Blog

  • Equipment Cupboard Completed, New Electric Switch and Consumer Unit Installed and Flooring Structure Created

    We resumed work on our “Engine Room” within the Utility Room this week by putting on the thick heavy roof to the equipment cupboard. It is three layers of the fermacell boards, making use of left-over pieces where possible especially after we had put on the first layer which was tongue’d and groove’d to stop the edges sagging under the weight. We dug out quite a fair bit of old pieces of fermacell off the rack in the Garage that has been there for years. All to try and improve the sound absorbing qualities of the whole cupboard, to keep any “engine” noises from disturbing the household.

    Cupboard-ceiling

    Cupboard-ceiling


    We then built up the front of the cupboard, to continue with this sound proofing technique by putting on two lines of horizontal CLS rails positioned at the floorboard support point and another one higher up at just above the plinth feature that will be constructed around the bottom of the cupboard frontage. We also did the floor support frame for going around the sink worktop zone (under the window) as well. Then, using these two new horizontal rails, we proceeded to insert two layers of OSB 18mm thick boards to squeeze in between the upright posts, to fill in the gap and make a smooth internal surface (we had to insert thin 2mm shims to pad out the two layers of OSB sheets because the posts where 38mm thick and the two layers of OSB only came to 36mm, hence the little thin shims) at which point we went around putting on a layer of fermacell on the inside surface, again for both more sound proofing measures but also to provide a better fire proofing protection too. With all this plasterboard like material now covering all the internal surfaces, we went around filling in all the joints and rounding off the corners with Polyfilla which we then use our new bulk sanding machine that we bought several years ago, just for this purpose. It is connected to our DIY vacuum machine and it was a dream to scrub down the wall, and ceiling, surfaces, removing the excess filler everywhere. All that was left to do by hand were the corners which didn’t take too long to do either.
    Cupboard-boarded-at-bottom-1

    Cupboard-boarded-at-bottom-1

    Cupboard-boarded-at-bottom-2

    Cupboard-boarded-at-bottom-2



    One of the jobs we almost forgot to do was to cut a chimney hole up through our new roof so that we could have our air ducting chute to come down from upstairs. It took a few hours because of the tight close quarters but we managed it and we now have connection for our “waste” air returning from every corner of our house, ready to be refined, processed, recycled and discarded.
    Return-air-duct-through-cupboard-ceiling

    Return-air-duct-through-cupboard-ceiling


    Now that we have the basic shell of our cupboard completed, we could move and build a proper electrical switchboard, to hold the consumer unit, fuses, junction boxes etc. all in the new cupboard. We have located this equipment to be at the left end of the cupboard, just near the window so we can just open a door above the worktop and gain access to the cut-off master switch and individual switches for each piece of equipment that will be inside the so called “Engine” room for our house. We also installed a row of temporary sockets to use whilst building. It took a day to get everything moved, sorted and made neat and tidy but we now have a solid foundation to grow the electric system for the whole house, the only bit left to do, is to hire an electrician to “plumb” in a unfused tap into the main distribution panel in the garage immediately after the smart meter etc.
    New-consumer-unit-and-temporary-wiring-1

    New-consumer-unit-and-temporary-wiring-1

    New-consumer-unit-and-temporary-wiring-2

    New-consumer-unit-and-temporary-wiring-2



    The remaining day and a bit was spent constructing the grid like support framework for our floorboards going across the room, making sure we had room to lay down our air ducting which is our largest item that lives under the floorboards, to get across the room and diagonally towards the door and into the hallway.
    Utility-floor-support-grid-1

    Utility-floor-support-grid-1

    Utility-floor-support-grid-2

    Utility-floor-support-grid-2

    Utility-floor-support-grid-3

    Utility-floor-support-grid-3



    And then start putting in the insulation pieces that encapsulates the hot water “flow” and “return” pipes, snaking across towards the sink under the window and sorting out the conduits that needed to cross over etc. One of those pipes, is the main sewage pipe going down into the concrete and we bought a module that allowed us to have the ability to plug in four separate 40mm diameter waste pipes, coming from the sink and washing machine plus also any condensed water that drops out in the air conditioning sub-systems.
    Start-of-Heating-pipe-crossing-the-room

    Start-of-Heating-pipe-crossing-the-room


    Next week, we will continue with that process of sorting out the hidden pipes and conduits so we then can put down a strip of proper and permanent floorboards in front of the door and window which in turn means that we can build the sink worktop and the cupboard and drawers that goes underneath. We are just planning a rough and tumble worktop for the time being, just using some OSB material we have lying around so we can have a working sink sooner than later.

  • Taken the Plunge and Ordered Motorised Valves from China

    After a long period of analysis, testing and weighing up the risks, we have placed an order for motorised water control valves from China, directly with the original manufacturer.

    Motorised Valve

    It is just the unknown and sheer distance involved with this venture that is the risk but we had our goals and we wanted to realise them without having to pay a very high price for a similar device sourced in UK or even Europe. China has now proved themselves to be a reliable source of material and devices, or they wouldn’t be where they are now. We have paid about £13 a valve against £35 locally.
    So we have spent nearly $1400 (plus $600 for shipping) on a set of water stop valves that can be controlled by a computer. We love the idea of automation and we always dreamed of having a smart house and hence this is an investment towards that goal. We had bought a sample valve from China a couple of weeks ago and analysed it, tested it and it all seems good and solid. So we are now having well over a hundred motorised valves coming, most of them are 15mm bore size but a couple will be the larger 25mm bore for the main water pipes we have laid out in the house.

  • Equipment / Machine Sound Absorbing Cupboard Half Constructed

    At the beginning of the week, we finished off preparing the Utility Room by concluding the task of putting up OSB wall boards around the door and then trimmed the window .. well we eventually managed it .. slowly! The router bit we had is getting rather blunt so we ordered some more replacement cutters, nice and sharp! Afterwards we extended the height of this wall board layer inside the window area so it goes up to the level of the worktop by using a whole series of biscuit joints around the three edges and sliding in the new piece from above and then fixed in with PU construction glue.
    Next, we proceeded to cover all this OSB material with Fermacell boards which was a simple process of spraying lines of PU glue foam all over the surface and then staple each piece up with 25mm long staples fired from our compressed air stapling tool. The joints between pieces were stuck together using the thicker PU construction glue instead, to achieve a tougher and stronger joint.

    OSB-on-window-wall

    OSB-on-window-wall

    All-walls-have-fermacall-applied

    All-walls-have-fermacall-applied



    That pretty much concluded the preparation work in getting the basic room done enough so we could start constructing the next object, namely an equipment come machine cupboard to hide away all the various devices, gadgets, mechanisms and storage that will provide the Utilities for the whole house and garage. It is essentially is a room within a room and we are constructing it using thick/heavy materials to try and reduce the noise levels as much as possible and not disturb the rest of the household. So we decided that we would have a cupboard the complete width of the room, from floor to ceiling, along the “E” wall and it will be 600mm overall deep including the wall thicknesses. Part of this design criteria was that we did not want to encroach too closely to the window, to give the window a better look and also we selected 600mm because we didn’t want to have a pile of waste pieces left over when we built the roof out of our 1200mm width sheets. Joining to this basic rectangular shell will be the cupboard region that will hold the clothes drying and vacuum machines, coming along the entertainment wall side of the room and stopping just short of the entrance way to the hall, allowing for the door to open fully and back against the wall. This section is going to be 700mm deep and it turns out to be about 1900mm long, which can be sub-divided into separate modules for each of the machines and other functions like shelving units. This is the extent of what we wanted in creating a noise reducing box like cabinet so we laid down a footprint of treated CLS 63mm timber pieces down on the concrete floor, glued and bolted that defines the outline shape. We also put down extra pieces in front of the window too, to define what would be our worktop and sink section, again being 700mm deep and also being about 1900mm long too.
    Cupboard-Footplates-fixed-down-1

    Cupboard-Footplates-fixed-down-1

    Cupboard-Footplates-fixed-down-2

    Cupboard-Footplates-fixed-down-2



    One of the minor tasks we completed before we continued with the cupboard, was to fill in the joints and corners around the fermacell walls with Polyfilla and smooth it all off so it is sealed. After that, we started building the cupboard using 18mm OSB boards but just before that, we stapled up little squares of foam material that is 8mm thick so that we can maintain a air gap between our new cupboard and the room’s walls, to disconnect any direct transmission of any sounds being generated by motors etc. inside the cupboard.

    We brought a dozen sheets of 18mm OSB inside from our pile outdoors and got them ready. One thing we wanted to do was to use a tongue and groove joints so they formed a solid structure, a backbone for the rest of the cupboard to be built from. Also, we needed room at the top of these walls to fit a “lid” on top and still be separated from the ceiling, this meant that we needed a full height board (2440mm high) plus a narrow strip of 270mm wide to start at the bottom line sitting on the newly installed CLS footplates. So sliced up two board into eight narrow strips and then cut a set of tongue edging on four of them plus groove edging on the other four.
    We proceeded with the narrow strip first, right around outer sides of the cupboard and then put a row of horizontally mounted full sized sheets, again with a set of tongue and groove edging. The long side of the cupboard (against the “E” wall) is 3740mm long so we put in a full sheet in the middle and filled in the left and right ends with 650mm pieces. We were making sure that no joints lined up with each other and creating a stronger monolithic backbone. The top line of OSB board had to have a large section cut out to make way for the air ducting sticking through the wall. Oh yes, the same for the five other sticking out conduits and pipes at various places and also we had unscrewed and lifted the air duct that is coming down through the ceiling.
    we ended up with the first layer all done, starting about 300mm from the window, coming along the “E” wall some 3.7metres and turning along the entertainment wall another 2.5metres before finally turning right angled from the main wall to form the end of the cupboard which is a further 750mm wide.
    First-row-of-OSB-for-cupboard

    First-row-of-OSB-for-cupboard


    That took a while to do because of all the tongue and groove edges we needed to cut and fit everything together with glue etc. but once we have done that first layer, we could mount on the second layer much faster because we didn’t need to do any further tongues or grooves again as we had the backbone layer to press against, keeping the joints neat and tidy. We proceeded to spray a zigzag line of PU glue foam all over the surface and screwed this second layer straight on to the first layer. We had drilled clearance holes all over the sheet, we did a grid of four rows by six columns, giving us a total of 24 screws to tighten the two sheet together squeezing the glue out thinly. We used about 200 screws by the time we done all the second layer!
    Next, we put up a solid CLS 89mm piece of timber right across to form a lintel for the front of the cupboard to help support the heavy “lid” which will be made of three layers of fermacell sheets.
    All-cupboard-OSB-placed-and-glued-1

    All-cupboard-OSB-placed-and-glued-1

    All-cupboard-OSB-placed-and-glued-2

    All-cupboard-OSB-placed-and-glued-2



    On our last day, we went around fitting in a third layer of material, this time our fermacell “plasterboard” sheets, again, just went straight up onto the wall surface with the PU foam glue and this time, was stapled on with 25mm staples. It didn’t take very long and we finished off the day by putting four vertical CLS posts, two 63mm ones up against the walls under the lintel, and the other two being 89mm pieces, again fitted under the lintel but this time 800mm out from the walls. All four will help support the lintel and in turn, the roof of the cupboard. The last piece of CLS, another shorter 89mm piece, went along the front of the side arm of the cupboard, also to support the heavy “lid” over this side section of cupboard.
    Cupboard-lined-and-basic-framework-errected-1

    Cupboard-lined-and-basic-framework-errected-1

    Cupboard-lined-and-basic-framework-errected-2

    Cupboard-lined-and-basic-framework-errected-2

    Cupboard-lined-and-basic-framework-errected-3

    Cupboard-lined-and-basic-framework-errected-3

    The-whole-cupboard-is-isolated-from-the-wall-of-the-room

    The-whole-cupboard-is-isolated-from-the-wall-of-the-room



    Next week, we will start building the lower sections of the front parts of the cupboard, up to the floor levels and getting ready for the flooring supports for the room and starting to lay out the pipework and ducting etc. going across the room and out into the hallway.

  • Preparing Utility Room so Ready to Build Equipment Cupboards

    We arrived for this new week to resume our work on preparing the Utility Room, to get it ready for installing the vast collection of equipment, tanks, switches, pipes and many other bits and pieces that will provide the services like water, air, electricity, vacuum and other utilities.
    We got going on dealing with the black plastic that is pinned up on the wall, covering the window so that got sliced and wrapped down the sides. We also inserted the plastic liners for both the bottom and top cavities that sits below and above the window too. We are just repeating the same procedure as we had done for Bedroom Three windows and these cavities are designed to provide space for the mechanism to control the automatic window blinds. As part of dealing with the window, we put in the extra pieces of CLS timber to frame on all four sides and then put up two vertical 11mm OSB boards on the left and right sides but only after we remembered to install several lengths of 20mm black conduits. We nearly forgot to put one conduit in to allow us access and the ability to feed through whatever electric wires we would need for the mechanism. It was a tight squeeze to slip the conduit behind the plastic already up on the wall but we made it. As part of putting up the plastic and wrapping it into place, we used our malleable white tape to seal tight all the conduits poking through the plastic but also did the large air duct boxing too.

    Next we did the doorway. We had to take off the door again plus all its equipment like electronic lock and sensors etc. so we could wrap the plastic up and onto the door framework, to ensure that we are creating a good vapour barrier. We also put on three extra CLS 63mm timber pieces around the frame that will form the inner surface wall and door entrance. We remounted the door, changing the hinge position slightly and put back all the door furniture and reapplied the door hook too.

    Dorr-framing-redone-and-door-rehung

    Dorr-framing-redone-and-door-rehung


    Looking at the order of things, we then got on with installing the ceiling covering. We needed to do the ceiling next because we are planning to build the equipment cupboard and that will go from floor to ceiling almost and we wanted to put up one layer of the fermacell (this is like a plasterboard material but highly accurate and engineered gypsum mixed with recycled newspaper and no paper liners) to improve the sound proofing levels to stop the machinery and equipment we are planning to employ from disturbing the rest of the household, especially the living spaces up on the First Floor. So towards that goal, we built a second air ducting but this time, it is coming down through the First floor joist structure. We used more of our 18mm floorboards chipboard material to create an oblong shape measuring 600mm long and 240mm wide, narrow enough to fit between two joists and also enters cleanly into our equipment cupboard too. We made it 370mm tall, enough to traverse through the first floor floorboard and joist space. Next, we lined up the box against the floorboard to mark where we want our hole and sliced our way through. This will allow the exhaust air that is being all collected upstairs and being routed around to this spot, to be diverted downwards into our equipment cupboard, to be processed and then rejected outside. We only screwed in this air ducting for now because we can see that we will need to move it out of the way when we come to build the cupboard later on.
    Air-duct-down-from-first-floor

    Air-duct-down-from-first-floor


    Before we can mount our fermacell boards up on to the ceiling, we need to cut a set of tongue and groove into selected edges. We discovered way back when we built the Garage that we couldn’t keep all the sheets of fermacell dead level to each other, even though we put on PU glue and fixed little screws in the joints to hold them steady while the glue dried, it came out very slightly wobbly and it took a great deal of sanding to get it smooth again. So back then, we tried cutting a tongue and groove into the fermacell and it worked like a treat. So today, we took that experience and set up our two router machines with new cutters, both are identical shaped cutters, that does both a series of tongues and groove within the thickness of the material. These cutters can do up to 25mm thickness but we are only wanting to do either 10mm for the fermacell boards and 18mm for our OSB boards.

    We also adapted the two router machines by extending their bases to a much larger supportive area so the heavy machines won’t tilt off the edge and we can pull it along against the surface and the fence, to get a smooth, regular and neat cut. The only different between the two routers is to the exact position of the cutters, one will do the grooves and the other one does the tongues.

    Router-with-extended-base

    Router-with-extended-base

    TG-cutter-in-new-base

    TG-cutter-in-new-base



    It took a little while to do these modifications and testing sessions but it is well worth the time, in order to get good quality results in the long run. So with these new tools, we proceeded to put up a set of fermacell 10mm thick boards up on the ceiling, using our very handy and strong board lifting contraption (It’s a bit rusty from being stored in a shed for 10 years). It runs on highly adjustable wheels so it can squeeze into corners and go around obstacles. But before we did that, we loaded the joist space with a load more of 200mm thick glass wool material to provide more sound proofing.
    Insulation-in-the-ceiling

    Insulation-in-the-ceiling


    We, and our lifter (each full size board weighs 25kg each!), did a row of boards, some 1200mm wide strip next to the “E” wall and then did a wider 1600mm strip along towards the door entrance into the hallway. We did this much of the ceiling because our equipment cupboard will go along the “E” wall and also along the Entertainment wall and stop about a meter before the hall door. We put spray PU glue on the joist flange itself and construction PU glue into the groove to joint two sheets together and plenty of 35mm long staples to fix the board up for the long term. The roof will be inaccessible after we have built the cupboard.
    Board-lifter

    Board-lifter

    Holding-up-a-board

    Holding-up-a-board



    After dismantling the board lifter, we then tackled the “E” wall and covered the entire surface with more fermacell, from concrete floor and right up to the ceiling. We had to put up three and a bit sheets along the upper wall plus a narrow strip along the bottom to cover up the plastic.
    Before we put up the last piece at the bottom we had to remove the very old ‘chimney’ which protected the entrance tunnel for the air from the earth tubes. This just pulled out of the hole in the floor and we had a peek down the tunnel because we didn’t actually know if the tunnel was OK.
    Top-the-Earth-Tube-tunnel

    Top-the-Earth-Tube-tunnel

    View-along-the-tunnel

    View-along-the-tunnel



    This layer, and the one on the ceiling too, will provide additional fire protection too, making our wooden house that much harder to catch alight if we ever had a fire as the Utility room is the most likely place to catch fire in the first place. We will put in extra measures when we build the equipment cupboard and there would be active fire suppression devices installed inside, plus plenty of alarms so we are fully aware when there is a problem.
    E-wall-boarded

    E-wall-boarded


    Now we moved around to tackle the Entertainment wall which is a stud wall made of 89mm thick CLS posts, we only wanted full board of OSB beside the hall entrance so we nailed up narrow strips of OSB pieces on the rest of the legs. We did have to pull off that full sized board because we forgot to put in the glass wool material first! So we duly put in more 400mm wide strip of the 200mm thick glass wool and stuffed them into the 89mm space, yes 200mm into 89mm! This will obviously compress the wool down when we put the series of board on the wall and this is great because it will reduce much of the sound and noises coming from the Utility Room and entering into our Entertainment room where you may be watching and listening to a movie and the last thing you want is, to hear the washing machine spinning or the vacuum system whirling away!!
    So this wall had a layer of fermacell put on, compressing the wool down and this finishes off this wall completely too. Again, we did this now because of our equipment cupboard which will be built slightly removed from these walls to provide another air gap for sound insulation.
    Entertainment-wall-boarded

    Entertainment-wall-boarded


    You may have noticed that we are putting these boards directly onto the wall posts and not on any horizontal rails. This is deliberate as there is hardly any needs for having electrical sockets or switches. Most of the Utility Room will have cupboards, cabinets and shelves and they will have their own electrical sockets inside these regions and nothing will be visible. The only exception is the little length of worktop in front of the window for a sink and we might put up a socket on the side of the cupboard at the end of the worktop.
    The last bit of work for this week is putting up the first layer of OSB board along the “F” wall, to cover up the plastic and provide a strong screwable surface for mounting anything up on the wall, like a worktop! We got as far as the door, again each piece was cut to give a tongue and groove edging to bring together each piece in a nice smooth finish, ready for the layer of fermacell to go on too.
    Window-wall-OSB-started

    Window-wall-OSB-started


    Next week, we will finish the OSB around the door, trim the edges and then put up the fermacell to get that finish. After that, we will start building the equipment cupboard which will be fun!

  • Preparing Utility Room

    One of the first jobs was to move the existing electricity control board from over beside the window and position it out of the way on the dividing wall between this room and Bedroom Three and reconnect some of the electric cables so they were all out of the way before we could fill in the walls with rock wool and cover it up with the vapour barrier. We also did some extra lighting for our hallways, see Installed Lighting Along Hallways. We then started preparing the Utility Room to be created with all its equipment, pipes, valves, pumps, tanks etc. that will serve the house and one of these items was to create an air outlet vent that will allow the exhausted air to escape the house and we did this by chopping our way through the 200mm thick foam insulation near the ceiling and near the left side of the “E” wall as you stand inside the room. The hole we made was the full width between two wall legs, some 550mm wide and a height of 600mm, reaching the cement board outer skin layer where we sliced a 450mm wide by 500mm high hole through the 10mm thick board. We had some stainless steel woven mesh (left-over from replacing our filter in the rain water filtration system), the mesh is woven with fine wire and has 2mm holes which should stop almost all insects and animals from entering the dangerous zone of a fast spinning blades of the air fan. We used some MS Polymer black glue to attach the mesh to the inside surface of the cement board and held it in place using a plastic covered piece of OSB board with clamps to keep it firmly pressed tight while the glue cured.

    Gluing-the-HVAC-exit-vent-mesh

    Gluing-the-HVAC-exit-vent-mesh


    Next, we took some of our left-over 18mm floorboard chipboard material and created a box that will form a large square duct that will help guide the air out of the building. It measures 450mm by 500mm to match the hole through the cement board and put on a ring of 50mm wide strip to provide a larger surface area to bond to the outer perimeter of the wire mesh. The whole box extends well beyond the thickness of the wall so we have options to how much we need when we connect the rest of the ducting and fan later on. Talking about the fan, got one of our new 300mm diameter fans and temporarily seated it inside the new vent hole and powered it up. We did some test runs with different air flow rates and went outside to listen to how noisy it was. We even got out our sound level analyser and took some readings. So at maximum air speeds, we were getting a reading of 63dB at a distance of about 2metres and 65dB and 68dB using different settings on the analyser, representing different patterns of sound pressure and frequencies. The background noise at the time was 40dB, it wasn’t very windy at the time. These figures are quite loud but this was for the maximum possible speed and the sheer power of the fan is that we will only need that kind of air flow rate during the very hottest times of the day in the middle of Summer. Most of the time, the fan will be running much more slowly and we think that it will be about 50dB which is a quiet murmuring noise that fades away when we moved some 5 metres away like the front door or out in the Loke.
    Oh yes, just to make clear, the outside layer of Larch timber was still there, the air was escaping through the gaps between all the planks and it seems to be working very well. It gives us the benefit of having somewhere for the exhaust house air to escape but not having a ugly large metal grill visible.

    So upon the good test results of running the fan, we proceeded to glue the wooden box ducting into place and filled around the edges with more foam boards, using PU spray foam to stick the whole lot together.

    HVAC-Exit-vent-1

    HVAC-Exit-vent-1

    HVAC-Exit-vent-2

    HVAC-Exit-vent-2



    The next job was to insert a long awaited conduit that needed to go from the concrete floor level and all the way up to the Eves, to provide a water irrigation supply for any hanging plants etc. We positioned this conduit near the copper water pipe already installed some weeks ago. There were a couple of other conduits that we also extended and positioned so they were poking out into the room, these were the mains socket in the wall and a couple of underground connections too. Another little task was to screw and glue a vertical CLS post in the corner, the E-F corner to provide a mounting leg for the wall boards when they go up later.
    Because the Utility Room has lots of cupboards, a worktop and the door and window too, this meant that there was virtually no where to put sockets and other switches etc. so we decided that we didn’t need to employ the same design of creating a Utility Channel running around the whole room. It is a bit ironic not having one of these channels, called a Utility Channel, in our Utility Room! Oh well. We did realise that we would like a switch beside the Side Door entrance so we could activate the lights or trigger the garage doors to open if we were going that way, so we embedded two short CLS pieces between the wall legs that is sandwiched by the door and window, to form a pseudo Utility Channel. Oh yes, We remembered to insert another piece of conduit that went down to the concrete!
    Another preparation task was to go around and plane off all the little sticking edges of the plywood that formed the wall leg structure, there are three of these plywood pieces for each leg and some of them are proud of the leg itself and we need it to be all smooth and ready for the wall boards to go up next week.
    Another job that needed doing was measuring and making horizontal rails for the bottom and top of the window and the top of the door too. These rails are the exact position that defines the height and hole of the window at 500mm from the floorboards and 2200mm at the top, also the same for the door too. But we don’t have the same utility rails that other rooms have, we had to fit them inside the framework instead and there is already pieces of CLS timber in place but only approximately at the correct position. We needed to create a special piece for the window, a 45mm to 47mm high piece for the bottom rail and a more even 30mm piece at the top. The doorway was easier and a normal 63mm piece went in straight. Well perhaps not easier after all, because we discovered that our temporary door was too tall and hit this new framework piece. This led us to having to deal with the door itself next. We took it off and decided that while it is off, we would go ahead and install a new temporary door sill, to make sure that we will get above what will be the new floor surface when we put down the floorboards. We found a piece of “4by2” treated timber, cut it down to 1040mm length, to fit the width of the doorway, levelled it off by using a couple of solid 5mm plastic spacers and a smaller 3mm one in the middle and fixed it into place using three concrete screws plus a heap of MS polymer glue to seal the outside joint to provide some water protection against future rain floods.
    Temporary-side-door-sill

    Temporary-side-door-sill


    Now that we had the new sill in place, we could measure the amount of material we would have to remove at the bottom of the door, some 45mm in total. We put in an replacement CLS frame to ensure the bottom of the door was still reasonably stiff. Then we chopped off 10mm off the top to clear that new upper rail and then put the door back. We did have to do further adjustments by running the planer across the bottom edge as the door turned out not to be exactly square but since it is only a temporary door, we kludged it to get it to fit without scraping!!

    Finally, we were in the position to do the next stage of filling in the walls with glass wool and the plastic vapour barrier membrane. We scrubbed the aged timber surfaces along the bottom, applied a line of the butyl heavy duty double sided sticky tape along the bottom edge, around the window and along the top edges too. Where there were a plastic layer already, we used acrylic sticky tape instead. Next, we unrolled and cut up lengths of glass wool pieces, 100mm thick stuff for the lower half and longer pieces of 200mm thick stuff for the upper sections. We filled in the corners and around the door and window so everything is now filled in.

    Fibre-in-utility-walls-1

    Fibre-in-utility-walls-1

    Fibre-in-utility-walls-2

    Fibre-in-utility-walls-2



    After that, we put on sheets of plastic to encapsulate the yukky glass wool stuff and provide a vapour barrier to stop condensation from forming in the body of the wooden walls and hence avoid potential rot problems.
    Utitlity-walls-with-vapour-membrane-1

    Utitlity-walls-with-vapour-membrane-1

    Utitlity-walls-with-vapour-membrane-2

    Utitlity-walls-with-vapour-membrane-2



    We now have finished covering up the walls, just a little bit to finish off like sealing around the air duct and various conduits sticking out, plus finishing off the window and door too. Then we can install a layer of plasterboard to cover up this plastic to provide a fire resistant barrier and then we can start on building the internal “cupboards” that will contain the equipment that provides the utilities and services for the house.

  • Temporary Lighting Installed Along Hallways

    With the days drawing in and as each room is completed, less and less daylight is reaching the inner hallways and they are getting gloomier and gloomier plus also part of moving everything out of the Utility Room, sorting out the wiring, we decided that the hallways on the ground floor needed additional temporary lighting installed. We had a collection of small 10W LED flood lamps, eight of them in all, and proceeded to distribute them evenly around our four lengths of hallways. We used some old 1mm twin and earth lighting cable to join each one up and connect the tail end back into the light switch beside our side door.

    Temporary-hall-lights

    Temporary-hall-lights


    We now have a brighter future in our hallways!

  • Wall Boards All Up and Utility Channel Cut

    We resumed the work on Bedroom 3 with the Wall Boards. We switched over to the tongue and groove method of joining two boards together and it seems to be working quite well. It is a simpler process of getting the two board to join as there are no loose biscuits to keep an eye on, just solid a tongue and getting it to slide into the groove is the only little troublesome aspect but nothing much really to worry about. The whole room is now covered with the 18mm thick OSB sheets.

    Walls-covered-in-OSB-1

    Walls-covered-in-OSB-1

    Walls-covered-in-OSB-2

    Walls-covered-in-OSB-2

    Walls-covered-in-OSB-3

    Walls-covered-in-OSB-3



    The window holes were trimmed to remove the excess sticking out edges of the OSB boards and then using our track saw, we went around cutting the Utility Channel slot too. The green laser line generator gave us the 800mm and 900mm off the floor surface which is where we have our Utility Channel positioned and we did the standard spacing (being 38mm) to stop each channel to avoid crowding the corners and windows plus doors.
    Utility-channels-cut-1

    Utility-channels-cut-1

    Utility-channels-cut-2

    Utility-channels-cut-2

    Utility-channels-cut-3

    Utility-channels-cut-3



    We also put on smaller side pieces of OSB boards around the en-suite entrance so that the glass wool is all covered up but also ready to build the finishing surfaces that will support the glass wall and glass door.
    En-suite-dorrway-lined

    En-suite-dorrway-lined


    We then installed a dozen electrical double sockets around the room as this room will become our new work area for the duration of the house build.
    The last two days were spent moving the entire load of tools and supplies including two sets of shelves, a stack of drawers and several tables from the Utility Room to Bedroom 3
    Everything-moved-from-Utility-1

    Everything-moved-from-Utility-1

    Everything-moved-from-Utility-2

    Everything-moved-from-Utility-2

    Everything-moved-from-Utility-3

    Everything-moved-from-Utility-3



    Then a good clean up of old rubbish, saw dust and other chunks lying about.
    Utility-emptied-1

    Utility-emptied-1

    Utility-emptied-2

    Utility-emptied-2

    Utility-emptied-3

    Utility-emptied-3



    We put up five more quick shelves in our Knick-Knack cupboard so we could spread out and organise all our plumbing bits and pieces, to be ready to hand when we build the various water and waste pipework. We also brought from downstairs our little work table we had set up for making the plastic air diffuser and put this operation in with the rest of the tools and work tables in Bedroom 3.
    Plumbing-supplies-sorted-1

    Plumbing-supplies-sorted-1

    Plumbing-supplies-sorted-2

    Plumbing-supplies-sorted-2



    We also had a general sweep-up of the hallway and this means we can start work on finishing the walls in the Utility room, start building the floor support framework and start mapping and designing the placement of the various pieces of equipment that will drive the environment for our house like air, water and electricity.

  • Wall Boards Are Going Up and Final Conduits Installed

    After having finished the floorboards for Bedroom 3, we can walk around much easier and inspect everything. We decided to swop out the cable conduits around the windows with our recently purchased rigid waste piping and also insert a another new piece of conduit, this time to provide access for power and signalling cables to the windows and their motorised blind mechanisms. We nearly forgot all about those!

    Replacement-window-bypass-conduit

    Replacement-window-bypass-conduit

    Window-control-conduits

    Window-control-conduits



    Another feature that we have been talking about is putting in a built-in hearing induction loop into and around the walls so we installed another length of conduit, running horizontally above the doors and windows using our stock of 20mm black polyethene pipes. We had to heat and bend much sharper corners because of the tight space requirement when traversing around the corner and having to keep inside the 38mm spacing limits. We made six of these tight bends and then used short 25mm diameter pipe to join them to the straight sections. The Loop started and finished at our Control Box which will house the induction loop amplifier. This is a very rare feature to have such a thing in a domestic situation, all built-in but having two people wearing hearing aids living here, we thought we had better provide the ability to install a loop later on.
    Conduit-for-hearing-loop-1

    Conduit-for-hearing-loop-1

    Conduit-for-hearing-loop-2

    Conduit-for-hearing-loop-2



    Then we used the left-over flexible 32mm conduits to put in the connection for our mass of low-voltage cables to start on each side of the entrance way.

    That concludes all the conduits for this room, we didn’t need to install a conduit for compressed air nor any other types like water or things like that. So we moved on to the next task of building the short stub wall and doorway to the en-suite. One of the first steps was to screw up a long piece of CLS 63mm timber at the 500mm height which matches the two windows in the room. We did this by using our green laser to ensure everything matched up. Then we measured to how far the toilet bowl would be sticking out from the wall and made sure that the door would be able to swing clear. It does mean that the doorway is slightly off centre but not by too much, some 410mm on the left side and 610mm on the opposite side. We used more of our “2by6” timber that we originally used to build the framework around the en-suite entrance, to make the stud wall and a flat top. We aligned the height of the little stud wall to the new horizontal rail we just put on so all three window like objects in the room all look very similar, with an oak sill on each one etc. We planed two pieces so it was nice and flat to go across the top of the stud walls and two vertical pieces underneath this flat top and goes all the way down to the footplates on the concrete. These were glued and anchored into place with lots of screws plus several battens too. The last piece of the 2by6 was to create the door sill sandwiched between the two stud walls, exactly 880mm wide which is our standard width for swinging type doors. We introduced a very slight slope to this door sill, dropping down by 5mm as one goes into the en-suite so that if there is a lot of water splashing about in the room, it is not prone to running out and into the bedroom.

    Ensuite-stubb-wall

    Ensuite-stubb-wall


    The next task is to slice up our heap of 8×4 MDF sheets into eight strips of 149mm wide per board, these strips go at the bottom of the walls to provide the back-panel to our air channel distribution system running around the bottom of the wall, completely all the way around the whole room. We went from post to post along the wall, stopping and starting on them to ensure that the ends didn’t flap in mid-air. We fired in staples on each post but also glued the top edge to the underside of the CLS horizontal rail so it kept the strips straight and sealed to stop air leaks. Talking about air leaks, the bottom edge was sealed using a black MS Polymer glue against the floorboards. Then we went around with a paint roller and painted the bottom section of the strip black to stop any chance of a gleam shining through when the room is finished and carpeted.
    Air-channel-backing-board-1

    Air-channel-backing-board-1

    Air-channel-backing-board-2

    Air-channel-backing-board-2

    Painted-black

    Painted-black



    The next job was to put up the wall boards, the 18mm OSB sheets. Before we put them up we inserted the final layer of glasswool insulation between the horizontal rails, this is roughly fitted and is really just to provide impact sound dampening for the wall.
    Final-layer-of-Insulation-1

    Final-layer-of-Insulation-1

    Final-layer-of-Insulation-2

    Final-layer-of-Insulation-2



    Also, we went around measuring the height of the walls, from floorboard to ceiling joists and it came out to be 2415mm on average, fluctuating only a couple of millimetres. This height was designed so after the 15mm thick ceiling fermacell panels is installed, the room will have around 2400mm clear, about 7feet 10½ inches.
    We then looked at the various methods of putting up these wall boards and we went for the more rewarding results by putting whole OSB sheets vertically from floor to ceiling in one go (instead of splitting it up into two halves, separated at the Utility Channel) and then cut out the Utility Channel afterwards and also deliberately overlapping the doors and windows so we can trim back the edges right back to the physical limits of these holes in the walls and get a much better finish. The next choice was how we would join the sequence of boards and part boards together along a wall section, we could either use a biscuit jointer or use a continuous tongue and groove method. We couldn’t decide so we went for the biscuit joining method first on the short wall that has the small window in it and proceeded to put in ten biscuits along the entire height with includes the extra ones around the bottom and top pieces that covers the window section. It was a bit fiddly in getting all the loose biscuits in and then slicing the two boards together but it was workable. The big problem we had was with the glue as it was taking us a good 15 to 20 minutes to get all the pieces ready, with their joints and biscuits and we were using the PU spray gun glue foam because it was a very handy tool to just spray the glue into place, but these spray expanding foam don’t have a long “open” working time before skinning over, even this especially designed foam to work more like a glue still has a short time before it skins over and cures. We did manage it by doing it in stages and we got the first wall up and screwed in place. That is another thing, we decided to use screws instead of nails, just like the floorboards because we wanted to know that the boards were being tightly pulled back onto the support horizontal rails and squeezeing on to the glue.

    We needed a glue which stayed usable for longer and after much discussion over different glues, and doing several tests (we put out three blobs of each glue, and then waited 5minutes, 10minutes and 20minutes to see if and when they skinned over and whether the joint was affected by screwing in small pieces of MDF material), we concluded that the solvent-free construction glue was suitable because it is both cheaper and less messy than the other choice of the PU construction type which worked the best (and the third glue, the Skixall performed the worse because it started to skin over by the 20 minute point but still did a good strong joint).
    Before we resumed putting up more wall boards, we felt that we should make sure that we could cut out the Utility Channel so we got our track saw out, drilled a series of mounting screw holes and then using our green laser line generator, mapped out on the finish wall the 800mm and 900mm levels, drawing two lines. We also decided that there will be a 38mm uncut area at each end of the channel so that the covers didn’t have to go right into corners or right up to the edge of a window or doorway. We then proceeded to mount up the track guides onto the wall and sliced two horizontal cuts into the OSB board, then finishing off the cuts using our wiggle saw. After tidying up the cut edges with sand paper, we now have our first Utility Channel ready for use, for our sockets and speakers and whatever else we may want in a room.

    First-walls-OSB-installed

    First-walls-OSB-installed


    Another little job we did was to make a magnetic clamping system for our green laser line generator because it would be much easier if we could put up a vertical metal ruler with pre-determined positions of various elements we have in a room and be able to move the laser up and down easily without having to use a clunky screw clamp. So we put on a long metal band on a piece of wood and glued in two strong magnets into the laser’s little shelf. We did have to add a coat of a rubber like spray on paint to increase the friction between the metal and magnet as it had a tendency to slide down under the force of gravity!

    Finally, for our next section of wall, along the “H” wall with the large window in it, we decided to try out the tongue and groove method of joining the boards together and see how well (or not) it performed. We got our two router machines out and set up the two cutters, one to make a groove 13mm deep and the second one to cut a tongue 12mm long. These are parallel straight 90degree tongues so it may give us some fitting issues when we get to try it out next week. The machines are now setup and the test pieces look good and form flat and smooth joints so it is promising.

    Tongue-Grooving-edge-of-OSB-1

    Tongue-Grooving-edge-of-OSB-1

    Tongue-Grooving-edge-of-OSB-2

    Tongue-Grooving-edge-of-OSB-2


    The last thing we did was to bring in a dozen more sheets of our 18mm OSB boards from our storage piles outside under canvas, we will need at least eight more boards to finish off Bedroom 3.
    Oh yes, we moved some of our LED flood lamps from upstairs and mounted them into the back bedroom where we have all the sheet materials and several lamps in the room we are doing because the place is getting darker with the rooms being built and blocking off light in all directions!
    Next week, among entertaining family members, we will continue putting up wall boards and even maybe a layer of the fermacell (plasterboard like material) on too and get to see an almost completed room, apart from the ceiling and the doors for the en-suites etc.

  • Floorboards Installed plus Various Wall Conduits Laid in Place

    Continuing with Bedroom 3, this week we installed more various elements into the wall and floor structure to provide additional functionality to the operation within the room like, for example, a control box that will contain the electronic controller, a display module and local circuit breakers for the power lines. This was constructed from sheet of left-over 12mm thick plywood board material and made two open faced boxes, measuring 360mm wide, 75mm deep and 400mm high.


    We designed it this way to allow the shell to be fitted into the wall structure but not too deep to intrude into another mechanism like the sliding door modules. These boxes will be covered up by the wall boards, the 18mm OSB sheets later on but will have internal brackets and fuse holders plus a display unit with built-in audio amplifiers to help drive the four speakers that will be the standard provision in this size of rooms.
    The next task was to drill 20mm wide holes for more conduits to connect to this buried box and through the utility channel too and plus another one going up to the ceiling to serve the lighting circuits. Talking about conduits, we installed a couple of extra ones either side of the entrance to the room, these being 20mm diameter pipes, to help thread the mains AC power lines in and around the utility channel. At this point, we have still the problem of having a flexible conduit that also needs to go either side of the entrance, this time to supply bunches of network cables, speaker wires and other low voltage signalling cables. Our supplier of the 40mm wide twin-walled conduits still have not arrived so we have been looking around for alternatives. It looks like that we will have to use rigid plastic plumbing pipework, the 32mm diameter size that is usually used for waste water plumbing but we could use that, coupled with sweep bends and achieve the method of channelling the cabling around our windows but we would still need a flexible solution and the nearest type we can find is a corrugated water hose being sold in 10metres length and 32mm internal diameter and this would be used at the entrances and going around en-suites etc. We will place an order for those solutions soon.

    In the meantime, we started looking at our air distribution system, the four separate orange 63mm ducting that will take the air to all edges of the room. We mounted our air splitter chamber in the entrance way so it is ready to be connected to the main air duct when that is constructed, and the four outputs were then connected to lengths of the orange 63mm twin-walled conduit. These conduits travelled across the room, cutting paths through the rigid foam board that covers the hot water pipes and anchored to various floorboard support legs and arrived in approximately the middle of each wall.

    Distributing-air-around-the-room

    Distributing-air-around-the-room


    Next was to design an sweeping adaptor that will take the output of this orange ducting and split the air into two sideway facing wings to send the fresh air along just behind the wall boards. We had thought that we could design a model on the computer and generate the object using our 3D printer but it turned out to be quite a complex shape sweeping up, backwards and then forward and sideways, all because the air duct is underneath the floorboard, has to go around the back of the support framework and arrive above the floorboard level but hidden behind the wall board. There were seven individual parts to make it possible to generate each 3D part on the printer (because of the limitations of building up the plastic object layer by layer so it is very very difficult to create hollows or bridges without it collapsing or having internal support structs etc.) and it would take well over 24 hours to just print one of these winged adaptors.
    3D-diffuser-feed

    3D-diffuser-feed

    We needed lots of them all over the house, at least fifty of them! So an alternative solution was needed and it found it by using the waste water rigid plumbing pipes, the solvent weld types, not the push fit ones. We took a series of 90degree bends with short straight pieces and created a fair substitute design that does the same job of channelling the air out and sideways behind the walls and into the room. We sliced little bits off various parts to reduce the size, trying to make it as compact as possible and eventually we applied the solvent and glued it together. It is a twin pipes going up and then turned to form the two outward facing wings. Finally, we took short lengths of the rigid 68mm brown pipework and experimented in heating it up with the hot-air gun and using various shaped wooden moulds, we could stretch the plastic out and then squeeze it down to wrap around the two 40mm pipes of our adaptor.

    Pipe-flaring-tool

    Pipe-flaring-tool

    Pipe-shaping-tool-inner

    Pipe-shaping-tool-inner

    Pipe-shaping-tool-outer

    Pipe-shaping-tool-outer

    Shaped-Splitter-pipe-

    Shaped-Splitter-pipe-

    Protoype-air-diffuser

    Protoype-air-diffuser



    We then did a test run by fitting it into the wall, underneath the large window in the room, placed two strips of the MDF strips (with little cut away sections) and screwed it up to the wall legs. We found two narrow pieces of our 18mm OSB left-over pieces and also screwed them on the horizontal rails so we created our air channel hidden behind the wall board. We connected the orange ducting up to the new adaptor and connected our old 150mm centrifugal fan to the main air splitter chamber to give it a blast of air through the system. We could feel the air gently sweeping along behind the OSB strips and gently entering into the room itself. We wanted to make sure that the air would gently distribute fairly evenly along the whole wall and had thought that we may had to cover the air channel with a cloth barrier to help guide the air to spread out but it turned out to work just fine without any additional cloth barrier after all.
    Prototype-in-place

    Prototype-in-place

    Test-channel-at-base-of-wall

    Test-channel-at-base-of-wall



    We then found some old pieces of underlay and carpet to place on the floor (just a sheet of 18mm OSB board that we are using to help us safely negotiate the floorboard support framework) and had a look at the finish results. The first implementation of the wall boards is positioned to allow a 50mm (a 2inch) air gap between the floorboards and the bottom of the wall board, to provide room for the air to escape and have our carpet fixed down in the gap. But we decided that 50mm was too big so we reduced the gap down by 12mm to just 38mm and looks much better. the air was still escaping out quite easily even with the carpet in place too.
    Carpet-under-50mm-gap

    Carpet-under-50mm-gap

    Carpet-under-38mm-gap

    Carpet-under-38mm-gap



    While we were doing our experiments, we ordered all the parts to make plenty more of these air divertors, some 450 pieces, a mixture of sweep 90degree bends and 90degree elbow bends plus also a pack of grey pipes too, all for overnight delivery. We made a jig to hold the parts whilst they were glued, This meant that we did proceed to make a further three adaptors and proceeded to install them into Bedroom 3, one under the smaller window, one along the section of wall just beyond the en-suite and the third one in the middle of the wall that is shared with the Utility room. We trimmed the orange ducting, applied sealant glue and therefore formed the ventilation system for the whole room.
    Final-air-diffuser-design

    Final-air-diffuser-design


    We also ordered 20 sheet of 6mm MDF board, paying a ridiculously high price for them (the world has gone mad for timber products!) and these will serve to provide the smooth backboard to the air channel. We will have to paint it black to reduce the gleam peeping out from under the wall edges.
    Another change of an implementation design and strategy was the cold water pipe. We had used the 28mm white plastic pipework that is designed for domestic water, especially hot water because it has a metallic barrier moulded into its wall thickness to prevent dissolved gases from “upsetting” the plastic material and forming weakness after a decade or so. But this kind of pipe is rather expensive and we need lots of it to provide our hot water circulation system. So we decided to swop out the 28mm cold water feed and replace it with 32mm polyethene water pipe instead. The pipe is much cheaper and even the T-junction adaptors are half price too so now we have a blue coloured pipe running from the Utility room and reaches the access chamber where we will have all our connections done to serve the en-suite basin, cistern and shower.

    Once we have doubled checked that everything is laid out, all the conduits, pipework and air ducts are in place under the floor, then we brought in loads of the shredded chopped up pieces of our left-over PU foam board and filled up the void and empty space in among the legs and pipework. We moved about two thirds of the content of our giant bag we got outside and filled the space to the level of the floor joist.

    Filling-the-undefloor-with-Scrap-insulation-1

    Filling-the-undefloor-with-Scrap-insulation-1

    Filling-the-undefloor-with-Scrap-insulation-2

    Filling-the-undefloor-with-Scrap-insulation-2



    The last day, the Friday, we tackled the task of laying down the proper set of the 22mm thick tongue and groove floorboards. This chipboard material was laid in the long direction, starting at the en-suite side of the room, slicing off the tongue so that the full thickness is fully on the framework around the edge of the room. We also sliced off the tongue at the beginning at where the entrance is so that would be ready to butt up when the hallway own floor is constructed. We put down three rows to see how it came together and everything looks good so we lifted those pieces up (they weren’t screwed down) and put in the finishing layer of glass wool to fill the final void directly under the floorboards to help deaden the sounds as much as we can do. The chipboard pieces were then placed back into place and this time, screws, three of them in each joist and also more around the edge of the room too. We put down 6 rows plus a little narrow strip to finish over by the large window. It was tricky to get the ends of each row in as the tongue needed to be inserted into the previous board’s groove but also to move pass the lowest horizontal rail on the wall too. This was especially true for the last narrow strip and we had to rasp a clearance slot where the wall posts were, just in order to get the tongue to engage fully into the groove. But we got there!
    Then-topping-with-100mm-glasswoool

    Then-topping-with-100mm-glasswoool

    Bedroom-3-Floor-finished-1

    Bedroom-3-Floor-finished-1

    Bedroom-3-Floor-finished-2

    Bedroom-3-Floor-finished-2



    That sees the flooring all completed now so we can now look forward to be doing the walls next. It is nice to see a room taking shape.

  • Continuing Putting Together Bedroom 3

    We continued with the work on Bedroom 3 and getting the floor, walls and windows ready. Whilst we are waiting for the deliveries, we got on with finishing the windows by putting the plastic vapour barrier around the bottoms and tops of the two windows. The first task we did was to insert small pieces of 25mm thick foam boards to encapsulate the last exposed bit of the concrete wall under the window and this will reduce heat losses and avoid condensation inside our window module. It was then a case of bending and folding the plastic up and over down into the chamber and back up again towards the oak frame under the glass. A slab of OSB 18mm thick board was then fixed into the bottom of the chamber to provide a mounting surface for the mechanical elements for our automatic blinds that will go up between the two pane of glass. The other piece of the black plastic was then inserted at the top end of the window to basically do the same job of sealing the wall structure from condensation derived from wet air generated by us human beings. The second smaller window was also done in a similar manner.

    Vapour-barrier-in-base-of-window-1

    Vapour-barrier-in-base-of-window-1

    Vapour-barrier-in-base-of-window-2

    Vapour-barrier-in-base-of-window-2

    Vapour-barrier-in-base-of-window-3

    Vapour-barrier-in-base-of-window-3



    The next job was to attach a line of left-over CLS pieces to run all the way around the room at the ceiling level. This line of CLS timber will support the top of the OSB wall boards, with a short section having had the timber planed down to remove 11mm to cater for the extra strong lintel we built over the large window that is needed to support the first floor joists etc. Then we did the middle support rail as well so that concludes the majority of the support CLS timber all around the room. The next short pieces are going above and below each window and above the main door and the en-suite too. The height of the upper rail will define the internal framework for the structure of the doorway and this distance is 2206mm from the floorboard surface. This will give us room to insert the Oak frames and provide clearance for the flooring covering (like carpets etc) and have a 7foot I.e. 2134mm tall doors.
    The windows also are set at this height so that both the windows and doors will match up with their openings, with the seats for the windows themselves will be set at 500mm off the floorboards. The seat will probably be 20 to 24mm thick Oak planks glued together and in the order of 365mm deep with a bull nose front edge sticking out into the room by 25mm or so.
    Last-two-rails-installed

    Last-two-rails-installed


    Then, still waiting for the delivery of our conduit tubing (we enquired and the supplier is having trouble in sourcing the 40mm twin wall conduits), we got on with doing the side walls for each window. A piece of CLS timber is needed at the back to extend the original framework around the window so that there will be sufficient support to hold the second oak frame that will hold the inner pane of glass . We had do some major planing of these timber pieces to make them line up with the original CLS so that the new oak frame will match up together. Long screws were drilled and driven through the full depth of the 63mm direction, to secure each piece into place. then yet another piece of CLS timber was placed, but this time at the front of the window section, just behind the horizontal rails, to form the vertical corners of the walls where the windows are inset and the fermacell “plaster boards” will provide the finishing surface coming along the wall and turning in towards the windows.
    Window-sub-frame-exstension

    Window-sub-frame-exstension

    Window-side-panel

    Window-side-panel



    One of the other tasks we did this week for this Bedroom, was to drill clearance holes through the horizontal timber pieces that forms the space for the Utility Channel and these holes had short length of various sizes of conduits and pipes inserted. These conduits helps to transfer the cabling from one side to the other of an opening like a window or door, to the other side so that the cables can carry on around the Utility Channel. There were 20mm diameter polyethene black pipes to carry the mains AC 230V supply and a second larger diameter plastic conduits measuring 37mm overall but 32mm internal, to carry all other types of cabling like network cat5, speaker wires, DC voltage power and other low-voltage types. We did the doorway around the en-suite plus also the two windows too.
    Conduits-fixed-to-base-of-utility-channel

    Conduits-fixed-to-base-of-utility-channel

    Conduits-bypassing-the-window

    Conduits-bypassing-the-window



    At last, our Flexible Twin Walled Plastic Conduits Arrives, but only our 63mm and 100mm types. We are missing the 40mm diameter one as it is in very short supply across the country and beyond. We are looking for alternatives to help us guide our low-voltage cabling around windows and doorways, we had some old wide bore water pipe so we used that one instead (it is the green ones).

    Now we could and did design and construct an air conduit splitter module (a plenum), which takes the 100mm feed coming from the main air duct, and splits the air flow into four separate 50mm streams to go off across the room to the four walls. We used left-over chipboard floorboards to build a triangular shaped chamber which squeezes from a 100mm gap, down to a 50mm spacing to spread the air out sideways, into four holes. The five holes all had short lengths of plastic pipes inserted and glued into place so we can just slide the conduits straight in and out to provide a good strong and tight seal. There were four 68mm wide pieces of pipe plus one 110mm wide sewage pipe, all ready for installation later on. We also did a small test of different glues and sealants to make sure that the plastic pipes we have used will stick to the twin-wall conduits and we can happily report that all four types we tried all worked just fine (PU sealant, PU construction glue, general purpose construction adhesive called Grip Bond and a modified polymer one called Stixall).

    Testing-joining-pipe-to-twinwall

    Testing-joining-pipe-to-twinwall

    Room-air-supply-plenum-1

    Room-air-supply-plenum-1

    Room-air-supply-plenum-2

    Room-air-supply-plenum-2

    Room-air-supply-plenum-3

    Room-air-supply-plenum-3



    The other task, the final one for the week is to slice up a sheet of our fermacell material, a gypsum mixed with recycled shredded newspaper board material, into 175mm wide strips so we can insert a backing panel in our Utility Channel, to both provide a surface to mount hooks and other lightweight items but also the fermacell layer will provide a fire resistant barrier to stop the spread of flames. So we took a sheet and sliced it up on our workbench table saw, set the fence to 175mm and cut six strips off one sheet. We went around the entire Utility Channel fitting each section with our new strips, occasionally having to trim the edges to make it fit and also in one section, we had two 20mm conduits sticking out the wall and had to drill a hole in the correct spot. We used the general purpose construction glue along the bottom and top edges, plus a line on each vertical leg and did the occasional vertical joint between fermacell pieces too.
    Back-of-utility-channel-covered-in-Fermacell

    Back-of-utility-channel-covered-in-Fermacell

    Exterior-conduits-passing-through-back-cover

    Exterior-conduits-passing-through-back-cover



    Another little job we did was to try out a test fit of some 6mm thick MDF board material to see how it looks and how it comes together, all to form the air dispersal channel running around the bottom of the wall, all the way around the whole room. We concluded that it will do a very good job so next week, we can look into doing that job.