Blog

  • Battery and Solar Charger Inspected and Fixed

    The battery was successfully charged up using the mains charger overnight.
    But when we tested the solar charger, we discovered that there was only
    4volts coming out! Oops!

    But after chasing down the wires and switches and relays, and not
    discovering what the problem was. There was a mysterious drain of 150mAfrom
    the battery and there wasn’t nothing wrong with the solar cell (it produced
    24V in the bright sunshine we were having).

    We slowly realised that an old keylock switch we don’t use any more, was in
    the “heating” position, for warming up the engine when it is freezing out
    there, and we suddenly remembered that we used the heater last week for that
    exact reason .. it was blooming cold!!

    But it seems that the switch was left in that position all this time – oh
    xxxx!!

    So the problem is now solved – because there wasn’t any in the first place!

  • Fourth Row is Coming

    This morning, we finished off the 3rd row (7 more blocks), and then started
    on the 4th row.

    The end wall had another set of reinforcing bars placed horizontally and
    then 3 more wide (215mm) blocks in a line, except that the last one near the
    front wall needed to be cut down because the front wall on the 4th layer and
    above are only using the 140mm wide blocks instead of the 215mm blocks.

    We got the diamond cutter disc and our angle grinder, to slice an end off a
    215mm standard block (we removed 75mm – the difference between 215mm and
    140mm!).

    Then We managed to do 14 blocks before we ran out of mortar. That is a total
    of 24 blocks this time!

    End-of-3rd-Row

    End-of-3rd-Row

    Start-of-4th-Row

    Start-of-4th-Row


  • Third Row almost complete

    We did two loads of the cement mixer today, one bag of cement in total. This
    allowed us to do a further 39 blocks. 20 this morning and 19 this afternoon.

    The steel bars lying horizontally in this row, does make it easy to lay each
    block down and just wiggle until it hits the two bars. It does means that we
    are using slightly more mortar for the joint as the bars are around 12mm
    thick, but we would normally do 10mm thick mortar joints, hence why we have
    only done 39 blocks today.

    Most-of-3rd-Row-1

    Most-of-3rd-Row-1

    Most-of-3rd-Row-2

    Most-of-3rd-Row-2


  • Suspect Problem with Battery

    We suspect that there is a problem with the dumper truck’s battery or the
    charging circuit from the solar panel. We got only 3 starts out of the
    battery today before it went flat.

    We put it on the mains powered charger and left it overnight.

  • 2nd Row Complete and 3rd started

    We got the 2nd row done today before lunch, having started at 9am this
    morning. That was 21½ blocks put down. We split one of the concrete blocks
    in half, the block was pre-made to allow for easy splitting and indeed it
    was!

    Then after lunch, we cut 1500mm reinforcing bars and bent 4 of them to start
    laying them on the end wall, and 2 long 6metres bars horizontally on the
    back wall.

    We built up the end wall and around the corner on the front wall, to build
    up the two layers, so those steel bars can be put on. We did 16 blocks until
    we ran out of mortar, by which time it was approaching 5pm. So we stopped
    then.

    It is looking good with the 3 layers on the end wall and progressing down
    the lane!

    Second-Row-Finished-1

    Second-Row-Finished-1

    Second-Row-Finished-2

    Second-Row-Finished-2

    Second-Row-Finished-3

    Second-Row-Finished-3

    End-Built-Up-3-Rows-2

    End-Built-Up-3-Rows-2

    End-Built-Up-3-Rows-3

    End-Built-Up-3-Rows-3


  • Another Half a Wall done

    We did only a half day of work today, as we had other commitments in the
    morning.

    On Monday, we tried mixing the mortar with 4litres and 50ml of Plasticiser
    but it was quite stiff so we had to add more water. Today, we did 4litres
    and 75ml of plasticiser and it seems to be much better this time!!

    We did 25 blocks. We found that our template for guiding and controlling the
    amount of mortar to put down on the blocks was slowing things down too much
    so we went back to putting a layer of mortar by hand and just used the
    template on the vertical joint to control the thickness. It worked out much
    better that way and we could get a controlled placement of the block and it
    didn’t run away with us!!

    Second-Row-Started-2

    Second-Row-Started-2

    Second-Row-Started-3

    Second-Row-Started-3

    Second-Row-Started-4

    Second-Row-Started-4

    Second-Row-Started-1

    Second-Row-Started-1


    It took us about 4 hours to do the 25 blocks this time, a full mixer load of
    mortar. So it looks like us doing one load in the morning and another one
    after lunch to do 50 blocks.

  • Made a mortar application tool.

    We have made a tool to speed up applying mortar to top of the block for the next row. This is slightly complicated in that there are only narrow rims on the blocks to put mortar on and large holes to fall into. An additional complication is the Re-bars running up the center of each hollow, so the tool had be open ended to allow use without having to lift over the top of every bar.

    The tool provides two slots a front and back to fill with mortar and trowel off level with the sides, this gives a fixed mortar bed of 12 mm. The spacers continue up the face of the previous block on the row to provide a per-pend joint.

    Home-made-mortar-application-Tool

    Home-made-mortar-application-Tool

    Mortar-Tool-On-blocks

    Mortar-Tool-On-blocks

    Mortar-Tool

    Mortar-Tool


  • Back Wall Has Started

    Date:21/02/2016 18:33

    We started building the back wall of the swimming lane today! We managed to
    do 43 blocks with 3 mixer loads of mortar before it got dark. Each row of
    the wall contains 50 blocks and we are doing 5 rows at this stage.

    It was quite difficult in keeping consistent with the mortar gap between the
    concrete blocks and not let it “run” ahead! We had to keep it down to 10mm
    or less because we got our steel rods going up through the hollow cores,
    meaning keeping the rods fairly clear of the edges of the blocks.

    And the other discovery we learnt, is the sloppiness of the mortar mix. Each
    concrete block are much heavier than house bricks so they press down with
    27kg of force, on their narrow edges, which means they squeezed out the
    mortar if it is too sloppy.

    We make a strong mortar mix using 1 bucket of sharp sand with 2 buckets of
    soft sand (a “Builder’s” bucket is about 13litres) which gives a total of
    40litres of sand, together with a 10litre bucket of cement (a complete 25kg
    bag fills just about 2 10litre buckets).

    Currently, we are working with 4litres of water (plus 100ml of plasticiser)
    and this produces a slightly sticky and sloppy mix which just about holds up
    the block.

    It takes a little while for our electric mixer to produce the “flop”
    consistency, and it seems that the plasticiser then starts creating
    microscopic air bubbles which makes the mix even more sloppy after another
    couple of minutes. We think we will reduce the plasticiser down to 50ml in
    our next mix.

    We will inspect our build in the morning to judge the quality of our current
    mortar mix!!

    Only 207 blocks to go!!

    First-42-Blocks-placed

    First-42-Blocks-placed

  • Concrete Blocks Moved and Ready

    We moved all the 120 concrete blocks over to the slab, spread out along the
    whole length (22.5metres), ready to build up 2 layers of the back wall, and
    the extras at the beginning, ready for the end section of the swimming lane,
    and the first few blocks on the front wall.

    We used our new purposed built trolley to move 10 blocks at a time, weighing
    in at least 250kg in total, pushing and pulling the load over the slightly
    soggy ground (we had a recent rain fall!) and rather bumpy at times too.
    Hard Work!

    First-two-rows-opf-blocks-ready-for-building

    First-two-rows-opf-blocks-ready-for-building

  • Removed remaining Foundation shuttering

    We also removed the shuttering framework that was wrapping around the
    foundation slab. The 89mm CLS timber, all 10 lengths of them, are now piled
    up on the side, ready for the next shuttering job of the main house’s
    foundations.