Temporary Lighting Installed Along Hallways
With the days drawing in and as each room is completed, less and less daylight is reaching the inner hallways and they are getting gloomier and gloomier plus also part…
A DIY Selfbuild by Stephen, Shaun & Daphne
With the days drawing in and as each room is completed, less and less daylight is reaching the inner hallways and they are getting gloomier and gloomier plus also part…
We resumed the work on Bedroom 3 with the Wall Boards. We switched over to the tongue and groove method of joining two boards together and it seems to be…
After having finished the floorboards for Bedroom 3, we can walk around much easier and inspect everything. We decided to swop out the cable conduits around the windows with our…
Continuing with Bedroom 3, this week we installed more various elements into the wall and floor structure to provide additional functionality to the operation within the room like, for example,…
We continued with the work on Bedroom 3 and getting the floor, walls and windows ready. Whilst we are waiting for the deliveries, we got on with finishing the windows…
At last! The arrival of the twin-walled plastic conduits tubing has occurred today this morning! But not all of it! We ordered three different sizes: 100mm, 63mm and 40mm diameters…
This Monday morning saw the arrival of the electric motor, the gearbox, chain, cog wheels and the electronic controller. All this equipment is going into the Stair Lift unit to…
We started the new week, after completing our staircase in just four days, by fixing up the metal joist bracket to the stringers at the top of the stairs. We…
We started on our next task on Wednesday, to design, create the parts and then build the staircase, all in just four days! The first job was to get our…
To finish off filling in the outer walls, and to provide a vapour barrier too stop moisture getting into our timber elements, we proceeded to cover up the glass wool…