Yesterday and today, we are progressing on covering the roof sections along the back of the building. We finished the first row, using our posh plywood boards (section “M”, “N” and “O”)
Then moving back to the beginning, started laying boards up the slope of the “I” and the “J” sections. It was incredibly hot in the late afternoon sunshine! But we did managed to process about 12 sheet in total!
Today, we carried on with the “I” and “J” roof sections, including working around the Chimney support arm, making sure we minimised the lack of any support for the plywood edges while accommodating the metal square pole coming through the roof panel.
Tomorrow, we will move around the corner onto the “K” section of the roof and carry on along the back of the house.
The video below is the combined two day worth of our activities!