Blog

  • Concrete End Cap Poured

    Today, we sealed the end of the gap between the swimming lane’s back wall
    and the fence, by pouring in concrete into a mould. This End Cap was
    necessary because the return channel needed to be built on a concrete
    foundation which in turn sits on the hardcore / soil but near the garage end
    of the swimming lane, there is going to be a filtration unit to “clean” up
    the rain water and the soil would have leaked out from under the foundation
    over time, so we capped it off.

    End-Cap-1

    End-Cap-1

    End-Cap-3

    End-Cap-3

    End-Cap-2

    End-Cap-2

    End-Cap-Finished

    End-Cap-Finished


    It took 3 bags of cement to produce 200 litres of concrete to make a 150mm
    thick wall from the bottom of the mass wall and swimming lane wall and the
    gravel board of the fence, some 1450mm high and 600mm wide, with a slight L
    shaped extension to the mass wall (this runs along and under the fence and
    right across the back of the garage).

    It will make a neat vertical wall, flush with the end of the swimming lane
    and allow us to control what we want to install in that location without
    worrying about the motions of rain soaked mud!!

  • Sixth Row is Complete!

    The back wall is now completed with the 6th row of blocks laid today. we had
    to do another 31 blocks to finish it off and 1 around the corner on the end
    wall.

    We continued along the front of the swimming lane to start the 1st row and
    we did 12 blocks. It took longer to do those as we were being careful and
    getting them level and at the right height so that the subsequence rows on
    top come out neat and tidy.

    Back-Wall-Complete

    Back-Wall-Complete

    Start-of-Front-Wall

    Start-of-Front-Wall


    The back wall is done for now until the soil behind the wall has settled
    down and compacted with future rain falls. It is likely to be several years
    before we get back to doing the next task, the return channel feature of
    the swimming lane.

    The back wall is now doing the job of holding back the soil and water from
    the higher grounds of our neighbours and we can hopefully forget about that
    issue for now.

  • The Shored Up Soil is Released

    Today, after a couple of weeks delay while we waited for the concrete in the
    back “retaining” wall, to cure and gain proficient strength, we released the
    shored up soil of the land stretching across to our neighbours (the workshop
    and a row of houses).

    We inserted a sheet of DPM plastic to minimise the chances of wet dirty soil
    from getting through our back wall and creating problems in the future,
    hidden behind the fibre glass resin coating.

    All the diagonal struts were proven to done a good job, because as we
    removed them, the boards and posts leaned over under the weight of the soil
    behind them. But we had mostly filled the gap between the concrete wall and
    the OSB boards so the whole thing wouldn’t suddenly collapse and potentially
    disturb the neighbour’s fence posts and panels!!

    But we had problems removing the OSB sheets as they were too firmly held in.
    We tried pulling them out using the mini-digger and rope, but the rope
    sliced it way through the OSB! Wow! So we decided to leave them there as
    mementoes and for ‘Timeteam’ to discover in some future archaeological dig!

    Dpm-in-Place-and-Mostly-Filled-e1461138200943

    Dpm-in-Place-and-Mostly-Filled-e1461138200943

    Now we can finish off the 6th row and put on an end cap at the mass wall to
    retain the soil from spilling out near the garage.

  • The Tubes are all done!

    WOW! We finished it all today, even though we started much later at 11:30am
    (due to having had an appointment in the morning). We did 38 columns using
    9½ bags of cement!

    We changed our jobs around so I could do the making and mixing the concrete
    and Stephen took the wheelbarrows loaded with the concrete over and up to
    the wall to pour in and vibrated each column down firmly. It was much more
    efficient!! But Oh Boy .. We Are Knackered!!

  • Another 33 Columns filled!

    Today, another 33 columns were filled!!

    We decided that it would make sense to split the mixing load in half and do
    only a half a bag of cement and 3 buckets of ballast. It works so much
    better this way that we hardly need to fiddle with the cement mixer, just
    put in 6 litres of water, half a bag of cement, mix this up for a second or
    so, and then chuck in the 3 buckets of ballast .. and that’s it!! it is
    virtually mixed all together as soon as the last bucket goes in. We do add a
    quick spray of water to loosen the mixture up a bit and it then pours out of
    the barrows and straight into the hollow columns.

    So today, the columns were 6 blocks high, hence why we did only (huh!) 33
    for the 9 bags, whereas yesterday we did 31 columns for 8 bags. But
    yesterday, we were doing just 5 blocks high columns!! That makes it a rate
    of three and two thirds columns per bag today, against three and seven
    eighths columns per bag yesterday, if you are interested in the maths!

    Saturday-33-Columns-Filled-1

    Saturday-33-Columns-Filled-1

    Saturday-33-Columns-Filled-2

    Saturday-33-Columns-Filled-2


  • 31 Columns Filled in Back Wall

    Today, we managed to fill a further 31 hollow columns in our retaining back
    wall. This is 8 bags of cement, mixing each bag with 6 builders bucket of
    ballast.

    We found that putting in slightly more water in the mix, helps with the
    pouring the concrete down into the hole and the vibrator thingy is very good
    at knocking down the mixture. Very glad to have bought one off the web!

    Friday-28-x-5-Block-Columns-Filled-2

    Friday-28-x-5-Block-Columns-Filled-2

    Friday-28-x-5-Block-Columns-Filled-1

    Friday-28-x-5-Block-Columns-Filled-1

    Friday-4-x-6-Block-Columns-Filled

    Friday-4-x-6-Block-Columns-Filled


    We found that putting the water in first and 1 bucket of ballast, mixed up
    before then adding the bag of cement. This creates a very wet and slurry
    mixture to help distribute throughout the further 5 buckets we then put in
    all at once and while the machine is stopped. Cannot add them while it is
    going because the slurry will get pushed out of the drum!! We are using
    about 12litres of water to bring up the resultant concrete to a good
    “flowing” consistency.

    So in summary, the concrete we are making is:
    1 bag of cement
    12 litres of water
    6 large builders bucket (3 gallon / 13.5 litre capacity) of a mixture of
    small stones crushed up to pea sized (10mm) and sharp sand.

  • Concrete Vibrator

    We use for the first time, our new tool! It is a vibrator to help settle the
    concrete down and knock out any pockets of air. It is very noisy but really
    does the job!

  • Concrete Filling Begins on Back Wall

    This afternoon, we began the task of filling up 101 hollow columns in the
    back wall of the retaining wall of the swimming lane.

    We got things organised and place the newly created platforms and ramp in
    place to take up the wheelbarrow loads of concrete.

    We are using pea sized ballast to get the concrete to wiggle down the tight columns that has a reinforcing rod up the middle as well as layers of horizontal steel rods every two layers of blockwork.

    The vibrator machine is very good for knocking the pocket air out and make
    sure we got a solidly packed column of good quality concrete.

    We filled nearly 2 columns, learning how to get the mixture up and tilted
    into the tops of the blocks, how long to mix the concrete (3 large builders
    buckets of ballast, about 40litres, against a smaller bucket of cement,
    about 8.5 litres, to make a half load in the mixer plus about 6 litres of
    water)

    Tomorrow, we can really get a routine going with 4 wheelbarrows to take the
    load of a completely full mixer (a whole bag of cement and 6 buckets), run
    them up and emptied into four columns and repeat. We can hope to do about 15
    columns per hour, so about 6 or 7 hours to do the 101 columns in total.

    First-Two-Columns-Filled

    First-Two-Columns-Filled

  • Mini Trolley Met Big Bad Truck!

    OOPS! The dumper truck has just ran over our poor little platform trolley!

    We were reversing the truck to gain room and straighten up, in order to move
    the load of concrete blocks that has been sitting in the skip for the last
    few days.

    We had been using the mini trolley to transport a few blocks at a time
    because the dumper truck’s starter button wasn’t working (see (see Dumper Truck Repaired) and we parked the trolley back
    over near the concrete blocks behind the truck!!

    Run-Over-Trolley-3

    Run-Over-Trolley-3

    Run-Over-Trolley-1

    Run-Over-Trolley-1

    Run-Over-Trolley-2

    Run-Over-Trolley-2


    It was amazing that the dumper’s huge tyres didn’t really feel anything and
    actually rode over on top of the trolley and of course completely flatten
    it!! Three of the wheels are now rather bent, two of them completely broken
    off the trolley, but it seems that the basic framework is still in good
    shape (literally!) but we will see when we bring the poor thing into our
    garage for a closer inspection!

  • Platform and Ramp

    The platform and Ramp is now ready for helping us get the concrete into the
    “hollow tubes” in the wall.

    The ramp is 12 feet long as we found that having only 8 feet produced a “too
    steep” angle on the ramp while trying to push up two concrete blocks as
    samples of the kind of weight we will be struggling to get up!!

    It is much easier with the extra 4 foot extension!

    Ramp

    Ramp

    Modules-and-Ramp

    Modules-and-Ramp

    Tipping-Barrow-on-Platform

    Tipping-Barrow-on-Platform

    Barrow-going-up-Ramp

    Barrow-going-up-Ramp