We resumed the task of cutting the slot into the Fascia boards, the final stretch going from “E” to “H” sections to complete the full circuit.
We also fully installed two more Downpipe Channels, one for the DE corner and the other one at the GH intersection.
Tomorrow, we will conclude doing the final three Downpipe Channels around the back of the building, on IJ, LM and MN corners and that will be that at last! We could be doing the roof boards and start covering up the roof next – yippee!!