  • Starting on M Section

    Today, at the start of a new week, under a wet cloudy chilly sky, we finished putting up the tile battens on the M section of the roof, all before lunch time.

    Battens-complete-on-M-1

    Battens-complete-on-M-1

    Battens-complete-on-M-2

    Battens-complete-on-M-2



    After lunch, we started putting up the slates, going up the valley and in the three or so hours of the afternoon, we managed 32 rows with two or three slates in each. It is a slow job measuring and fitting the slate into the angled valley, we got a good way up with about 19 rows to go.
    First-few-slates-on-M-End-day-6

    First-few-slates-on-M-End-day-6


    Tuesday saw the installation of the kerb flashing along the Skylight, made up of a strip of rubber and a line of aluminium strips in front, both mounted on wooden short batten pieces spaced out every 500mm (see 1:29 in video).

    Then in the later part of the afternoon, we finished off the valley rows and also finally, fitted the last couple of slates over on the I roof and the final ridge flashing slate along the J roof.

    Left-Valley-completed-End-day-7

    Left-Valley-completed-End-day-7


    All day Wednesday and Thursday morning was a complete wash out in terms of working on the roof but we did instead do some analysis of the task in doing the windows (see Sorting Oak Timber for Windows) so wasn’t a complete waste of time.
    Thursday afternoon, we resumed work on the roof and finished off the complex intersection of the K ridge line meeting with the valley coming up the L and M section of the roof. After that, we were able to mount approximately 300 slates in just two hours to conclude the day’s work. That was fast work!
    Progressing-across-M-End-day-8

    Progressing-across-M-End-day-8


    Friday also had some rain interruptions and we lost a couple of hours in the afternoon. But we still managed to get a further 500 slates up on the M roof, we are well started up the other valley (the M-N valley) now but probably still have another 800 slates to go to finish this roof section.
    Starting-up-Right-Valley-End-day-9

    Starting-up-Right-Valley-End-day-9


    On our final day Saturday, we continued putting up more slates, working up the valley, with shorter and shorter strips and in total we did about another 500 slates. There is just a fairly small triangle patch of roof left to do.
    Nearly-finished-M-End-day-10

    Nearly-finished-M-End-day-10


    But we did have a short pause where we had to analyse why the position of one row of slates was slightly off (you will see the moment in the video below) and this is the first time it has happened. We concluded that the beginning of the horizontal row was not started in the correct position, we realised that there was too much of a risk of drifting whenever we start a new row on the left end. The lesson learnt today will help set up the next section of roof properly and mark the starting point on the left ends of each row from a known reference vertical line in the middle of a roof section.
    In conclusion for this week’s work, we could have done the whole of the M roof section if we had not had the rain interruptions on Wednesday, Thursday and Friday.
    Now enjoy the video of us dashing about on the roof!

  • Sorting Oak Timber for Windows

    Because we had an interruption of work outside, due to rain all day Wednesday and also Thursday morning, we switched over to doing alternative work indoors. This time, we tackled the task of sorting out the design and quantity for the Oak timber used in our windows in the house. The windows will be our next task to do after we have finished putting the slates on the roof.

    We have 13 windows as follows:

    • 9 large windows, 1700mm wide
    • 2 medium windows, 1100mm wide
    • 2 small windows, 500mm wide

    They all have a height of 1600mm and are set at 500mm above the floor level.

    This is the basic design of all windows (showing the front and side cross-sectional views)

    The glass we are planning to use is triple glazing units which measures 50mm thick so some adjustments is needed to the framing to accommodate this. We had originally planned to use double glazing, one on the outside and one on the inside. But we can get better performance in thermal insulation using the triple glazing units at barely higher prices since triple glazing is becoming more popular.

    The Oak timber summary (of 2m long planks) is:

    • 12 pieces of 50 x 160 mm for the sills
    • 12 pieces of 50 x 160 mm for the lintels
    • 26 pieces of prime 35 x 95 mm for vertical framing pieces
    • 52 pieces of 20 x 90 mm for the octagon “covers”
    • 52 pieces of 25 x 20 mm for the glass beading

    We will start processing these oak pieces whenever we have rain in the future and build up a stockpile inside our dry house, ready for the day when we do the windows!

  • Proceeding with L to N Roof Sections

    For our week’s work, we got on with the next three sections, the L, M and N which forms a U shaped inset. We first got all the tile battens up on L section and then used up the remaining full length battens we had up on the platform to do the first eleven lines on the M roof, all by Monday lunch time.
    We then started putting up the slates on the L slope, to have a change of job as it can get painful on our muscles in our legs having to crouch down, especially doing the slates.

    N-End-of-Day-2

    N-End-of-Day-2


    Being such a short section of the roof, we are having to stop and start a new diagonal strip of slates quite often (starting at the valley and stopping at the hip), and that slows us down considerably. By the end of Tuesday, we estimated to have put up only about 280 slates for a day and a half of work.
    N-End-of-Day-3

    N-End-of-Day-3


    Wednesday saw the “almost” completion, with another 300 slates, of the L strip of roof, only leaving a small triangular bit right up at the top of the valley. We needed to cut and trim the third small length of the fibre-glass trough to fit, modifying one batten to make sure the trough will go as high as possible to ensure capture of all the rain water.
    N-End-of-Day-4

    N-End-of-Day-4


    On the next morning, on Thursday, we trimmed off the bull nose middle part of the trough and reapplied a new layer of fibre glass woven mesh and dark grey resin to seal up and form a solid waterproof trough again.
    Top-of-N-M-Valley

    Top-of-N-M-Valley


    While the resin was hardening, we spent most of the day (running late into the afternoon because we thought there was going to be a heavy rain shower mid-afternoon plus also we had a meeting to attend) putting up lots and lots of tile battens up on the M section. We used thirty or so full length battens to cover almost the whole of this section and only has the left-over bits to fill in next week.
    After our late lunch, and no sign of the rain, we took out our new modified trough out and fixed it into place and then continued putting in the final fifty slates or so to completely finish the whole of the L section, including nearly all the flashing tiles too. The final part of the intersection of the four roof sections will be completed when we reach it with the slates on M next week, as we need to know exactly were the slates meet.
    N-Complete-Nearly

    N-Complete-Nearly


    The next two days (Friday and Saturday) were washed out so we didn’t fancy working in the wet and slipping on the battens. We will resume next week on Monday and finish putting the tile battens on M and then start slating that segment next. We have covered about twenty percent of the roof (4 segments) so far but it will jump to about thirty-three percent when we get both the M and N sections finished, which hopefully won’t be too long in coming.

    And we have resumed shooting daily videos of our work so here are the time lapse versions for you to watch…




  • Flashing for J Hip Complete and the K Roof all Covered in Slates

    We started the new week by finishing off the “Hat” covering the Hips for J-K and K-L as well as the ridge between J-L roof slopes. We filled in the little pin holes in the top of the bull nosed with plastic padding filler, rubbed it all down and coated with another top glossy finishing coat of the resin.

    Then we designed and constructed a template tool for making nail holes in a slate. These slates are the flashing slates to go up the hips to cover up the rubber membrane and the jagged edge of the main slates and provide rain protection at these joints.

    Hip-Flashing-slate-hole-punch-1

    Hip-Flashing-slate-hole-punch-1

    Hip-Flashing-slate-hole-punch-2

    Hip-Flashing-slate-hole-punch-2



    We tested out our new tool by preparing about sixty slates to go up the J side of the Hip and Ridge which we duly went and installed them all!
    Roof-J-Complete

    Roof-J-Complete


    After that, we got on with slating the K roof, like for example, on Wednesday, we did managed to put up an estimated 500 slates in a single day session which is amazing!
    Roof-K-Half-Done

    Roof-K-Half-Done


    But it took another whole day (Thursday) to complete the K section, including all the flashing tiles. The bulk of the roof was just, almost, simply shoving the slates onto their hooks, but reaching the other Hip meant lots and lots of fiddling with angles and slicing slates to fit the last piece into place.
    Roof-K-Done-1

    Roof-K-Done-1

    Roof-K-Done-2

    Roof-K-Done-2

    Roof-K-Done-3

    Roof-K-Done-3



    We are calling it a 2 day session to fully put up all the estimated 800 slates for the K segment so that is pretty good for us but we could beat that record when we get around to the front of the building for even bigger sections of roof to do!

    Finally, we started filling in the tile battens on the L and M roof so we could start on slating them next week .. but Storm Hannah came along to disrupt our work with strong winds and rain showers so we only managed to do a couple of hours on Saturday morning!!

  • Gutter Mesh Protector Installed, Corrected Alignment of M-N Valley Trough and Hips plus Ridge “Hat” Created for J K and L Roof Sections

    It was a week of lovely dry weather. We started the week  by tidying the workshop and completing the making of the Ladder Support stainless steel brackets and setting out strings to get the hip flashing straight (The roofs wobble a bit).

    Skylight-safety-wire-supports

    Skylight-safety-wire-supports

    String-to-align-hips

    String-to-align-hips


    We tackled the next job of putting on the metal Mesh Protector over the guttering where we went along the K section, round the corner into L. Then from one valley (L-M) to the other valley corner (M-N) .. ..

    Gutter-complete-on-K

    Gutter-complete-on-K

    Gutter-complete-on-L

    Gutter-complete-on-L



    But before the mesh went down in around the bottom of the valleys, we had to nail into place the glass-fibre trough modules, the first section at least. But we discovered when we came to do the M-N valley that the angle was all wrong. We tried to be too clever when we laid down the counter battens to support the trough, but our lack of experience, and lack of double checking the theory, we shifted the position sideways so that the valley line would be centred to the gutter and downpipe channel! This was Wrong! it made the intersection  of the slates different heights… So we spent the morning doing some open surgery on our roof, peeling back the layers of breathable membranes, moved the wooden battens and realigned it.
    Incorrect-MN-valley-Before-work

    Incorrect-MN-valley-Before-work

    Incorrect-MN-valley-All-opened-up

    Incorrect-MN-valley-All-opened-up

    Incorrect-MN-valley-Fixed

    Incorrect-MN-valley-Fixed



    The new angle of the trough now means that the two roof surfaces of the slates coming in towards the valley point are both at the same height and meeting point and makes (will do) a neat line down the valley.
    We resumed the interrupted task of covering up the gutters with the metal mesh and finished three quarters along the N section just before the N-O outside corner. We haven’t done the O gutter with its rubber liner yet.
    MN-Valley-installed-and-gutter-finished

    MN-Valley-installed-and-gutter-finished

    LM-Valley-installed

    LM-Valley-installed



    We had one day of interruptions with a meeting in the morning and putting up the sun shield on our temporary living quarters but we resumed the work, this time, making a rain protective “Hat” for all our Hips and Ridges around the house, we have twelve Hips and five Ridges in total! This is part of providing a flashing system using slates and a layer of rubber membrane and this “hat”. We decided to go with this design because we needed to minimise the effect of the wobbly edges when they come together on the Hips and Ridges, which will be covered up the exposed cut slates of the roof surfaces, with a line of straight slates running up the Hips and along the Ridges. The hat will be a vertical piece of 19mm (¾”), strip with a rounded top (made from an OSB sheet). This is then covered over with a 150mm wide woven glass-fibre ribbon which will get coated in the dark grey resin. This combined object is sitting on top of a 400mm wide strip of rubber membrane.
    We stapled down each of the layers, then using short iron wire pieces, fixed to the underside of the bull nosed strips, was bent to provide a stiff anchorage method of holding the hat upright position against the various angles of the roof surfaces coming together.
    Hip-hat-support-wood

    Hip-hat-support-wood

    Support-wood-installed

    Support-wood-installed

    Fibreglass-tape-in-place

    Fibreglass-tape-in-place



    The whole thing then got coated with two applications of a flexible roofing resin before applying a top coat finish. Looking at the results, we think we ought to put on another coat of the finishing resin to make sure we haven’t left any pin holes behind to let rain water in.
    Hip-hat-finished-1

    Hip-hat-finished-1

    Hip-hat-finished-2

    Hip-hat-finished-2



    Finally, on the last corner of the back of the building, the O-P outside corner, we sliced off the layers of plywood that made up the hip support, put on a layer of heavy glass-fibre matting and then coated the whole thing with black top coat finish. All rubbed down and smooth, ready for going along the P section towards the Conservatory.
    OP-Gutter-corner-fibreglassed

    OP-Gutter-corner-fibreglassed


    This means now that we can insert the last strip of rubber liner for the gutter along the O section and put on the breathable membrane and battens to have this section of O roof ready for slating too.
    Next week, we can resume the job of putting up thousands of Slates for the K slope (and L, and M, and N, and O too!), and doing the flashing slates a the same time as we climb up the roof. We are Getting There!!

  • Sun Shield Installed and very Minor roof repairs done on Living Quarters

    Today, in the afternoon, we installed the Sun Shield tarpaulin up over the long corridor in our temporary living quarters . It seems to be very early this year, but we were suffering in the collected heat of the sun pouring into our corridor!

    But the first job was to repair the Sun Shield tarpaulin because the stitching we did last year had torn apart. Well actually, the thread had frayed and came apart due to excess loading when we had high winds.

    So this time, we decided to try to glue the two pieces of the tarpaulin (2.5 metres wide by 5 metres long) using contact glue. We first tested this method on an spare bit of the similar tarpaulin and it seemed to be just fine, in fact, very strong indeed! Of course, we don’t know whether the glue joint will survive in the sunshine but we will give it a try.

    So we proceeded to glue the two sections together (with a 150mm – 6inch – overlap) on top of our garage, on its flat roof where we had plenty of room, plus also we didn’t have to disconnect the tarpaulin from the first anchorage point.

    But we discovered that when we pulled out the new combined piece, it wouldn’t reach the far end! Of course not, we nicked 6inches didn’t we! But fortunately, we had wrapped some excess amount of the material around the fixing batten so we undid the first anchorage point after all, unwrapped it one half turn to give us the extra back again and redid everything back.

    We now have a Sun Shield and aaah h.. it is nice and cool! Sigh!

    To finish off being on the roof of our temporary living quarters, we inspected the surface and did some very minor repairs in the felt and also took notice that we will have to do a major roof job soon, perhaps later on in the Summer, and lay some new strips of roofing felt as the current layer is definitely shrinking and pulling itself away from the glue line. It is after all 8 years, or even 10 years since we put on the felt so it has done very well!!

  • Rubber Liner for Gutters and Breathable Membrane Covers L, M and N Roof Sections

    The work this week was to cover the next three sections of the roof surface with the breathable membrane and protect the wooden Oak guttering with the required rubber material.
    The rubber membrane was the first to go into the gutters, doing our usual order of gluing down the bottom surface first (using the wet rubber solution), followed by the much slower use of two layers of contact glue on the ends of each rubber strip. We had to paint the glue on and dry the exposed surfaces using a hair dryer to speed this process up and then carefully smoothly iron the rubber into place (using our hands and fingers). We finished all three gutters on Monday.

    Gutter-rubber-installed-in-LM-N-1

    Gutter-rubber-installed-in-LM-N-1

    Gutter-rubber-installed-in-LM-N-2

    Gutter-rubber-installed-in-LM-N-2



    The subsequent days were spent laying on the dark grey breathable plastic membrane, row by row, around the three roof surfaces, fixing each section with vertical counter battens and a few lines of tile battens to act as a ladder for us to climb up and down easily.

    One of the other jobs that had to be done was to finish off building up the hip and ridge layers of plywood strips to provide the fixings for the flashing slates, on the OP hip angle and the O Ridge line.

    Membrane-and-Hips-and-Ridge-Done-on-N

    Membrane-and-Hips-and-Ridge-Done-on-N


    Then we could complete the breathable membrane coverage on the N roof with a half width strip going over the ridge line and then doing the final strip of membrane on the M roof, a very long piece over 11metres (35feet) long and then a small 300mm wide strip to provide the complete protection up onto the kerb of the Skylight.
    End-of-week-13th-April-1

    End-of-week-13th-April-1

    End-of-week-13th-April-2

    End-of-week-13th-April-2



    End-of-week-13th-April-3

    End-of-week-13th-April-3

    End-of-week-13th-April-4

    End-of-week-13th-April-4



    This week sees the completion of fully waterproofing sections of the roof along the back the building that is served three downpipes, so we are now collecting approximately 130 square metres (about 1/3 of the total) of rain water from the roof when any rain falls out of the sky!! This amounts to 130litres of rainwater for every 1mm of rain fall recorded!

    Next week’s set of tasks is to finish off the stainless steel brackets for holding the ladder support wire (then we can clear up the tools in the workshop), make a flexible fibre-glass plastic hip and ridge “hat” strips and then carry on putting up more slates on the K section!

  • Section J Fully Covered in Slates, K All Battened Up and Guttering Complete Along Back of Building

    Another week is done, apart from two days of interruptions (due to a day of rain and two half days of other commitments), we had a good week of work. We completed our second section of roof, prepared the next one ready for the slates and finishing off the last stretch of Guttering.
    First job of the week was to put on the breathable membrane layers up on the K roof, overlapping the rubber strip already done from last week, putting down vertical counter battens every 610mm apart and then nail on all the horizontal tile battens at the usual spacing of 112mm up the slope. We did this job in two separate stages, the first one being just enough so we could climb up and get over to the J roof so we could complete the task of installing the slates.

    Menmbrane-and-battens-on-K

    Menmbrane-and-battens-on-K


    Thus, we duly did finish off putting on the slates on the J section of the roof, a total of about 400 of them. We had also put on the metal mesh over the gutter going around the corner (from J to K).
    End-of-April-4th

    End-of-April-4th

    End-of-April-5th

    End-of-April-5th



    The forecast was for more rain, light random showers, so we got on with putting up the second stage of tile battens on the K roof and got that done, including all the hip flashing battens too.
    K-completly-battened

    K-completly-battened


    The other job that was completed, earlier in the week, was completing the guttering along the O section and also a little bit on to the P section too, which now concludes all the roof elements along the back of the building.
    Gutter-started-on-P

    Gutter-started-on-P


    Next week, if the weather holds good, we may install more rubber and breathable membrane layers on the rest of the roof surfaces along the back, L, M and O, and put up the first set of counter battens and a few tile battens to act like a ladder. If the weather is bad, then we will be working in the workshop to make fibre-glass flexi-plastic objects to protect our Hips and Ridges against the rainwater when we put on the flashing slates.

    P.S. We have been asked to include a diagram to remind people of the position of where we are working…

    House

    House

  • Slates on J Roof and Progress on Gutters

    Another week is done and we are progressing on the roof putting Slates on the J roof segment and Guttering on the next four sections from L to O.
    We came back from our trip down south and resumed work on Tuesday by completing the valley line of slates and did a further three more lines up the diagonal before we got too close to the hip corner joining the L segment of the roof. We couldn’t continue because we wouldn’t been able to climb up over the hip to get to the higher rows of slates without having the next set of tile battens nailed up (to act as the ladder!).

    Slates on J Roof and Progress on Gutters

    End-of-26th-March


    So for the next couple of days, we got on with installing more of the Oak timber guttering, continuing from the corner of K and L, completing L and going around along M and N plus also the last section O we got along the back of the building (and have scaffolding platforms installed).
    Slates on J Roof and Progress on Gutters

    Gutters-L-M-N-Attached-1

    Slates on J Roof and Progress on Gutters

    Gutters-L-M-N-Attached-2

    Slates on J Roof and Progress on Gutters

    Gutter-O-attached



    We quickly put up more of the hip support layers of plywood strips on the N and O corner and cut off the overhanging pieces to make a neat squared off ends. The other corner K and L was also cut and made neat too. This means that the task of fibre-glassing with black resin was done on all four corners (two outside hip coroners and two inside downpipe channels valley corners) in one session.
    Slates on J Roof and Progress on Gutters

    Corners-and-Downpipe-channels-fibreglassed-1

    Slates on J Roof and Progress on Gutters

    Corners-and-Downpipe-channels-fibreglassed-2

    Slates on J Roof and Progress on Gutters

    Outside-corner-with-fibreglass-over-hip



    The last piece of work of the week, was starting to install the rubber liners inside the gutters whereas we laid in the 9 metre long rubber membrane for the K section. We decided to try a different order of doing things and this time, we applied the wet rubber latex solution on the base of the oak gutters first, laid the rubber down and then tackled each ends separately. The ends were also done differently, doing each flat surface in turn with the contact adhesive and getting a much better result with a very neat flat finish.
    Slates on J Roof and Progress on Gutters

    Rubber-lining-for-K-glued


    On the next week, we will continue putting in more rubber liners for the gutters for L, M, N and O (the O section, we will have to do the outside hip corner O P (we left it undone thinking we could do that later when we move around to do P) but we realised that we do need to have half of it installed so we can lay the rubber in the O segment and also have all the sections of the back of the building completed and be able to move all our scaffolding platforms in one go and move to tackle the next portion of the building’s roof) Then we will start laying down the breathable membrane all the way along and so on.

  • Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    We resumed work in new week by continuing slating the I section of the roof, Creating a roof ladder support system and getting the flashing line of slates onto the kerb underneath the overhang of the skylight done too.
    One of the first jobs was to make a heap of kerb flashing slates which were made from cutting a standard slate in half down the long direction (to make 100mm wide by 300mm long pieces) and we then made a jig to hold our slate nail hole puncher in a fixed position and align each half slate to have a nail hole put in exactly 75mm from each end and 50mm from one edge.

    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    Jig-for-punching-holes-for-Kerb-Slates


    But also before we could continue with the slating, the roofing ladder support suspension system (This will be a stainless steel cable attached around the skylight, to which we can hang a roof ladder if we need to access then skylight etc) needed to have various components created, namely the stainless steel brackets which are 100mm long (a right angle steel bar) with a 12mm rod sticking out which is also 100mm long.

    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    Parts-for-Kerb-Wire-supports

    The two pieces will be welded together (with stainless welds!). We got one finished so we could take it and mount it up onto the kerb at the start of the skylight. The angle iron piece had two screw holes and we used stainless steel hex head coach screws to fix it in place horizontally between the vertical battens.

    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    Roof-Wire-support


    We then got the rubber membrane which is 250mm wide and stapled it along the first section of the kerb to all the vertical battens so it is ready for the half height flashing slates to cover over it, with the dangling part of the membrane to go underneath the final row of tiles.
    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    First-kerb-Slate-with-Wire-support-post


    The chimney bracket was the next challenge! The square metal pole (50mm across) sticks out of the slope of the roof and we had to cut and trim each layer of the slates to fit around it.
    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    Slates-cut-around-bracket


    The pole had a rubber membrane stretched over and pulled down the pole and laid flat on the top slate. It was sealed with proper rubber sealant between the rubber and the metal pole and clamped using a black cable tie to mechanically hold it in place while the sealant cured. Then the rest of the rubber membrane was glued to the slate itself with contact adhesive to stop it flapping in the wind and provide a good surface for the rain water to run off correctly.
    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    Rubber-seal-glued-to-the-Bracket

    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    Rubber-seal-complete-on-Bracket

    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    Chimney-bracket-in-the-roof



    We arrived at the point where we needed to sort out the last section of the valley trough. We had to analyse how the slates will be laying from the two slopes of the I and J sections of the roof and how the ridge comes into play as well. We made some adjustments to the fibre-glass trough to turn it into an arrow shaped and also trimmed off the “bull-nose” sticking up bit so we can lay down the flashing slate tiles protecting our ridge line. We mixed up some white resin with black dye until we got close enough to the mid grey colour and then sealed up the “hole” we created at the top of the trough and now we have a waterproof collector mechanism that goes right up to almost the kerb.
    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    The-Modified-top-of-valley-trough


    We finally completed the I section of the roof, bar the last five slates which we can do from the other side of ridge when we are doing the L and M roofs, because we can organise the layers of the flashing rubber membrane pieces in such a way to ensure that rain water will always be collected and diverted down the valley trough.
    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    Roof-I-fully-slated


    So we now have started the J roof and we have most of the markings drawn on the J roof with the regular 204mm spacings on the tile battens. Next job was the metal mesh inserted to cover up the guttering up to the outside corner and clamped down with the oak thin strips.
    And got on with the task of putting on more slates, starting back at the bottom over the gutters, at the valley end and working left to right as usual.
    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    End-og-22nd-March


    We will have a small break (Saturday and Monday) as we need to go and visit family down in London but from Tuesday, we will carry on with the J roof, which hopefully won’t take so long because it doesn’t have chimneys or kerb complications to worry about!!

    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    End-of-18th-March

    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    End-of-19th-March-1

    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    End-of-21st-March

    Ladder Support System Created, Roof Section I complete and Kerb Flashing Done

    Roof-I-fully-slated