Another week is complete, with lots of Slates being mounted plus some little bit of work on the window’s octagon pillars.
The hip flashing was first to be done, with the bull-nose shaped fibre-glass covered in the dark grey resin, going up the P-A intersection of the roof.
Then we went to work on the “P” section of the roof and finished it off, as now we have means and support to climb up (on the “A” roof) to gain access to “P”.

P-Finally-finished

P-Finally-finished


We also put up the Skylight rubber flashing along the “A” section to the “C” ridge line and put up the aluminium cover strips too.

We then installed the other half of the slating battens on ‘A’ (another 24 rows and about 260m long)

Roof-A-all-battened-up

Roof-A-all-battened-up


Next, the metal mesh (for the guttering) was cut into strips off the roll, but with an additional modification applied at the same time. we put on a steel rod on to the jig so we could push and squash the mesh around the rod to make a “bump”, sticking up into the air. We are hoping that this will solve the annoying and troublesome rainwater from running across the mesh without dripping off into the gutters and dribbling over the edge down to the ground. This bump will, fingers crossed, interrupt the flow of the water and force it to drop into the gutter as it should do in the first place!
We then proceeded to cover all the way along the “A” section and half of the “B” section including the valley corner. We had already, by then, installed two 3metre valley trough modules up the A-B valley.
Gutter-Mesh-on-A

Gutter-Mesh-on-A


For the last two days, we got on with slating the “A” roof and we have managed to do about a one thousand three hundred slates.
A-Slating-Day-1

A-Slating-Day-1

A-Slating-Day-2

A-Slating-Day-2



There were interruptions during the week, some due to bad weather where we worked in the workshop on our windows and continuing with the task of shaping our octagon pillar pieces, but we had other little interruptions too.
Next week, we will carry on with the “A” section and put up another 1500 slates, up the valley and to complete that. Then will do the three porch metal posts and get them done before we start putting on more weight on the roof and the porch.

By Shaun