Blog

  • Snow Stops Play!

    We woke up to a thin layer of snow on some of the raised objects (off the wet ground) where it didn’t melt. The temperature is hovering around the freezing point, which is not good for concrete. So we wait for the warmer spell that is supposed to be coming soon!

    Snowy-Ballast

    Snowy-Ballast

  • High Platforms x 4

    This afternoon, we built 4 wooden platforms to help with the next stage of
    pouring concrete down the hollow columns in the ball wall of the swimming
    lane.

    In order to make them as mobile as possible and also fit into the gap
    between the diagonal struts, we made them 450mm by 550mm oblong modules so
    they can be joined together in different arrangements.

    They are 1330mm high (4 feet 4 inches) to reach the top of the 6 rows of the
    concrete blocks.

    We will use a 8 foot long ramp, or maybe a 12 foot long one, depending on
    where the position is and how much soil there is heaped up near the swimming
    lane.

    We probably keep these platforms for other jobs in the main house when we
    need to get up high somewhere.

    Tall-Platform-Modules

    Tall-Platform-Modules

  • Starter Button Fixed!

    The truck now starts! We have Noise and Action again!

    The wire had corroded and come off the connector to the starter button
    circuit. We conclude that there is enough conduction when rain gets in, with
    the 12V and the differences of the metals (copper wire soldered (lead and
    tin) onto a brass spade terminal connector), to allow the copper to
    “oxidise” and turn into dust.

    We had already started coating other joints with the plumber’s LSX to
    provide a waterproof protection, but this one was an old joint and we had
    missed it!

  • Ballast Arrived!

    Our 13 tons of 10mm crushed ballast arrived today, in two separate loads of
    4 tons and 9 tons!

    13Tons-of-10mm-Ballast

    13Tons-of-10mm-Ballast

  • Fifth Row Completed and Sixth Row half Done!

    Today, we finished off the 5th row and did as much of the 6th row we can do.
    That is another 38 blocks used! This is a total of 289½ blocks we have laid
    down these last couple of weeks!!

    The next job is to mix up concrete to pour down into each of the hollow
    columns.

    Row-5-Done-and-6th-As-far-as-possible-2

    Row-5-Done-and-6th-As-far-as-possible-2

    Row-5-Done-and-6th-As-far-as-possible-1

    Row-5-Done-and-6th-As-far-as-possible-1


  • Thirteen Tons of Ballast Ordered!

    Today, we ordered 13 tons of 10mm gravel and sharp sand ballast. This is the
    quantity we think we need to make the concrete to fill up all the columns in
    our hollow blocks we have been building the walls with.

    Each “column” will need about 18 to 20 litres of concrete, depending on
    whether it is 5 blocks high or 6. We can mix a medium sized load in the
    mixer using a half bag of cement and 40 litres of the ballast.

  • Dumper Truck Won’t Start!

    Oh Dear! Our dumper truck “starter” button doesn’t work anymore! It seems
    that something has disturbed the wiring inside when the last maintenance was
    done on the truck last week.

    We had to resort to our newly mended platform trolley to transport over 3
    loads of 10 blocks and an odd quick load of 4 blocks!

  • Fourth Row Complete and Fifth Half Done!

    We did well today! We had finished off the 4th row left over from Monday,
    and started the 5th row.

    We laid down 48½ blocks in two sessions of 23½ in the morning, and 25 blocks
    in the afternoon.

    The 5th row is the highest we can go for the section that still has the
    support structure in place to shore up the bank of soil, but for the other
    half, we will do the 5th row and then also do a 6th row as there is nothing
    in the way!

    Row-5-Mostly-Done-2

    Row-5-Mostly-Done-2

    Row-5-Mostly-Done-1

    Row-5-Mostly-Done-1


  • Mini Platform Trolley Mended

    We repaired the bent wheels! The front two wheels suffered under the strain
    of hoisting the concrete blocks! We were (and still are) loading 10 blocks on the trolley (this weighed in at about 270kg!) and that started the problem but really it was when we put on 13 blocks (a total of 351kg!!) .. that did the real Damaged!

    I welded on some extra steel pieces to reinforce the axle to the
    flange of the wheel. We only hope now that the ball bearings will survive!!!

  • Fourth Row Progresses

    We only did half a day of work today, so we did another 22 blocks on our 4th
    row of the back wall of the swimming lane.

    We had another commitment suddenly pop up and therefore the afternoon
    session had to be postponed. Tomorrow is forecast to have heavy rain! So we
    will do other tasks in the garage in the dry instead.

    Row-4-Mostly-Done-2

    Row-4-Mostly-Done-2

    Row-4-Mostly-Done-3

    Row-4-Mostly-Done-3

    Row-4-Mostly-Done-1

    Row-4-Mostly-Done-1