Skip to content
  • Sat. Jul 12th, 2025

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed
Build Progress Phase 4 Roof Timelapse Movies

Video Footage of the Entire Job of Covering Our Roof With Plywood Boards!

Jul 31, 2018 Shaun

Here is a video of our roof being covered up with 12mm thick plywood sheets, starting on the “A” roof section and going around anti-clockwise and finishing on the “P”,…

Build Progress Phase 4 Roof

Finally “P” Is Completed!

Jul 31, 2018 Shaun

At last, we managed to get back out to work on our roof after all the twirling rain showers we had over the last four days – we had nearly…

Build Progress Phase 4 Roof Timelapse Movies

Roof “Q” Is Completed and “P” Nearly There!

Jul 28, 2018 Shaun

We had a slow start today as we had a series of short sharp thunderstorms and showers with a twirling strong breeze so didn’t get going until about 11am. We…

Build Progress Phase 4 Roof

Half of “P” and Half of “Q” DONE!

Jul 26, 2018 Shaun

Another day spent on the job of covering the roof with plywood boards, but we are making good progress. We have completed half the “P” section of the roof (in…

Build Progress Phase 4 Roof

“O” Is Completed and “P” Now Begins

Jul 25, 2018 Shaun

We moved on to doing the next roof section, the “O” steep roof but it was quite small and only needed three boards to complete it. Then it was time…

Build Progress Phase 4 Roof

Roof “M” and “N” All Done!

Jul 24, 2018 Shaun

Under a slightly hazy sky, a lot more wind, temperatures hovering around 28°C hence the blazing Sun wasn’t so harsh, we continued to work on the three roof sections which…

Build Progress Phase 4 Roof

“L” Complete, “M” nearly and “N” Progresses!

Jul 23, 2018 Shaun

What a blistering hot day! Our Thermometer recorded 28°C today! Under that heat, we continued putting up plywood boards and we got the ‘L’ section completed, almost all of the…

Build Progress Phase 4 Roof

“L” and “M” Roof Sections Progresses

Jul 21, 2018 Shaun

For another shortened day of work, we started on the “L” and “M” sections of the roof and got the second row fitted. It is very very hot out there…

Build Progress Phase 4 Roof

Section “K” Complete

Jul 20, 2018 Shaun

For our half day of work today, we started on the next section of roof, this time it was “K”, and we got it all done! It only needed two…

Build Progress Phase 4 Roof

Back Roof Coverage Progresses ..

Jul 19, 2018 Shaun

Yesterday and today, we are progressing on covering the roof sections along the back of the building. We finished the first row, using our posh plywood boards (section “M”, “N”…

Posts pagination

1 … 37 38 39 … 148

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

Proudly powered by WordPress | Theme: Newsup by Themeansar.

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed