and finished off the complex intersection of the K ridge line meeting with the valley coming up the L and M section of the roof. After that, we were able to mount approximately 300 slates in just two hours to conclude the day’s work. That was fast work!
    Progressing-across-M-End-day-8

    Progressing-across-M-End-day-8


    Friday also had some rain interruptions and we lost a couple of hours in the afternoon. But we still managed to get a further 500 slates up on the M roof, we are well started up the other valley (the M-N valley) now but probably still have another 800 slates to go to finish this roof section.
    Starting-up-Right-Valley-End-day-9

    Starting-up-Right-Valley-End-day-9


    On our final day Saturday, we continued putting up more slates, working up the valley, with shorter and shorter strips and in total we did about another 500 slates. There is just a fairly small triangle patch of roof left to do.
    Nearly-finished-M-End-day-10

    Nearly-finished-M-End-day-10


    But we did have a short pause where we had to analyse why the position of one row of slates was slightly off (you will see the moment in the video below) and this is the first time it has happened. We concluded that the beginning of the horizontal row was not started in the correct position, we realised that there was too much of a risk of drifting whenever we start a new row on the left end. The lesson learnt today will help set up the next section of roof properly and mark the starting point on the left ends of each row from a known reference vertical line in the middle of a roof section.
    In conclusion for this week’s work, we could have done the whole of the M roof section if we had not had the rain interruptions on Wednesday, Thursday and Friday.
    Now enjoy the video of us dashing about on the roof!

  • Video Footage of the Entire Job of Covering Our Roof With Plywood Boards!

    Here is a video of our roof being covered up with 12mm thick plywood sheets, starting on the “A” roof section and going around anti-clockwise and finishing on the “P”, right back at the starting point.

    We spent a total of 21 days in total (this includes two half days), so about 42 man-days of work (about 180 man-hours), in the whole month of July. The video has been speeded up 600x times faster and it is only 4½ minutes long to watch the whole roof being magically covered up!

  • Roof “Q” Is Completed and “P” Nearly There!

    We had a slow start today as we had a series of short sharp thunderstorms and showers with a twirling strong breeze so didn’t get going until about 11am. We did as much as we could on the “P” section of the roof on this side of the “Q” roof (the section facing backwards towards the Swimming Lane) and then moved the mobile platform tower along to the very front of the building and we carried on the other side of the “Q” (the Conservatory) and did the first row of with the posh plywood on the smaller last section of the “P” roof. And finally, we installed the three rows to cover the second half of the “Q” section. It is a bit more tricky as there isn’t a lot of room to work in.

    Roof-boarding-Day-20-Continuing-P-Q

    Roof-boarding-Day-20-Continuing-P-Q

    Roof-boarding-Day-20-Continuing-P-Q

    Roof-boarding-Day-20-Continuing-P-Q



    So on Monday, we should get the rest of the “P” roof done and that will be definitely that! Not Bad at all!

  • Progressing Along the Back of the House!

    Today, with it being just slightly cooler than yesterday, we started working on covering the roof along the back of the house. We decided that because we could access any part of the roof along our walkway, then we did several complete jobs in one go, for example, we went along to drill conduit holes through each and every rafters including the outside corners. Then we planed off excess timber that were too high above the Fascia board and filled in any gaps to bring it up to the Fascia board level. Finally, each rafter was touch with the planer to make sure there was no sticking up edges where the plywood webbing was stuck on too high. Also the brown glue was cleared away on the joint between the rafter and the Fascia board (got to the middle of the “M” section).
    All these steps took the morning but now we can get on with gluing and nailing the plywood boards up with out having to remember to do any of these preparation steps. The back of the house is the sections from “I” through to “O”.
    In the afternoon, we got on with fitting on the plywood sheets, cutting the angled ends to match the Hip or Valley joins, reusing left-over pieces where possible and we managed to get the first row (these being the Posh boards) done for “I”, “J”, “K”, and “L”.

    Progressing Along the Back of the House!

    Roof-boarding-Day-11-First-row-on-I-J

    Progressing Along the Back of the House!

    Roof-boarding-Day-11-First-row-on-K-L



    Only three more smaller sections, being “M”, “N” and “O” sections to finish and then we can start working back on “I” with the ordinary grade plywood and cover up the whole section before moving onto the next roof area.