Sewage Processor Day 3, 4 and 5!
The work continues with the Sewage Processor installation and its connections! Day 3 – Tuesday 13th July Started with the concrete mixing to bed down the processor unit but didn’t…
A DIY Selfbuild by Stephen, Shaun & Daphne
The work continues with the Sewage Processor installation and its connections! Day 3 – Tuesday 13th July Started with the concrete mixing to bed down the processor unit but didn’t…
A quick review of our construction of the Leach Field. The video contains all 12 days of our work speeded up by over 300 times normal (one picture every 30…
Day 1 and Day 2 of the Installation of our Sewage Processor! Saturday Day 1 Finished off compacting the soil over the Leach field. The Sewage Processor’s location is calculated…
The work continues .. .. Day 7 – Friday Finished off the sand layer to required depth (700mm). Marked out the trench lines ready for the 40mm stones. Day 8…
We have been busy for the last week… On Friday we set out the trench lines for the leach field. Day 1 – Saturday Marked out and dug the first…