Gutters Installed but also more Site Clearance done too
It was another week of a mixed bag of jobs and tasks, but we made progress on the guttering, oak planks for our windows and did some site clearance too.…
A DIY Selfbuild by Stephen, Shaun & Daphne
It was another week of a mixed bag of jobs and tasks, but we made progress on the guttering, oak planks for our windows and did some site clearance too.…
A week of a mixed bag of lots of little tasks, jobs and errands, with a mixed bag of super-hot days, thunderstorms and a cool damp day to finish the…
For the last three days of this week’s work, we were in the workshop processing the pile of Oak timber that makes up the vertical elements of the window frames.…
For the first three days of the this week of work, we were lucky with the weather but also unlucky as we suffered in the heat too! But we did…
We started this week with good dry weather in resuming the job of mounting Slates up on to the roof. We finished off the little bit left to do on…
With a lovely prospect of good weather ahead of us, we got on putting up the final rows, about 13 of them, of the tile battens to finish off preparing…
On this rainy day, we worked in the workshop on our Oak timber pieces for our window frames. We carried on with the task of shaping the Sills and the…
We had a very disrupted week of work, losing three and a half days, due to other commitments and meetings. It is just one of those things that happens now…
On Monday this week, taking advantage of the good weather, we proceeded to glass-fibre and resin the two complex junctions and the corner we installed last week. The two Downpipe…
The last two days of the week (Friday and Saturday) were nice days so we got on with installing the two Downpipe Channel modules for the P-Q valley that forms…