Category: Build Progress

  • Cold Water Header Tank Created

    While we waited for our Test Tank to dry out completely before we can initiate any repairs, we got on with building the mould for our next tank to make, this time the cold water header tank that sits upstairs behind the Shower Room. This tank measures 700mm wide and 400mm deep and 1900mm tall, it will sit on the reinforced platform we have already built and there will be about 150mm (6inches) clearance at the top to allow us to get the lid off and look inside.
    So, we got two more sheets of our 11mm OSB off our rack of miscellaneous sheet materials and proceeded to build a similar designed mould like we did before. One of the major differences is that we need to be able to crawl inside the mould to reach the screws that holds wooden blocks around the edges. We decided that this mould needed more secured edges because it is larger, hence the reason for having more wooden blocks around the long edges. It was quite interesting crawling inside, flat on our stomachs and screwing the final screws in place to tighten the mould together!!
    We did the usual routing on all the edges, to put a nice curved and smooth edges for the glass fibres to bend gently around the flat surfaces.
    Cold Tank Mould being made

    Cold Tank Mould being made

    Mould ready for tape

    Mould ready for tape



    And then, covered the entire mould in our new brown parcel tape, using two complete 66metres rolls!!
    Covered in release tape

    Covered in release tape


    Next, we cut all the glass fibre material into 12 pieces of 2.3metres lengths (this is being the circumference of the tank in a horizontal direction, measuring two sides of 700mm and two sides of 400mm, giving a total of 2200mm so we added an extra 100mm to be on the safe side), then we created six rectangular pieces for the base of the tank measuring 500mm wide strips off the roll, enough to cover the 400mm width of the base, but deliberately used the whole roll width of 990mm to cover the 700mm in the other direction and send the excess around the corner to reinforce the bottom 140mm of the side walls so we can install plumbing connectors and not overly stress the material too much with the very stiff plastic 32mm diameter pipes. Next, we tore off 120mm wide strips and then slice it in half down the middle and these narrow strips will go around the flange at the bottom of the mould.
    Finally, we cut a length off our woven cloth roll, ending up with two pieces measuring 1900mm long and 1550mm wide (the original cloth width). That isn’t quite enough to wrap around the tank so we then sliced off a further 1900mm piece again, but this time, we sliced the width in half to make two 750mm wide strips, to join with the other piece and make a complete loop. The last couple of pieces is for the base and we sliced a 500mm wide length off the roll and also sliced this one again in half, to make the final two pieces.We had originally put our mould on two planks of timber that had four office chair castor wheels so we could spin the mould around when we are working on it. It worked well when we were wrapping the brown parcel tapes onto the mould, but discovered that just standing up in the Garage, on the concrete floor, we actually didn’t want to keep moving it around, and instead, we would walk ourselves around the mould!! So we could off the wheels and those two planks!!

    The next job was to prepare the resin and we are going to use 25kg of the stuff, it comes in a very large bottle! But, we had our tin that had our dark brown resin in, so we poured off the small amount of that left-over resin into a small pot (we will use this resin to attempt to repair our Test Tank). We then tipped the large bottle and filled up the metal tin which holds 5kg, making it much easier to mix in the white colour we want and easier to pour small batches of resin, ready for the hardener catalyst liquid to be added and stirred in. Our white colour, which is titanium oxide powder, needed to be sieve through a old tea stainer, to knock out all the lumps and then have a small amount of resin dropped in the powder, to make a smooth paste. This vastly improves the white colour to be completely mixed into each tin load of resin, by adding several teaspoons of the white resin and thoroughly mixed in.
    Now, we can get started, fresh at the start of a new day, even starting an hour early at 9am and keep going until we have completely finished. We put on the first cloth layer by coating the whole mould with the resin and then putting on the first large piece of cloth, repainting it over again. we decided that we would try and turn it inside out so that we can maximise the amount of resin this very first layer should get. But, it proved rather difficult so we didn’t do it again to the second piece of cloth and just thoroughly coated it with lots of resin. We wanted to make sure that we had a decent starting layer of water tight glass fibre saturated in resin, especially on all the corners. We don’t want a repeat of the tiny little leak we had in our Test Tank!!
    We then started laying on the 2.3metres length of matting, doing the lower half first, and then putting on the upper half afterwards, and making sure that we put on two coats of resin every time. We repeated this twice more so we had done three layers and half way there, at which point, we consolidated all the layers and resins by using our aluminium textured roller, which is designed to pressurised the individual glass fibre strands and mix the resin completely together, going carefully around each of the corners and edges.
    We put on the last three layers of matting and finally, put on the second layer of the woven cloth to finish off.
    We were working for nearly 7 hours non-stop !!

    Header Tank All made

    Header Tank All made


    We left it overnight, to allow it to cure and harden the resin as much as possible, before we tackled the next task of removing the wooden mould from inside the freshly made tank. The first job was to carefully trim the flange so that it is an even amount all the way around the whole tank, by using our wiggle saw and a chunk of CLS timber to act as a spacer guide. Then we carefully lay the tank on its side and prop it up on a couple of wooden planks so the weight wasn’t resting on our new flange after we had removed the first part of the mould. The “lid” came off and we needed to crawl inside to undo all the screws, to release the four sides from each other and make it easier to bend each side inwards and then remove.
    Shaun undoing mould fixings

    Shaun undoing mould fixings


    We managed to get the four long sides out fairly easily but we discovered that the sticky parcel tape has gone extra sticky for some reason. This meant that we had to crawl across this yukky tacky surface to get to the bottom final piece of the mould and dig it out. Mind you, we had to wait five minutes first, to blow away all the fumes of the solvent. We used a fan. This perhaps gives us a clue to why the sticky tape has gone extra sticky because the solvent was able to migrate through the thin plastic film of the parcel tape. Anyway, we managed to dig out the bottom section of the mould and were able to peal the majority of the stick tape off, by starting at the bottom of the tank and pulling it out like a sleeve. We discovered that our tank is translucence and it glowed in the sunshine !!
    Tape stuck to the inside

    Tape stuck to the inside

    But it came off fairly easyly

    But it came off fairly easyly



    The problem with the extra stickiness was extended to the resin finish as well and we needed to leave it open, with fresh air blowing on it, for three or four days over the weekend, before most of the sticky tackiness had disappeared.

    The whole tank got a bit of a rub with sandpaper, to take off any sharp edges and glass fibres that didn’t settle down during the last coat of resin. The flange got its four corners rounded and the sharp edge smoothed over as well.

    In the meantime, we took the original base that the mould sat on, reapplied more sticky tape but this time using the clear parcel tape instead for a comparison test and made a four layer matting with the same white resin flat across the board. It came off much easier, without leaving behind this sticky stuff so it looks like that the parcel tape is too thin to give the best results. So we have made our lid for this Header Tank, so that we can keep out the dust and dirt. It will be clamped down using wing nuts, on a sandwich of rubber draught excluder strips, to provide that seal.

    Cold Water tank lid laminated

    Cold Water tank lid laminated


    That concludes the construction of the Header Tank, we are waiting for plumbing bits and pieces to arrive before we can perform a soak test and find out if we got any leaks. This tank will hold a maximum of 500litres and that weighs half a ton !! So we WILL not be tipping it over, out of our garage door to empty it!! We Do Not want a tidal wave gushing across our driveway!! Hence why we have been waiting for our plumbing order to arrive, with a tank connector and a shut-off valve so we can empty it the old fashion way! In fact, we will take the opportunity to try out our water pump motor and see how it performs and how noisy it is as well.

  • Creation of Test Tank

    We are at the stage of designing and building our water tanks, one cold and one hot. Because, we have a limited target volume to locate these tanks, we decided to make our own tanks, using glass fibre and polyester resin. We have used this kind of construction material a number of times before so we calculated the amount of material we would have to buy, in order to build the three tanks we are wanting. But first, we needed to make sure that it works out properly so we are doing a Test Tank first. Actually, it will become a plant pot for a tree that came at Christmas time!
    It will also be part of a boiling water test as well because we need to make sure that our hot water tank will hold the hot water without softening the walls.
    So we ordered 33kg of glass fibre matting, 35kg of ‘normal’ resin and 30kg of ‘special’ heat and chemical resistant resin, plus also 20metres of woven glass cloth as well.
    The Test Tank measures 450mm on a side, making a cube. We want to have a lip around the top so we can see how well it forms, ready for a lid to seal down on it, on our larger tank later on. The Test Tank won’t have a lid.
    So we need a mould, to take the eight layers of matting and two layers of cloth, to make a wall thickness in the order of 5mm thick.
    This mould will have to be constructed in such a way, that it can be disassembled afterwards, as the completed tank will be solid and sticking to the mould.
    So we used sheets of 11mm OSB boards, sliced it up into four sides and one base. Two of the sides were slightly narrower so that the overall dimensions came out the same on all four sides. Also, these two narrow sides had a saw cut sliced almost all the way through the 11mm thickness, to make it much easier to drive a crowbar into the gap between the finish tank and the mould and be able to bend the sides inwards. We did the same for the base as well. We then screwed little battens around the edges to hold the corner edges together, but done in such a way so that the pre-cut sides can move inwards. It was a careful process of making sure that we could ?undo? the mould, in the correct order.
    Finally, we put on a larger ?lid? on the mould so, when the mould was turned over to sit on this so-called lid, we had a space to form the lip of the tank as well. We rounded all the edges using a 12mm quarter turn shaped router and also applied a little bit of plaster to provide a gentle bend for the lip too.
    Box mould constructed

    Box mould constructed


    Now, we wrapped all over the mould a complete layer of parcel sticky tape because we discovered that the parcel tape offers a very very non-stick surface against the polyester resin. We did some quick test using various grades of sticky tapes, as well as some very thin plastic film material and this is how we discovered that standard parcel tapes works the best.
    So this is what we did with our Test Tank, wrapped it up in this sticky tape. Mind you, we only had the ‘clear’ sticky tape and it was quite difficult to see where we have been or not. So, we ordered the brown stuff !!
    Covered in tape

    Covered in tape


    Next, is to prepare the glass fibre and have them ready, in a pile of torn pieces. But, before that, the 33kg roll of matting needed a carrier so we could pull off the roll the required length. We quickly assembled a wooden carrier using left-over OSB 18mm pieces and a length of broom handle (we had some left-over of those too from a previous project, so we didn’t have to use a domestic broom!)
    The roll is a metre wide so the carrier is 1200mm wide, with a two battens loosely sandwiched together at the top, for the glass fibre matting to slide in between. This allows us to press down on the upper batten and grip the glass fibre and tear pieces off.
    33Kg of Glass fibre Mat

    33Kg of Glass fibre Mat


    So we tore off twelve pieces measuring 450mm long, and four pieces of 900mm long. These form the bulk of the walls but we wanted to put an initial layer of the woven cloth on the mould first so that this offers the maximum strength bending around the corners of the tank. We unrolled the cloth and cut a single piece 1350mm by 1000mm long. Then, we draped it over the mould and carefully cut the overlapping folds, to remove the triangles so the cloth would lay down flat.
    We did a second one so we could put that cloth piece on as the final layer, to encapsulate all the strands of glass fibre that comes in each matting sheet. These matting sheets are made up of a random sprinkling of 50mm long glass fibre strands, held together with a very light glue that will instantly dissolve when the resin is applied.At this stage, we decided to put in colouring dye into the resin so we went for a muddy brown colour by mixing four teaspoons of red powder and four teaspoons of blue powder dye and this made a muddy brown colour, suitable for being a flower pot !
    The final steps of preparations, was to get several pots of acetone ready for cleaning our rollers and other tools, a pile of paper wipes and a collection of mixing trays etc.
    So, we started at 11:25am and mixed our first batch of resin with the hardener, using 1% ratio of hardener so we had plenty of time to apply the mixture before it started setting. The garage temperature was about 15°C so 1% will give us a good 30 to 40 minutes of handling time.
    We coated the mould with the brown resin, using a fluffy roller to transfer the liquid over, and then draped the cloth over. We slid the cloth around and made sure that it went from edge to edge and that the two sides folded in and overlapped properly. Then, we rolled on more resin liquid until the cloth was entirely coated in resin. Then, we got our four larger pieces of matting, and one by one, laid each over the mould, tearing one edge so that it can rotate around the mould and the loose flap goes over the top. We put plenty of resin all over the surfaces. We used the aluminium roller to work the resin liquid into the individual strands of glass fibre, and also, to force out any trapped air.
    Next, we took the narrower strips and went horizontally around the mould, repeating the process of loading lots of resin on each piece of matting and eventually, we put on a total of eight layers. We also put on the second woven cloth material near the end of the process.
    It took us two hours to do this Test Tank.
    Test box fibreglassed

    Test box fibreglassed


    We gave it a couple of days (over the weekend) for the resin to cure and harden before we tackled the task of dismantling the internal mould and generally, it was not too difficult. We unscrewed various screws and then used a crowbar to lever the two side walls that had the ?almost? cuts in them and this then allowed the other two walls to come out and finally, we got the crowbar into the cut line in the base and managed to lever each half out. Then, we pulled off the parcel sticky tape which got left behind on the inside of the finished tank, it looks like that the resin had quite an attraction to the glossy side of the parcel tapes, more than the sticky attraction to the wooden surfaces anyway. It wasn’t a problem as we could peel off the tape fairly easily, leaving behind a brown cubic reinforced glass fibre plastic tank. It needed a bit of trimming around the lip because we had a ‘dam’ to make the lip flange, but it ended up with too much glass fibre and resin. So, we just laid down a small piece of 6mm thick MDF board on the floor and, positioned up to the edge of the flange (the tank is upside down) and used our wiggle saw to slice off the lumpy bits.
    We also ran the sand paper over the surfaces, to rub down little spikes of resin and fibre and also rubbed the edge to round the corners and the square edge.
    Test tank demoulded

    Test tank demoulded

    Test Tank

    Test Tank



    The final stage of this test, is to put in water, both cold and hot water, and see if it holds it without leaking.
    This Test Tank holds about 90 litres so we got the garden hose and filled it almost to the top and sat it in our Garage and left it for a few hours while we got on in making the next mould for the larger header tank.
    Unfortunately, we had a leak!!
    A very very small one! But still a leak!
    It is amazing to how water can get through 10 layers of glass fibre and resin. The leak is actually on one of the rounded bottom edges and we believe that we were not careful enough in making sure that these rounded edges were carefully loaded with extra resin, to make sure even those fibres are saturated.
    We learnt a valuable lesson and this is what this Test Tank revealed to us!
    We will have to patch the leak before we can perform the hot water test and we will do that later on.

  • Started Constructing Walls for the Rooms Upstairs

    These last two weeks have seen us start work on building the initial framework for the walls for the rooms upstairs. We would like to lay down a “floor-plan” of all our rooms.
    But first, we had to move our large pile of our 63mm CLS timber planks! We wanted to gain access to all the space where our “stub” wall will go around the edge of each room, the wall being four feet tall when it meets the sloping ceiling. So we had to move approximately 250 planks of timber, plus also 25 planks of “green” preservative treated timber as well. The green planks will be used for our wet rooms downstairs, where there is lots of water splashing about.
    Anyway, it took a couple of hours to move the timber!
    Then, we built a template that emulates a fully constructed “four-foot” wall, so that we can glue and screw up a whole sheet of a OSB board in one go, without having to slice it at all. This template is only four inches wide so we can slide it along on the floor, until it “bumps” into the sloping roof. We then would mark the floor with a green spirit pen and move along a couple of metres and do it again. The green colour was used because we had already other black marks on the floor from our previous attempts of laying out a rough plan of our rooms upstairs!

    We started near the Gallery and marked out the two “four-foot” walls, one between the Gable wall and the stair case hole, and the other one, on the other side of the room, from the gable to the toilet, which is situated opposite the stairs.

    Next, is framing around the stairs hole, positioning a footplate, made using our 63mm CLS timber. This footplate is lined up with the wall frame that is coming up from downstairs so that the wall surface will continue smoothly all the way up to the roof. We glued and screwed this CLS plank down, going all the way along the edge until it reached the steel leg holding up the Skylight. We then sanded the steel leg, using an angle grinder with a sanding pad installed, and polished the steel, removing all the paint and little bit of rust. We then glued a vertical plank of CLS timber on to the steel leg, using PU construction glue and clamping it into place for 24 hours.
    Next, we carefully took another length of our CLS timber and glued it upwards to the 11mm OSB boards that coats the underside of the roof. This plank forms the top-plate for our wall. we then cut a series of posts, getting taller and taller, with an angled 32degree cut on top of each one, and nailed them every 600mm (2feet) along this section.
    This forms the Hall side of the wall, for the stairs, and will continue across the upstairs, under the Skylight, to meet with the toilet wall.

    There is a steel plate that is glued to the floorboard that ties the two steel legs together, all part of the structural framework for securing the whole Skylight against twisting and sheer forces coming from the winds outside. This means that we needed to glue a horizontal piece of timber on top of this steel plate so we undid the original screws, but first, having used the heads to bash “dents” in our CLS timber so we knew where to drill the clearance holes through the wood. We have been using our green laser line generator which is fully automatic, finding a dead vertical line and projecting a horizontal green line as well. We wanted to extend the stair wall so that it keeps the smooth flat surface going across as well. So, we positioned our CLS piece and bashed those screw heads after we had lined it up against the green laser line. Very very useful tool to have, the laser line generator!!
    We sanded the metal plate like we did before, then glued the wood down and put in slightly fatter and longer screws so it would grip the steel instead of the wooden floorboards underneath, to tighten the new bottom-plate down tight to the steel and the glue.
    Then, we glued another vertical piece of CLS timber on the other side of the steel leg, to finish off that leg beside the staircase.

    While the glue was drying and curing, we continued marking where the “four-foot” wall is located around the rest of the rooms, doing the Study room that is over the Entertainment room and Front Door, around the large Office come Work Room to the right side of the house and then positioned our green laser line to go back across the other two steel legs, to finish the fourth side of this Work Room. The next line to mark down is between the back two steel legs that will have wall to front the Shower room and Toilet, plus entrance way into our Storage area at the back of the house.

    Now we started gluing and screwing down one layer of CLS planks, to follow these new green marks around the floor. We did the three sides of the Studio come Sitting room (which is also our spare Guest Bedrooms, next to the Gallery), to form a space measuring about 6.2metres across (20feet) and about 4.8metres deep (16feet). This is the space between the “four-foot” walls so that is not walking around head clearance, the actual 6foot clearance space is about 4metres (12feet) across, maybe a bit more.
    Then we laid down shorter pieces of CLS timber to form the Toilet, which measures 1280mm (4feet) across by 1800mm (6feet) deep. We put in a double layered wall for sound proofing purposes, and also, to allow a vacuum pipe to come up from below so we can plug in our brush and tube to our central vacuum system, for hoovering the upstairs rooms. The waste sewage pipe is also fully hidden inside the right side wall, plus also it will hold the steel framework that will support a wall mounted toilet bowl. The basin will be located at the back of the room under the sloping ceiling.
    The Shower Room came next so first, we glued and screwed down two lines of CLS planks going across and pass the two steel legs, heading towards the front of the building. This wall is the entrance way into the Office come Work room. Now that we got this line of wall done, we can work backwards towards the Toilet and put down the second wall on the other side of the Shower room. This room measures 1100metres (3½ feet)wide and 1800mm (6feet) deep again.
    Now we laid down a line of CLS around the circumference of the Office Work room, joining back to the piece going across the steel legs. This wall is also double layered so that the steel legs are hidden away so we don’t have unsightly “boxing” sticking out in our rooms. Nice and Neat!
    Finally, the Study room, which is a L shape room, had its line of foot-plates put in as well, joining up to the side of the Office Work room, including a short double skimmed wall as well for more sound proofing. The last line is the one going along the edge of the Stairs and out into the middle of the Skylight. We had to put in a “kink” when we reached the last section going underneath the Skylight, because the wall needs to align to the metal tie bar and the glazing rafter so that the wall surface itself can go up and neatly meet the wooden beam that is supporting the double glazing glass units. So the daylight is divided into the Hall and the Stairs, and for the Study room.
    This “kink” will have a gentle 45degree angle put on it, rather than a sharp right angle turn to the wall surface.

    We then put on two of the three horizontal utility rails, one for the Air Channel, including putting on the MDF 6mm pieces. Then, we put on the lower half of the Utility Channel and that is where we got to. We didn’t have any fermacell sheets sliced up into narrow 175mm wide strips. So, we are going to do that later.

    First floor foot plates

    First floor foot plates

    That concludes this little section of work, to basically define all our shapes of all our rooms upstairs. We can now do something else, for a change. And, we have decided to go and build our cold water header tank, that sits behind the Shower room. We want to get on with implementing a lot of our utility services like water and air ventilation, so we can actually start having the chance of having real running water in the Kitchen or Toilet etc. yippeee!

  • Constructed Finishing Surfaces for the Walls in Great Room

    We spent the last one-and-a-half weeks doing the work of building up the double layers of finishing surfaces for all the walls. Now that the floor is done, we can construct the various layers of the wall surfaces. We tackled doing the first base layer of 18mm OSB boards for this stage of the work in the Great Room.But, we need to make sure that we have put in the required conduits from the Utility Channels, going up to the lighting channel running around the top of the walls, going to the upstairs Gallery and so on. This included checking the hearing loop wiring that we had already fixed up above the doors and windows. It is a standard network cable, made up of four super-twisted pairs of thin wires and we wanted to make sure that a loop amplifier could generate a good strong signal, using this choice of cable. Normally, a induction loop that is fitted to a room is usually a single solid copper core wire but instead of having to buy this wire, we had loads of CAT5 network cable so we used that instead, plus also, this allowed us to experiment because, an electro-magnetic field is generated by two main variables, one is being the amount of current you can shove down the wire, or, increase the number of turns you have in the complete loop, or both, to strengthen the power of the magnetic field, hence making it louder for hearing aids users. So, we pulled out our existing hearing loop amplifier we had in one of our temporary bedrooms, and connected it up to our new network cable in the Great Room. Just by connecting the four twisted pairs together, so that it formed a single “wire”, worked just a treat. We even quickly tested the next configuration by joining up two twisted pairs together and then got it to go around the room twice before the signal ends back to the amplifier. That works nicely and it possibly sounded louder too. At this point, we accepted that the wiring was working just fine and we could continue with building up the wall surfaces, and bury and hide this network cable inside the wall. We won’t be able to replace it etc. It was a compromise between installing 35metres of black plastic 20mm conduits like we have done for the other rooms, or install the wire directly inside the wall and have the two ends dangling in our control box.

    But first we nailed up a complete loop of 63mm CLS timber pieces near ground level that we deliberately left for construction later on, to make it easier to lay down the floorboards. The rail sits the top of the Air Channel which is 150mm high.

    The next task, we noticed that our existing sixteen air distributors needed to be more secured so we went around anchoring them into place so they did not protrude beyond the CLS rails, avoiding being squashed when we put up the OSB boards, or fall backward into the wall cavity. We used little stainless steel screws to lock each plastic unit into place.

    The next job is to put in the Air Channel backing strips, to guide the air around the room and float gently outwards. We use our stock of 6mm MDF strips to go around the entire room but we discovered that we were short so we went out to buy another sheet of MDF material and sliced it up into more 150mm wide strips.

    We sealed both the MDF strips along the top and bottom edges and also the Air Distributors themselves so all the air will get sent out into and along the Air Channels and into our Great Room.

    Great room air outlets

    Great room air outlets

    We also painted the lower 50mm black so no one will be able to sneak a look along the carpets and perhaps notice something pale lurking inside the wall!

    We put up the top rail precisely so that our lighting channel is one aluminium strip gap under the slope of each roof. We had to do four sections of the roof, the “A” section which has a 32degree angle slope, then coming around the corner, is the “P” roof which is a 40degree angle inclination, which reaches the “O” section that is even steeper at 45degrees and finally, a short “N” section which is back to a 40degrees angle. We wanted to be able to slide in our lighting modules which will be housed in an aluminium extruded U-channel shape. It is quite thick walls so it can spread the heat from all the individual LEDs but these long units needs to be able to slide in and out for servicing, hence why we needed to make sure that the top CLS horizontal rail are positioned so that the metal U channel will slide in and rest on this CLS timber, after we have put on the wall boards.

    We then went around putting in a layer of glass wool horizontally, between the wooden rails so it fills the gap that would exist behind the OSB board and reduce the hollow sounds of wooden walls. This glass wool is supposed to be 100mm thick, but it is never is. We believe that the manufacturers are not careful enough when they squash the output of their factory productions into those rolls, ready to be transported. The gap that we are filling is only 38mm deep and so we staple up these so-called 100mm thick wool strips and they swell out only about 30mm or 40mm beyond the horizontal rails. This is sufficient for our purposes and the wall boards will squash this wool down and provide some degree of sound adsorbing filler, to make the overall resonance sound of the wall more solid.

    We then measured the two “control” boxes, one is the electrical junction box for all the cabling coming into the Great Room, as well as having a computer sitting there, looking after the various components that lives in this room, like lighting, sockets and speakers etc. The second cavity is over the doorway and that space will have the sliding door mechanisms and controls. Both of these boxes needs to have access panels and we will cut and remove the OSB sheet material later on after we have glued and screwed all the OSB boards up on the walls. Hence why we needed to measure the exact location and size of each box and its access hatch.

    Great room Control panel location

    Great room Control panel location

    Great room Door panel location 1

    Great room Door panel location 1

    Great room Door panel location 2

    Great room Door panel location 2


    One of the task we had to do before we got into putting up wall boards, was to re calibrate our two router machines that has tongue and groove cutters in them. We wanted to move the cutters further out of the machines so that they could cut thicker materials we may need to do in the future. But we needed to make sure that we set them exactly the same position so that the tongues and grooves came out in the same place as before as the walls coming down from the Gallery and the gable wall coming around each side of the Gallery, has already a groove cut into the bottom edge of the boards, ready to receive the new sheet materials later on. So, we readjusted the two routers so the cutters are now sticking out by 25mm, each tongue (and groove) are 8mm across at the widest point so in 25mm, there will be three tongues (or grooves). We have two machines because we discovered that these sheet materials, especially the OSB boards, are very slightly varying in overall thickness so you cannot just simply flip the board over and run the cutter on the other edges because that produces a very slight misalignment and does not bring the two surfaces to a smooth finish. So, years ago, we invested in two machines, one to do the tongues and the other one to do the grooves, without having to flip the board over at all. It produces a very very good joint that is very smooth indeed, and incidentally, makes a very strong joint as well, especially using PU glue too!

    Here, at this point, we started putting up the first layer of wall boards, using 18mm thick OSB sheets. We started on the wall that divides the Great Room from the rest of the house and the two nearest rooms, namely the Kitchen and Bedroom One. It goes under the Gallery, but we needed to connect to the existing wall that is already fixed to the upper half of the Gallery. It was a bit fiddly but we made it, on both side of the Gallery and concluding in the far corner where we got our 4foot wide window. Next, we tackled the two short ends, also cutting the top edge of the OSB board with the appropriate angle, to match the slope of the ceiling as mentioned earlier about the aluminium lighting modules.

    All our walls that goes up to the sloping ceiling are extra tall, measuring 2780mm or a bit over 9feet tall. That is just the wooden material itself, there is another 40mm gap at the bottom, and approximately 60mm gap at the top which makes the total height from floor to ceiling of 2880mm, or 9feet and 5inches!!
    And to just finish this little point, the middle of the room stretches up, and up, and up to our mobile lighting unit, hanging at the apex of the vaulted ceiling, is very nearly 4800mm tall. We know this because we could almost get a standard length of CLS timber to stand upright in the middle! That is nearly 16feet!!

    Anyway, we continued putting up the wall boards, having completed the two short ends, the “O” and “A” sections, and then we tackled the last long section that goes pass the Patio and Conservatory. We started at the doorway for the Conservatory and then worked back towards the “O” completed wall. It is much easier to put in the last piece of OSB board, cut down to exactly the correct size (and sometimes angle) and slide it into place by using the completed wall surface to slide along and force the joint nice and tight.

    The other thing we needed to do special along this section, is the Dormer where we got our exposed rafters and gable triangle section of wall that defines the start of the Conservatory. We are wanting to mount our lighting modules, the same aluminium U channels, to slide in but this time, to sit vertically so the light output will shine upwards into the Dormer section. This meant that the top edge of the OSB board is shaped differently and also it is slightly lower as well. The aluminium channel will sit on this cut edge, providing a small gap underneath, approximately 15mm, to allow for our electrical cables to run pass and continue the circuits. We tested this arrangement by screwing up a small piece of OSB in various positions and holding up a piece of our fermacell plasterboard and tried to slide in the aluminium channel. We discovered that the vertical layers of fermacell plasterboard that we had fixed up a couple of weeks ago, and painted white, was very slightly causing the metal U channel to jam. So, we scraped the bottom edge of this vertical fermacell material, to increase the gap, and angle, to allow the metal channel to slide in. We used our trusty little surform “razor” tools to go along the entire length of this Dormer section. We have exposed the grey interior of the plasterboard again so we will have to paint that little bit again!

    Great Room OSB Finished

    Great Room OSB Finished

    Great Room OSB Finished 2

    Great Room OSB Finished 2

    Great Room OSB Finished 3

    Great Room OSB Finished 3


    This pretty much finishes the first stage of constructing the wall surface, the basic “rough” structural walls and they are now ready for the next stage, when we are ready, of putting up the fermacell plasterboard, shaping them nice and neat and painting them to the required colours, whatever that may be!!
    But, for now, we are going to have a change of scenery and go back upstairs to carry on getting the First Floor rooms mapped out and some of the wall’s framework built so we can build things like the water header tanks and ventilation ducting etc. We wanted a change! But, We promised ourselves that we will get back to the Great Room and finish it off during the Summer and present a completed “show room!”

  • The Floor Is Completely Filled and Reassembled Permanently

    We spent the last two weeks in getting the flooring in our Great Room permanently fixed down at long last. We had originally laid the floorboards down a couple of years ago, but we weren’t ready to glue and fixed them down, because we needed to get the insulation put into the roof rafters and any rubbish pieces left-over, needed to be shredded and ready to put under the floorboards in the Great Room. The shredded pieces was used to insulate the room against the cold concrete foundation, but also to insulate against the heat that will be rising off the buried Energy Module we had under the concrete slab. It could reach 90°C and we didn’t want that kind of heat to flow into our Great Room, so we knew that we could put all the final rubbish and trimmings, under the floorboards and also protect ourselves from the very hot Energy Module.
    The first thing to do was to empty the entire room of all the items we had stored in various corners and move everything into our Kitchen, so we could lift the floorboards up.

    We started at the right hand end of the room, standing at the hallway door but it was locked into place by the tongue and groove system. Therefore, we had to move all the floorboard pieces towards the left end, by about twelve inches and keep each row of boards unconnected so we could move each row more easily. Another thing we did during this process, was to label all the individual piece with a row “letter” and “number” for each piece as the whole floor have been measured and laid down to fit the two doorways etc. We didn’t want to mix any up and run into trouble later on. So we pulled up three complete rows at the beginning, under the “O” window, looking out to our swimming lane at the back, and started filling in the huge pile of insulation boards pieces we had prepared from our time of doing the roof rafters last year. They are stored upstairs so we started chucking them off our Gallery, bit by bit!
    We also had six “ton” bags of random odd sizes and pieces of PU foam rubbish as well and we dragged each one down the stairs and along the hallways to the Great Room.
    And not forgetting a room full of “fluffy” stuff we had previously generated, being stored in our Entertainment Room downstairs!


    It is a slow job of laying down sheets of the insulation boards, skipping around air ducting, conduits, water pipes and so on. Building up the layers until we reach underneath the cross rails that is 63mm from the top. That is about 320mm to 330mm of cavity to fill up, depending on how thick the original concrete slab was. We first tried to fill the remaining space with fluffy fragments but we discovered that it is so light and “fluffy” (Of Course!!), that it would not keep still. We wanted to glue the floorboards down tight on the wooden framework and this fluffy stuff kept going everywhere!!

    Starting to fill Greatroom floor

    Starting to fill Greatroom floor

    So, we switched over to Plan B, and laid down 100mm layer of glass wool over the fluffy stuff. This helped greatly to contain the fluffy stuff and made it much easier to vacuum the rails clean and get the glue down without any problems.

    We used our spray gun foam to squirt a line of PU Glue Grade foam and then lay a floorboard on top. Next, we put in a collection of 50mm screws in each cross rail, to make sure that the 22mm thick chipboard boards will squash tight down onto the glue etc. For our first row, it started off at the left hand end, with a small piece, to bridge over the smaller spacing off the framework enough and the next board goes into the tongue and groove joint, getting knocked sideways to make sure the joint is nice and tight. This joint is also glued with more of our PU foam and this board is screwed down too. The final piece, is another larger piece, to finish the row. Each row always has three pieces but the first and last piece changes in size by approximately 600mm, to make sure that all rows do not have any joints aligning up consecutively, to improve the structure and strength of our floorboard generally.
    We then carry on doing each row in turn, making sure that we knock each row tight into the previous row, by using a small piece of the same chipboard material that has a groove on it, plus a piece of CLS timber glued on to the back edge so we can thump it hard using a club hammer, to provide a reinforced tool, that slots into the tongue on the board and that will not damage it, while we are knocking each piece into place.

    First row down

    First row down


    One of the jobs we had to do while the floorboards were up, was to seal the ventilation ducting to our wall distributor modules. The orange flexible 50mm conduit comes from a four way splitter and each duct goes off to various locations around the wall. Each end needed sealing up with aluminium sticky tape.
    We got to the spiral staircase position, row number “G” and “H” and one of the thing to do was to reinforce the flooring, to make sure that this zone is strong enough to support the entire stair case, in one single small spot. We are going to have a pillar going up the middle of the spiral stairs and it measures 200mm across, which will be the main load bearing element. So, we built up the framework structure, putting in a zone of 400mm by 600mm of solid layer of CLS timber pieces, all glued together into a single block. This is then supported underneath by a couple of sturdy cross pieces using a wider 89mm CLS pieces and then finally, underneath those two pieces, we put in four legs down to the concrete floor slab, two legs under each cross piece. Everything glued and clamped together.
    The final top surface was planed smooth, to remove excess glue and excess timber and made it level across neighbouring floor joists.
    Reinforcing floor for spiral staircase

    Reinforcing floor for spiral staircase

    Staircase Reinforcement smoothed

    Staircase Reinforcement smoothed



    We built this reinforced spot near a couple of existing legs so we have six legs in total in the immediate zone but there are a further two legs only 300mm away and also the floorboard itself will help spread the load right across all the framework and in turn, down to the concrete slab.One of the things we tried to do, is to run our shredding machine and get the output to go straight down into the cavity space under the floorboards but it proved rather awkward to generate a constant flow of shredded bits coming out of the machine. The machine itself couldn’t shred the foam and let the pieces fall naturally downwards underneath the machine, it was “fluffing” up all over the place! So, we tried to combined the large vacuum machine we had used before, but instead of filling up domestic bin liners of foam bits, we tried to connect a plastic conduit to the bottom of the plastic bin liner so that the shredded bits would fly down the tube and into the floor cavity. But, as soon as the bits started building up in the bottom of the black liner, it would block the output tube and no more fluffy bits would fly along the tube!! We abandoned that method and just took each lump of foam and fitted them in a collection of random positioning, mixed with fluffy shredded bits we already had done months ago. We also took many of these lumps and arranged them into larger blocks before putting more fluffy stuff in on top.
    It was a bit fiddly but we got there!

    We got the middle section where our Utility services runs across the room, heading at a diagonal for half the distance and then straight to the Conservatory doorway point. We will have air, electricity, compressed air, and hot and cold water coming in and out of this zone, so we needed to seal off the rest of the floor on either side, to stop an avalanche of fluffy bits falling into this section. So, we cut pieces of 25mm thick foam sheets and glued them vertically into place. The 100mm “purple” air pipes, four of them in total, were supported with lumps of foams and then held into place through these vertical barriers. All the other utility like water pipes was already fixed in a neat line coming through a sheet 12mm board of plywood.

    Now, we tackled the last furlong of the race of filling the floor and gluing and screwing down the floorboards, to the left of the Utility service channel, by removing all the floorboards and heaping them up over on the finished side, stacked in the correct order.
    We went around the edge of the room, nearer to the outside world, and put in a solid arrangement of narrow strips of foam boards so that we maximise the heat retention for the house against any temperature differences in the outside world.
    This left the middle area of the space to be filled up so we spread out all our remaining chunks of foam rubbish, and poured in all the last of our fluffy bits. And finally, topped the whole lot with two or three layers of 100mm glass wool, depending on how much there was to finish off.

    Starting on second half 1

    Starting on second half 1

    Starting on second half 2

    Starting on second half 2

    Second half nearly filled

    Second half nearly filled

    Second half ready for floor boards

    Second half ready for floor boards


    We then could get on with laying down the final rows of the floorboards, getting them glued and screwed down, all the way to under the window looking out to the Loke. The rows that went over the Utility Services, we had to mark very carefully to exactly where the floor support framework is located because we needed to know precisely the positions of the “hatches” that we will cut out after the floorboards have been glued together using our construction PU glue instead of the PU spray glue. We also put a layer of parcel sticking tape on the surface of the framework so any excess glue that may leak through the joints, won’t permanently stick the floorboards down to our wooden framework!!
    The final job was to get our track circular saw and slice down 22mm (and a bit), to cut our floorboards to those hatch markings. It was a nervous moment because we couldn’t undo any of these cuts!! But, It Turned Out OK!!

    Central Service area Hatches made

    Central Service area Hatches made

    That concludes permanently building the Great Room flooring, at long last! We can get on in building the walls next!

  • Dismantling Of Temporary Flooring

    We spent the last couple of days dismantling our very lovely and useful temporary flooring, the false floor that allowed us full and safe access to our sloping ceilings in our Great Room, plus also the Dormer section with its exposed rafters as well, plus also access to our Skylight too.
    The first job before we unscrewed anything, was to give the surface a thorough clean by sanding the OSB boards using our 9inch rotating sanding machine with a 40grit paper loaded on the head. It cleaned away plaster blobs, paint blobs, PU glue blobs and allsorts! It did a very good job!

    Next, we removed the 18mm thick OSB boards, unscrewing each one at a time and carefully removing the sheet back to the Gallery and brought through the doorway and stacked up to one side, to be reused later on when we build the First Floor rooms. We had to blast each the screw heads to clear out any rubbish. We worked our way from the furthest boards around the Gallery, taking up the last few sheets right next to the Gallery.
    Then, downstairs, we tackled the job of dismantling the forest of wooden legs using ladders, and then unscrewing the long horizontal wooden beams as well, including the horizontal rails we mounted on the walls too.
    We put back these CLS planks back into our stock pile, ready to be reuse for construction of the framework of the First Floor rooms.

    Temporary floor removed (1)

    Temporary floor removed (1)

    Temporary floor removed (2)

    Temporary floor removed (2)

    Temporary floor removed (3)

    Temporary floor removed (3)

    Temporary floor removed (4)

    Temporary floor removed (4)



    That concludes the massive and complicated job of getting the upper half of the Great Room finished including putting in the foam insulation, vapour barrier, plasterboards, painting, veneer on rafters and building of our lighting gantry plus up inside the Skylight too!!

  • Cut New Trench and Install Conduit for Full Fibre Optic TelComm Cable

    We were having an upgrade of our phone and internet connections but the old conduit that we had running from the telegraph pole out on the Loke, going all the way to our Garage, seem to have been blocked or damaged by something. It is possible that our twin wall corrugated 50mm plastic conduit that we originally installed back in 2010, may have suffered in a location where there was more load pressing on it than we expected. The original phone line is still working and it even moves so it probably would have been ok to thread in the new fibre optic cable but we decided to have a complete rethink of where we wanted our new high speed data communication channel to be routed and now that we have our main house constructed and we got our Tech Cupboard available, including already having a WiFi hub and switch located in there.
    So, over the last four days, we decided to lay in a brand new conduit, a black 20mm thick walled plastic pipe, from the Tech Cupboard, under the floor in the Hallway, around into the Utility Room and through the Utility Cupboard and through the wall to the outside, all below the floorboards, right down near the concrete level.

    Then, outside, we cut a 18inch 450mm deep trench, using a narrow long bladed spade, coming away from the building at right angles, curving around in front of the front porch legs and near the fence line, continued all the way past our house and eventually, reaching opposite the telegraph pole that is located on the other side of our Loke.

    Fibre Conduit trench (1)

    Fibre Conduit trench (1)

    Fibre Conduit trench (2)

    Fibre Conduit trench (2)

    Fibre Conduit trench (3)

    Fibre Conduit trench (3)

    Fibre Conduit trench (4)

    Fibre Conduit trench (4)



    We then had to cut our way across the Loke, using our electric super heavy “kango” road breaker machine, to cut through the highly compacted tracks, to reach the telegraph pole. We were careful during this segment because there are existing utilities running up and down the Loke, so we only went down 12inch 300mm, to make sure we avoid accidentally hitting a gas pipe, mains electricity and water. We did find a virgin media conduit and also we did discover our own previous conduit for our telephone and we skipped underneath both of those ones.
    Fibre conduit across Loke (1)

    Fibre conduit across Loke (1)

    Fibre conduit across Loke (2)

    Fibre conduit across Loke (2)

    Fibre conduit across Loke (3)

    Fibre conduit across Loke (3)



    The conduit pipe snaked around to the back side of the pole and then climbed up another 3metres, held on using three copper pipe clips and stainless steel screws.

    The next task was to thread the fibre optic cable that was coiled up and left behind by the engineers, waiting for someone to thread it into our garage. So, we did the job for them!!
    We sucked a length of string through the pipe using our most powerful vacuum DIY cleaner machine and join the end with the fibre optic cable and reversed the process by pulling the string back. We had measured forty-three metres of conduit that we used to go from the Tech Cupboard, all the way to ten feet up the telegraph pole! It was hard work pulling that length of cable back through the conduit, but, slowly, and finally, we made it !!

    Fibre comes into Tech cupboard

    Fibre comes into Tech cupboard


    At this point, there was a pause of some days while we waited for the OpenReach engineers to come back with the necessary fibre optic junction box and modem which will convert the laser light into an electrical network signal and that point, we can plug it into our network, and it is all done .. Just Like That !!
    Broadband Fibre all connected

    Broadband Fibre all connected


    We now have 500 megabits download speeds and about 75 megabits of upload speed, all only costing us a very similar price to our old broadband connection! Amazing!

  • Exposed Rafters Covered in Veneer in Dormer Section Over Conservatory

    These last few days had us covering our rafters we have exposed, seven of them, situated over the section where we have our Conservatory, like a Dormer sticking out of the roof and will eventually join to a glass structure that will be our Conservatory.
    We never intended to have exposed rafters in our original design but the idea came along when we were building up the ceiling in the Great Room and we wondered how to “fill” in that Dormer section and it came to us that we could leave it open and have exposed rafters, to make it a talking point for the room, especially if we also installed discrete lighting to light up inside the Dormer as well.

    This means that we need to cover up the exposed rafters, which were never designed to be visible and rather ugly to look at. We found some natural looking wood effect veneers and bought three sheets, each measuring 3000mm long by 1300mm wide, and only 0.7mm thick.
    They are resin coated paper, just like the original Formica products are.
    The rafters are 400mm wide, plus 11mm for a strip of OSB strip that has been fixed to the front to cover up a rough edge, which might have made it difficult to stick our veneer to.
    This means that we can get three strips off a sheet, measuring 433mm wide. One of the sheets came damaged on both edges (we got a 50% discount on the price and that is a bargain as we can easily use the major middle portion and only lose about 5%!).
    We then found an old roll of backing wallpaper we had loads of, in our garden shed and this provided a stiff thick pieces of paper to place on each rafter and fold the ends at where the rafters disappears into the surrounding plasterwork. Our first attempt didn’t work out too well but we were able to reuse the cut veneer on another rafter, after trimming it down so the angles became closer together against the wall and ceiling.
    We joined all our track saw segments together to form a single 3.5metre long track and that allowed us to cut the sheet into the 433mm strips. We also changed the circular saw blade to a fine tooth one, having lots of tungsten carbide teeth on it, to minimise the force on the cutting process.
    Another aspect of our first attempt that we forgot to recognise, is that the paper template needed to be put on backwards because we are cutting the veneer strips with the face side downwards, to also minimise any chipping on the cut edges as the rotating saw blade always comes around and cuts upwards.
    We had measured rafter number 3, on the right hand side of it and therefore our first attempt was able to go over to rafter number 5 but on the left hand side instead .. phew!
    Our second attempt, we thought that we were being careful enough but we discovered that one of the ends didn’t align very well, and unfortunately this time, we could not use it on the other rafter because it turned out to be too small as well. This meant that we needed to slice up our third sheet for another 433mm wide strip. Oh Dear! But Thank Goodness that we bought a spare third sheet!!
    We change the method of placing the thick paper up on the rafters and this time, we used the straight edge to align it along the bottom edge of the rafter, stapled it on to the rafter, making sure it was nice and flat. Then, we bent the two ends carefully one at a time. This time, it was much more successful – Phew!

    Paper used fror templates

    Paper used fror templates


    As you can see, we now have a large pile of backing wallpaper in a heap!
    We now have a collection of veneer pieces, ready to go on the seven rafters, ranging in size from two tiny little exposed bits of a rafter, right up to the longest single rafter in the middle of the Dormer.
    Next, is to glue them into place. We are using a brown universal “stick-all” glue that has proven to be very good at sticking many types of materials together. So using a fine tooth notch trowel, we coated the sides of the rafter with a complete covering of the brown glue, pressing the glue hard into the wooden surface, which we had blasted with our compressed air to get rid of as much dust as possible. We carefully placed the veneer piece into place and then pressed hard to work the glue into the veneer as well. Each piece still got it protective plastic film stuck on so we could press hard with our fingers and occasionally leave behind little blobs of brown glue. Mind you, we had to be very careful not to touch the surrounding “beautiful” white surfaces and alas, we have accidentally did leave tiny blobs there too, which we dealt with later on.
    We made sure that the veneer pieces were big enough to overlap the bottom edge of each rafter because we had noticed that some of them were not completely straight. This meant that we wanted to trim the veneer so that is follows the ever slight bend of the rafter as closely as possible. We also ran a bead of the brown glue behind each edge of the veneer and used a small scraper to carefully fill in and smooth the surface.
    We bought a trimming router bit that is a solid tungsten carbide blade that has been grounded into a sharp spiral shape, so it actually will slice the thin veneer some what like a pair of scissors would do, making sure that it cuts downwards into the veneer.

    It went very well indeed using our smallest router machine and finished off the trimming with our wiggle saw that has a very fine teeth blade and also the blade is designed so it is flat against the surface you wished to slice to. We then sanded the front facing surface to remove any excess glue and ever so slightly wavey edge.

    Rafter sides laminated

    Rafter sides laminated


    The final task was to cut narrow strips to go up on the front of each rafter. The rafters are approximately 63mm wide, but just in case they varied, we sliced 75mm wide strips off our remaining 3metre piece and covered the seven exposed rafters, the two smallest ones on the outside, measuring 500mm on the front, then the next two inwards measuring 1200mm, then the middle pair measuring 1750mm and finally the single central strip measuring 2400mm. Then, we had a small left-over piece where we used a pair of heavy duty scissors to cut the top end at the correct angle, making slight adjustments until it fitted nice, and transferred this little template to the strip being fitted to that particular rafter. Then carefully, measured the exact length, added 10mm and cut the bottom end. The extra 10mm then allowed us to slide the front covering strip sideways so that it overlapped both sides and ready to be trimmed later on. We proceeded to do the other six strips and the last one, the centre one, had a more complex shape for the top end to cut, but we managed it.
    And finally, we cleaned their back sides with methylated spirits, put a thin layer of the brown glue all over it and then rolled each strip onto the rafters, to dry and cure overnight.

    The final step was to trim them using our router again with that fancy cutting bit and very carefully cut the tops and bottoms where router couldn’t reach, using the wiggle saw. Then, using a metal file and a fresh fine sanding paper stuck to a length of CLS timber, we rubbed the edges to take off a tiny bit of excess material and make it all smooth. We pulled off the protective cling film and doubly made sure that the edge was nice and neat.
    The final job was to scrape off blobs of the brown glue that we had managed to get on our beautiful white wall by using a razor blade and then paint over any remaining colourations.

    Dormer rafters complete 1

    Dormer rafters complete 1

    Dormer rafters complete 2

    Dormer rafters complete 2



    This complete the coverage of the three visible sides of all seven rafters and turn them into  “look-alike” solid wooden plank of timber.
    This concludes the work on getting the upper half of the Great Room completed and now we can dismantle the working temporary platform and start work on the lower half of the Great Room!!

  • Great Room Ceiling, Lighting Gantry and Gallery Wall All Prepared and Painted

    Since our Christmas break, these last few weeks, we have been working on the upper half of the Great Room, including getting the Gallery’s wall constructed with all its gaps (ready for shelves and cupboards), above and below the Utility Channel plus the doorway too.
    Since we had finished the Skylight and didn’t need the use of the mobile platform anymore, we constructed the remaining wall framework in the middle of the Gallery, between the metal legs that are holding up the Skylight. We put in two more “gaps” for 600mm wide shelving units and cupboards, alongside a standard 800mm wide doorway that gives access to the First Floor room beyond. The wall surface was built up to match the rest of the wall that goes past the Gallery and down to the Great Room, forming an internal gable divider to the rest of the house.

    In the meantime, the fermacell boards that got put up before Christmas, had all their joints thoroughly sanded using our trusty old belt sander with a base plate fitted that allowed us to remove any slight ridges formed between sheets. We decided that because we had a solid OSB backing layer all over the ceiling, we didn’t have to “Tongue and Groove” the thin 10mm thick edges of the fermacell boards, only relying on the PU construction glue in the joints to hold everything tight together. This meant that there were a very slight variations in how flat we managed to staple up each sheet and the joints had a tiny steps in them. So, we came along with our belt sander and using a 40grit belt, went around “ironing” these steps and smoothed out the whole surface.
    The Dorma section was similarly done but had to be done by hand as the machine was too large to fit inside among the rafters!
    As that was happening, the staple holes and the now smooth joints were filled with good quality decorators filler. The initial wall, the “A” section, was done using a standard spatula tool but then had the idea of using a piping bag so we raided mum’s baking supplies for those disposable plastic bags and nozzles! It was a very good idea as we could squirt in the filler into the staple holes, after we had blasted them out using our compressed air, and leave a little sausage of filler proud on top, to allow shrinkage. On the first section we were doing, using the spatula, discovered that the fermacell plasterboards were so absorbent that they sucked the water content out of the filler hence shrinking it down in the holes, causing us to repeat the filling again. But, using the piping bags, it was much much better, in both time and efficient use of the filler.

    A roof of blobs

    A roof of blobs

    P Roof filler dots

    P Roof filler dots



    The intersection angle between two roof surfaces were trimmed and also smoothed with heavy use of the sander and manually using a surform shaving tool. We did the “M” and “N” long sloping junction, as well as the Dorma section over the Conservatory, showing off the exposed rafters. These were also filled in with filler especially around the exposed rafters so it comes out all in a straight line in both surfaces as they meet together.

    Then came the messy job of rubbing down all the filler! Fortunately, our orbital sander had a vacuum port, to suck up 99% of the dust. We had another lovely tool to help us with this task, a 9inch rotating disc sanding machine attached to a long handle grip, with the vacuum tube running up the handle. This made quick work on sanding down all the surfaces and only needed hand sanding around the edges and corners.
    Oh yes, we filled in the three corners between the sloping rooves, by using a piece of 110mm diameter drain pipe as a shaped spatula, to create a smooth curved surface to smoothly sweep around from one surface to the next.

    Initial sanding A

    Initial sanding A

    Initial sanding O&P

    Initial sanding O&P



    The Gallery section also had all the staple holes and joints filled in, including rounding the corner on the three edges around the doorway, and then all smoothed down too.
    The next task was to drill large holes for our lighting units we are going to have in the two wings of our Skylight, the flat strips that are coming perpendicular out from the Gallery wall and joins to the Skylight. We bought a sharp tungsten carbide teeth circular cutter measuring 95mm in diameter and proceeded to drill a set of eight holes staggered across the surface on each wing.
    Gallery Wall Built

    Gallery Wall Built


    We also lowered our mobile Lighting Gantry unit and turned it upside down on four trestle tables so we could finish with that as well. We first installed the aluminium U-channel bars, which will contain strips of LEDs to shine down the slopes of the ceiling, all the way around the edge of the lighting module. Then we surform the fermacell edges that overlapped the U-channels so that both came together with a smooth graceful line. While we remembered, we stuck down a line of masking tape inside the aluminium channels, at the base so that we had still a bare strip of metal after we had painted them white, for the LEDs to have a good thermal conductivity to aid keeping them cool and long lasting. Most LEDs products these days are over driven and have very poor thermal cooling, and unfortunately, these lamps have short lives. We do not wish to suffer this fate so our LEDs will be under driven, well cooled and hopefully long lasting- fingers crossed!
    Anyway, back to the gantry module, we then sanded the flat surface to make sure the joins are smooth and any screw points that pushed a little hump out, is all cleared away and left flat and smooth. Then, we drilled a further twenty-four holes, equally spaced out all the way along the module, only having to adjust very slightly their position twice to avoid internal metal framework. We now have plenty of downlighters to help illuminate our Great Room!
    Gantry Spot light holes drilled

    Gantry Spot light holes drilled


    The other thing we did to the lighting module, was to take one length of the aluminium U-channel and cut a very shallow groove inside the metal surface, near the front so we can slide in a short length of plastic diffuser in the section that will look over the Gallery under the Skylight. We didn’t want to have the LEDs fully visible, poking their bright pin prick light sources at you, and also to avoid being able to see the electronic control circuits as well.So we were getting closer to the actual painting at last. We double checked everywhere, put in any filler in missing holes and scrapes, installed a little conduit under the cupboards on the Gallery for future lighting options and then gave the whole area a good and thorough vacuum and sweep. Also washing with plain water all the painting surfaces with a floor mop to remove any dust, sanding a couple of missed “bumps” along the way!
    We then covered up the naked exposed rafters with masking thin plastic sheets, to protect the wooden surfaces so they can have the “pretty” veneer stick nicely to them .Finally, we can actually proceed to the painting at last! We got out our paint sprayer and got our 10 litre of white emulsion paint. It was quite thick and the sprayer said that it should be diluted with water, to make it thinner. It recommended a minimum of 10% of water and that the paint dribbles off smoothly and doesn’t form “bumps” or “tracks” in the paint before settling down. We ended up diluting it to about 12.5% before it looked ok. We had two spray nozzles and the wider fan nozzle, doing 50degrees wide fans, seem to be making a slightly bumpy surface on a sheet of insulation board. We switched over to our second nozzle, which produces a finer and narrower 30degrees fan, seem to be better.
    So we proceeded to spray the ceilings, starting on the “A” section and working around clockwise. We managed to cover almost all the ceiling surfaces before we ran out of paint. We were surprised that we couldn’t get the 10litres to last long enough to cover all the ceiling and walls. The instructions on the paint pot claims that it should cover about 130 square metres and we estimated that our Great Room ceiling and Gallery is about 70 square metres. It looks like that we had put it on too thickly. Then, we spotted that the paint pot also said that they recommend diluting their paint 25% if one was using a sprayer. Oh Dear!!

    Paint spraying equipment

    Paint spraying equipment


    In the full daylight on the following day, we also noticed that we had missed sections. We were painting in the late afternoon and we hadn’t had enough lighting. We are learning!!

    Another side-effect we have discovered, is that the fermacell plasterboards, which are made up of newspaper pulp mixed in with the gypsum, goes “hairy” when we do heavy sanding on the surface, like when we had to smooth out a joint. The paint has soaked into these hairy bits and produces a textured finish. But fortunately, we also discovered that by just simply sanding the surface with 240grit paper, it knocks off the hairy bits completely in one single swipe of the sanding paper. So, we went around the whole room with our large circular sanding machine, loaded with 240grit paper and got everything nice and smooth. This is good news and rather pleasing that it came out very nicely indeed.

    The next discovery, was that we had missed several staple holes, staples that were not fully hammered below the surface and various gouges that revealed themselves by the high contrast colour of the white paint. We went around with more filler and touched up these spots.

    Our new tubs of white emulsion, this time buying Dulux branded paint and discovered that their domestic grade paint is much thinner than the previous one we were using. We only needed to add 10% water to get it running and dripping quickly, as recommended by the sprayer people. We then used the first nozzle, the 50degrees fan and proceeded to finish those area we undone and we had to stop early to allow all that lot to dry and harden.

    On the following day, we went around sanding smooth all the blobs of filler we had put on, gave the Gallery wall a gentle rub to nock off the hairs and even now, we keep coming across a missing staple hole once or twice. There was a case where we had accidentally put on a strip of the fermacell back to front and the manufactured grid pattern was visible. This was the narrow strip up inside the doorway on the Gallery, so we diluted our filler mixture and applied a thin layer all over its surface using a wide bladed scraper. And just to finish off our morning’s work, we proceeded to spray the second coat of “Pure Brilliant” white paint everywhere, using well over another 15 litres of paint. It seem that we cannot help putting on more paint than what the tin says. We just shrug our shoulders and it is not a great expense, considering the cost of the underlying material we had already invested in.
    After lunch, we rubbed down that doorway surface, which came out extra smooth and gave that a coat of paint. While we were waiting for the second coat to dry, we remembered that we needed to cut two pieces of the aluminium U-channel, for the two Skylight Wings, to provide more lighting output to shine down the slopes of the ceiling. We took the metal channels and cut the grooves to hold the plastic diffuser strip and drilled a cable access port plus screw holes to fix the bars up and stuck down a strip of 19mm wide masking tape, like before, to maximise thermal transfer of heat being generated by the LED strips. Finally, we gave them a spray of paint as well.

    On the morning, the surfaces were again very gently sanded, to get rid of more hairy patches and after lunch, use our finishing coat of white paint, this time using a brighter Absolute White colour, which claims that it will reflect 90% of the light back into the room. The colour of this Absolute White is definitely “whiter” than the previous paint which is called Pure Brilliant White and it says that it has a 80% reflectivity of light. This paint has a very very very slight yellow tinge to it, especially comparing against the new Absolute paint we had put on.

    Upon the following day, the surfaces are looking much much better and we are definitely winning against any more hairy patches showing up. In the sunshine, we could see several patches of a slight difference in “Whiteness” so they got an extra squirt from the spray machine. And, after lunch, those patches have disappeared and it is looking very good indeed. We have decided that the job is finally done!

    All painted (1)

    All painted (1)

    All painted (2)

    All painted (2)

    All painted (3)

    All painted (3)


    There had been a great deal of learning involved during this particular task of building, preparing and finishing the final “plaster” layer for the ceiling and walls. We now know what to expect, what to do, when we repeat this kind of work again on other parts of the house, and it should be easier and quicker.
    The next job to do, before we dismantle the temporary flooring, is to cut and shape our wood effect laminate sheets and cover the exposed rafters at the Dormer section over the Conservatory.

  • Finishing the Skylight in Great Room – Part 2

    We resumed work on the Skylight on Monday after the Christmas break and we got on with filling all the little staple holes all over the fermacell boards with a gypsum-based filler which has extra additives to make it extra sticky and shrink proof. One of the things we thought that would make a better job of sticking this filler into these tiny holes, is to air blast them clean of any crushed fermacell material when the staple was fired in. This will provide a longer term finish.
    We also ran a bead along the joints and also the corners as well. We then ran all over the woodwork and filled in the tiny little nail holes in the beading that holds up the double glazing glass units, filling in knots holes and the various joints along the ridge beam and metal work.
    All these fillings were sanded down and where discovered, refilled any holes that did actually shrink after all. This is a bit strange since the filler boast that it doesn’t shrink so we concluded that the water is being struck out into the dryer fermacell material (which is gypsum and newspaper mix) before the gypsum has the chance to form the lattice work during the curing process. Another job we did was to trim the bottom edge of the vertical sections of the walls and then rounded it gently to soften the edges plus also to protect against being bashed and having little chunks fly off.
    Starting to decorate skylight

    Starting to decorate skylight


    The next job is to paint the wood framework with universal combined primer and undercoat white paint, and a metal white paint for the steel cross tie. We had a little issue with one of the Skylight rafters where a knot hole kept on “leaking” colour when it got painted so we got out our oil-based primer and dabbed that area which did the trick. We repeated the undercoat for the second time all over to make sure that everything has a good strong whiteness.
    We, while waiting for the woodwork to dry between coats, applied a coats of white emulsion on the walls, using a regular bulk white emulsion and then finishing off with a high quality brilliant white paint.
    GR Skylight Decorated! (1)

    GR Skylight Decorated! (1)

    GR Skylight Decorated! (2)

    GR Skylight Decorated! (2)



    At this point, everything that we needed our mobile working platform to reach high up is finished so we moved it away to the other end of the first floor, ready for some future task like building the boxing that will hide the backs of the solar panels and the air ducting etc.
    We can now finish constructing the rest of the gable wall going across the Gallery, putting in the doorway etc and shelving units, blocking off the gap between the two steel posts holding up the Skylight.