We resumed the work of covering our roof with plywood boards and we got the last complex rhomboid shape made and fitted up to finish off the “G” roof segment. Then, carried onto the “H” roof section and put up another six sheets of plywood, half of them had angled cuts on the end to fit into the valley. Working on this roof section, is just that little bit more tricky as the angle of the slope is 40° and our boots doesn’t quite have enough grip by themselves so we are having to put up double number of “foot-rails” to support us and keep us safe!!

Roof-boarding-Day-9-G-done-and-H-Started


Tomorrow, we should see the “H” finished off and we can then start working along the back of the house and using our fixed working platforms too.

By Shaun