And finally, we had to deal with a failed covering on our Timber Store located in our Swimming Lane. The tarpaulin has been completely “fallen” apart from being blasted by the Ultraviolet radiation from the Summer Sun! We didn’t know that the Tarpaulin was a non-stable UV material, probably a cheap and nasty one we acquired sometime in the past!
We took two old pieces we had left over from other jobs and replaced the rotting bit. All is well again .. for how long??!
Category: Swimming Lane
The Swimming Lane and Pond.
-
Tarpaulin Covering “rots” under the Hot Summer Sun!
-
More Dirt Up Against the Fence Behind the Back Wall
This afternoon, after the rain interruption in the morning, we moved few
more tons of dirt over to the gap between the back wall of the swimming lane
and the fence to our neighbours. It is now full and heap a little bit higher
than needed so it can sink down over the coming months.Hopefully, this will stop any further floods and rivers of mud coming off
the neighbouring higher grounds and causing a mess in our land. -
Tidy Up After Wall Building!
This afternoon, we started the tidy up process. We have finished building
the walls of the swimming lane, as part of this stage of construction goes.We are now using the excellent space for storage and we are re-organising
the site to move various items around.
Like for example, all the concrete blocks we got delivered the other day, they will be very useful as “piles” to make sure our materials will stand clear of any water that probably will accumulate in the swimming lane!
We have blocked off the other end of the lane with the rest of the fat 215mm blocks to stop (hopefully) the mud and dirt from leaking in the swimming lane, off the workshop’s higher grounds. The DPM is long enough to stretch right across the end and wrap around the front wall. We now got 3 columns of blocks, stacked up 7 high, with the DPM plastic sandwiched in between them.
at the Beginning of the lane, we will put the OSB sheet stack, followed by two
stacks of the CLS timber (the 63mm and 89mm pieces). Then a stack of the odd
and ends timber that came from the old house, and finally a stack of old
pallets and other equipment.We can really have a good old tidy up and sort out where future delivery of
more timber and sheet material can go. This will maximise flexibility of
storage. -
Third Row Completed on Front Wall!
It is nice to see the 3rd row all completed! It is looking neat and tidy,
especially with the black DPM plastic sheet covering and protecting the
mortar joints from any rain showers at the moment while the cement set and
cures.The final 24½ blocks went in smoothly, taking us 4 hours to lay them in
place.We have decided that it would be much more practical to NOT have tall
reinforcing bars sticking up along the front wall and basically potentially
be in the way for the next 2 years. We will just lay flat two rows of the
narrow 140mm blocks to gain extra height (just laid dry without any mortar
etc) and then place the DPM plastic and hang it down the wall, in front to
provide a waterproof barrier against any dirt and rain water. -
Third Row Commences on Front Wall
We grabbed the morning to start the 3rd row of the front wall, doing 25
blocks before the rain came in the afternoon. This is our last row of the
fat 215mm wide concrete blocks – at last!! Well at least, for this stage of
the swimming lane construction, as we got the pond and the final couple of
metres of the lane to build later on after we have built the house itself!!On this row, we inserted a reinforcing steel bar horizontally to improve the
strength in the direction of “bowing” outwards under the pressure of the
water.We protected our wet joints with a plastic sheeting, from the rain. Which
turned out not to be so heavy as forecasted after all!! -
Second Row of Wall Completed!
With our early start this morning, we managed to finish off the 2nd row of
the front wall before we had to stop for other tasks and commitments. A 9am
start saw us doing the final 16 blocks before 12:30pm, which also included
the delay of our mortar guide breaking apart under the strain of having done
over 400 blocks! It was a half an hour quick and nasty repair job to get
going again and finish off the final 6 blocks!!Stephen improved the design in the afternoon, to make it stronger and also
more flexible as we will be switching over to the narrow 140mm blocks soon,
and there is another 570 blocks of those to do too!!!So we just got another 50 blocks of the fat 215mm blocks to do and then we
look at doing one row of the narrow blocks for the 4th row. -
Second Row of Front Wall well over Half Completed
We were interrupted with heavy rain showers in the morning, so we didn’t get
started on doing any work until after lunch at 2:30pm.We managed to do 33 blocks of the 2nd row of the front wall of the swimming
lane. It was a long haul and we didn’t finish until 7:40pm – phew!But we are glad that we did manage to do that many as this week is going to
be rather interrupted with other commitments and weather too.It is quite noticeable that our skill at laying concrete blocks is improving
all the while and compared to our back wall, the front wall is coming out
very nicely indeed!! Only 16 blocks to go to complete this 2nd row and then
we can start on the final 3rd row of building the wall using the fat 215mm
wide concrete hollow blocks. Then we might do a 4th row using the narrower
140mm wide hollow blocks. This would bring the level of the wall up to just
above nominal ground level and we can then fill up in front of the swimming
lane, using the excess sand / soil mixture that will come out when we dig in
the energy modules. It is coming together slowly but surely!! -
First Row of Front Wall Completed
It was a lovely sunny day on this Sunday, to complete the 1st row of the
front wall of the swimming lane. We took four and half hours to do the
remaining 19 concrete hollow blocks. It went very well, laying the block
nice and evenly, even though we discovered that a fair number of the steel
reinforcing bars sticking up out of the foundation slab were “out of
position” and we had to bend some of them right over and chip a bit off the
bottom of the blocks to make them fit!!But now we have a nice level line to work upon tomorrow and it should go
faster with the 2nd row.Something to note, we discovered that we had rain overnight and there was
some standing water in our swimming lane! This means that we are going to
get our swimming lane sooner than we expected, if we get a real heavy
thunderstorm blast of rain! At least, the ants will enjoy the swimming
exercises!! -
Continued with the First row of the front wall
We spent half a day on doing the 1st row of concrete blocks for the front
wall of the swimming lane. We managed to do 17 blocks today which took us
about 4 hours to do. It was a case of spending quality time on making sure
the blocks were level and at the correct height, so that the subsequence
rows would come out neat without too much fuss.We had done 12 blocks previously a couple of days ago, plus the 2 that was
done a month ago, means we now have done 31 blocks in total so there is
another 19 blocks to go to complete the 1st row.We are doing just 3 rows to build the front wall, and we will stop at that
point. We don’t want to do any more than that for now, as we might need the
extra clearance around the house as we build it, and avoid any future
situations where a 3 foot high wall above the nominal ground level would get
in our way, if we went ahead and built all 7 rows of the front wall!! -
Soil / Dirt / Rubble put Back Behind new Back Wall
Today, we shovelled loads of soil and rubble back over to behind the new
Back Wall of the swimming lane. Much of this dirt was the same material that
had collapsed and washed down away from that higher grounds during the
thunderstorm we had back in January.
It is all rather neat now and once it is settled down a bit, we can put back
the old fence too.We also put together a solid blockage using excess concrete blocks and the
extra length of the DPM plastic sheet to seal off the open end of the
swimming lane to stop any further rain water and mud from sliding down into
the lane. Or at least we hope so!!









