Blog

  • Second Delivery of CLS Timber Arrives

    Our remaining timber arrived Thursday yesterday late afternoon. There were 348 planks in this second delivery, adding with our previous one of 99, we now have 447 planks of 63mm by 38mm CLS untreated soft wood, each measuring 4.8metres long.
    We spent the last hour of Thursday and several hours on Friday morning, moving the entire load into the house and storing them all down in our Great Room.

    Second Delivery of CLS Timber Arrives

    Lots-of-wood-ready-to-use


    We are missing one plank plus also one of the pieces was seriously damaged so we have requested replacements

  • Tidy Up and Replace Lighting Units Plus Installed New Camera System

    After skipping the first day of the new week because of some appointments, the next three days we went around tidying up the house after we had finished the Entertainment Room, dismantling the wooden platforms that were still inside the room. We also cleaned up all the mortar spillage that had dropped down to the floor and swept all the rubbish out.

    Tidy Up and Replace Lighting Units Plus Installed New Camera System

    EntRoom-Shell-Finished-1

    Tidy Up and Replace Lighting Units Plus Installed New Camera System

    EntRoom-Shell-Finished-2

    Tidy Up and Replace Lighting Units Plus Installed New Camera System

    EntRoom-Shell-Finished-3

    Tidy Up and Replace Lighting Units Plus Installed New Camera System

    EntRoom-Shell-Finished-4



    Next was to replace the burnt out floodlight we had up on the Skylight and put up eight new smaller 100W LED lighting units. We put two in the Utility Room which is becoming our new Tools area. Then mounted the remaining six units around the Skylight area, near each metal support leg, and rotated the existing 300W LED floodlight more horizontally to illuminate our workshop area down in the Great Room.
    Tidy Up and Replace Lighting Units Plus Installed New Camera System

    New-work-lights-1

    Tidy Up and Replace Lighting Units Plus Installed New Camera System

    New-work-lights-2



    The third thing that happened this week, was the installation of our new camera system. A dedicated recorder box and a couple of 4K cameras. We put the recorder in the Utility Room and then ran a cable all the way down to the other end and up into the rafters to mount the camera as high as we could reach, to look down length of the house. We now can view and record all our work on building the internal rooms and also the first floor rooms too. The second camera is being held as a spare for the time being but it is likely to be employed later on when we start doing individual rooms and will mount it on a upright stand and capture what we are doing.
    Tidy Up and Replace Lighting Units Plus Installed New Camera System

    New-camera-Daylight

    Tidy Up and Replace Lighting Units Plus Installed New Camera System

    New-camera-Nightlight



    The last thing that happened on Thursday late afternoon, was the arrival of the remaining CLS timber we wanted, see Second Delivery of CLS Timber Arrives it took us until Friday lunch time to move all of it into the house.

  • Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    This week it is the turn of the Concrete Beams and hundreds more of the concrete blocks to be hoisted up and laid out to form the roof of the Entertainment Room’s internal sound proofing shell.
    The first job was to construct a lifting hoist location where each individual 120kg beam is lifted up and swung around, to get pass the skylight metal leg and lowered down to the top of the concrete wall.

    We got three of our shorter metal scaffolding modules, plugged them together and then clamped the whole thing to the wooden wall. Then we got our metal hoisting arm up (only just fitted, avoiding the skylight) and then attached the electric winch.

    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Setting-up-hoist

    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Hoisting-a-beam-up



    We first lifted two beams up and got them positioned over the far end of the room, near the window. This allowed us to then set and position the second of our heavy duty angle iron piece, with clearance holes drilled into it and then glued and screwed on to the wooden legs of the external wall.
    Then we sliced up one of our paving slabs down the middle to give us two similar pieces, 900mm long by 300mm wide, plus a small bit left-over from the previous time of using the paving slabs at the bottom of the window, to make a filling in piece measuring 240mm wide by 300mm deep. Then, we glued on half bricks on the edge of all three pieces so that they can sit on the concrete beam and form the lid over the window, sitting on the metal angle iron and the beam. We wanted to raise this “lid” higher to maximise the space above the window to ensure that we had enough room for our mechanism for controlling the automatic window blinds. We glued these composite pieces using regular PU glue to stick them into place.
    On Tuesday and Wednesday, we proceeded to lift up the remaining eight beams and 162 blocks, plus 5 further blocks sliced down the middle to form the finishing piece in each row.
    We used spray PU foam to act as a glue and space filling at the same time on each block as we inserted a block along the beam. Not forgetting the two driveway 50mm thick concrete bricks were placed at the start and end of each beam to fill in the gap between them sitting on the wall.
    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Gluing-blocks-in-with-foam


    The last day, Thursday, we had to fill in the tenth row which was half the width so we sliced nine blocks in half to produce a filling in piece, measuring in a set between 190mm to 200mm wide and also cutting down two more bricks to fill in the final space on the wall.
    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-All-blocks-installed


    We had a half bag of cement powder left over so adding two buckets of soft sand, we mixed them together in a dry form, ready to vibrate in all the joints on the roof. But first, we nicked a quarter of it to make the normal mortar “muck” to stick down the last row of half blocks to the top of the wall and finishing off the whole roof.
    Then we proceeded to pour the dry mix all over the roof, brushing it over all the joints, banging and vibrating the roof using a piece of wood and club hammer and filled up the cracks between the blocks and beams. Finally, we went over the roof surface and sprayed a small quantity of water to help activate the cement and harden it up.
    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Grouting-the-blocks

    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Blocks-grouted


    The rest of Thursday and much of Friday was spent tidying up all the equipment, taking down the winch motor and its metal lifting arm, sweeping the floor and creating a “rubbish” bag down the bottom of the garden (using one of those large ton bags and four old metal re-bars to act as legs) and moved all the broken and sliced concrete block remainders, dismantle the various wooden templates and finally moved the cement mixer away from the Front door area.
    One thought that came up, was to get the ceiling battens installed now, rather than later on because we might forget to do it before we put up the First Floor Joists, which may impede our attempts in screwing up the CLS 63mm battens up inside the Entertainment Room. So Saturday was spent in doing that to get it all done and dusted before we forget and before we dismantled the wooden platforms too. We drilled six holes through each row of the concrete blocks (they are 6mm holes), just alongside each concrete beams, a total of 60 holes for the 150mm long screws to go through and grip the CLS plank of timber.

    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Roof-sprouts-screws


    We used 3.6 meter long 63mm sized pieces because they very nicely brought the surface of the ceiling just clear of the concrete beams, which makes it very easy to then screw and glue up the ceiling boards later on. We then screwed the wood up leaving a gap which we sprayed PU foam glue into, after which we tightened the wood up squashing the foam tight.
    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Ceiling-support-battens-

    Concrete Beams and Blocks Forms the Lid for the Entertainment Room

    EntRoom-Ceiling-support-battens-glued


    So in just over three weeks, we constructed a complete concrete shell from start to finish! Not Bad! And it took only a little bit longer to build the wooden framework that surrounds the whole room. Very nice to see that all complete.
    The next job is to start bedding down the footplate (double layer of treated CLS planks) that makes up rest of the rooms onto the concrete floor.

  • Untreated 63mm by 38mm CLS timber Arrives

    We had our delivery of fresh timber arrive today, this morning, but it turned out to be only fraction of what we ordered.

    Untreated 63mm by 38mm CLS timber Arrives

    CLS-Delivery-20201120-1

    Untreated 63mm by 38mm CLS timber Arrives

    CLS-Delivery-20201120-2



    There was some confusion back in the builders merchant yard and we only got 99 planks. We were expecting 448 planks, which supposed to be a complete pallet load. We are chasing them up!!

  • Concrete Shell Almost Finished

    Monday, we did two and half layers in building up our wall inside the Entertainment Room, that is over seventy blocks! We completed layer 4, then number 5 and number 6 and a little bit of layer 7.

    Concrete Shell Almost Finished

    Entertainment-room-Blocks-Row-6-Finished

    Concrete Shell Almost Finished

    Entertainment-room-Blocks-Row-7-Started



    Tuesday, it was a half day because we are reaching the limit of lifting up the 20kg concrete blocks high enough to get on to the progressing walls whilst being able to see if they were in the right place. We finished layer 7 and a section of layer 8, for which we had to use one of our mobile platforms so we could use up most of the mortar mix we had. The remaining of Tuesday and Wednesday was spent building a safe, spacious working platform for us to stand on and continue building up the wall and finally put on the roof without compromising our effort and muscles. The platforms were made from the same basic frame work as the external one used for the roof, we just adjusted the length of the legs to suit.
    The last part of Wednesday was spent moving 121 concrete blocks and making four piles in the middle of the room, ready to be lifted up onto the platform. We couldn’t immediately start a new mortar mix because it was far too late in the afternoon as it generally takes three hours to apply that amount of mortar to the 50 blocks or so. So instead, we moved enough blocks to finish off the final three and half layers (number 8, 9, 10 and 11) before we reach the critical twelfth layer.

    Thursday saw us put up over eighty blocks to finish off layer 8, get layer 9 and 10 done completely and on Friday morning, to did layer 11. We also put on the lintel over the doorway.
    For the rest of Friday, we laser surveyed the height of the wall to find minimum and maximum variations so we can adjust the height of the final twelfth layer. As the result of this survey, we sliced up 27 blocks of 135mm high, 9 blocks of 185mm high and a couple of 70mm thin ones over the doorway (sitting on the lintel).

    We test fitted all these blocks in “dry” mode, including cutting down those blocks in corners and around the windows so everything was ready for the final stage in completing this twelfth layer.
    So finally on Saturday afternoon, we mixed our usual load of mortar and proceeded to stick down all these shortened blocks and again, using the laser level , we made sure that they all finished up nice and flat.

    Concrete Shell Almost Finished

    Entertainment-Block-Walls-Done-1

    Concrete Shell Almost Finished

    Entertainment-Block-Walls-Done-2

    Concrete Shell Almost Finished

    Entertainment-Block-Walls-Done-3




    So this concludes the building of the concrete walls and on Monday, we can start the massive job of lifting the ten 120kg concrete beams up and plonk them on our new wall!! No Sweat!

  • Concrete Wall Grows Taller

    For this new week, we started the task of building the concrete shell that will sound proof our Entertainment Room. The first task was to make a template to help us align the rows of blocks so we put together a piece of plywood with a straight CLS timber to stiffen the board and stop it from curling. Then marked out two lines set apart by 225mm which is the height of a block plus a layer of mortar. Then we marked along the lower line with marks spaced at 450mm (the length of a block plus a mortar).

    Concrete Wall Grows Taller

    Block-alignment-and-spacing-Template


    Then, in the mid-afternoon of Monday, our Concrete Blocks Arrives. We had ten pallets to unload!
    So on Tuesday, we could start laying out the first layer of blocks around the room, making adjustments, and then tackle the job of slicing concrete blocks to the required size. For this we created another jig, see Jig to Slice Concrete Block to help us.
    On Wednesday, our Ten Concrete Beams Arrive very early, but we had other tasks to do in the morning and the afternoon was spent dealing with the beams.
    So we didn’t actually start putting our blocks into mortar until Thursday and it was a very long day. We got all the equipment out, the cement mixer, wheelbarrows, the plasticiser, water hose and measuring jug. We got our first load of mortar done and didn’t finish that load until well past 2pm. We had a quick lunch and resumed at 3pm. The second load got us all the way around the circuit of the room plus half the second layer, and we finished 7:15pm! We had put down sixty blocks, each weighing 19kg each!
    Concrete Wall Grows Taller

    First-days-block-laid-1

    Concrete Wall Grows Taller

    First-days-block-laid-2



    The next day, we got the second row done, including stopping and starting either side of the door entrance (we created a quick wooden guide to ensure that we had a 50mm clearance to the door frame, so we can insert a vertical plank of timber to create the inner framework). We got all the third layer done too and got further around on the fourth layer, but this time deliberately avoiding the window area as that needed special attention.

    The final day, Saturday, we tackled the job of putting an extension of our concrete shell out towards the window. We found a heavy duty angle iron in our supply, a left-over length from when we were building the steel framework up in the skylight. We sliced off two length of 2050mm each, de-rusted them thoroughly, and then drilled five clearance holes. Both were painted with a rust protective zinc paint and then the first one (with the holes) was placed onto the concrete outer wall underneath the window.

    Concrete Wall Grows Taller

    Wall-support-steel-angles


    Five holes were duly drilled and five concrete screws were driven in. we also put in a good amount of PU glue to stick the metal bar to the concrete wall to provide extra security and load bearing capabilities.
    Concrete Wall Grows Taller

    Bottom-wall-support-attached


    Then we got two more concrete blocks and sliced them with a sticking out bit at the back. These blocks are the start of the vertical sides of the window alcove and they rest on the metal support and have a little sticking out bit at the back to reach the wooden framework of the window. we left a small gap and that will be filled up with expanding foam later on. Then we sliced up two paving slabs to create a shelf across underneath the window. These paving slabs are very, very hard and the diamond cutting blade had to work very hard, even just to slice 10mm deep into the 50mm thick slabs! We eventually sliced both sides and hit the slab with a club hammer to break it apart. We needed pieces 345mm wide and width in total of 1845mm wide. We made three pieces from our 600mm by 900mm slabs.
    Finally, we were ready to stick all the pieces into place, so mixed up a small portion of mortar and using some left-over Stixall glue (on the metal bar and between the paving slab pieces), we got it all assembled, including finishing off the fourth layer around the window.
    Concrete Wall Grows Taller

    Bottom-of-window-enclosed-in-concrete



    We can on Monday to continue putting up the next eight rows in reasonable ease (apart from the growing height), until we reach the top when the next complicated bit needs special treatment, the ceiling!!

  • Ten Concrete Beams Arrives

    Suddenly at a bright early hour, our concrete beams, all ten of them, arrive! We had to parked them on our driveway in such a position so we could then transport each beam inside the house through the Side Door, without hitting problems like trying to turn a 4metre long object around a sharp 90degrees turn! We also had to keep the driveway clear to allow our car out too! Phew!

    Ten Concrete Beams Arrives

    Conctete-Beams-Delivered


    After doing other chores and tasks in the morning, we started the heavy duty of moving these beams into the house. We bolted two large castor wheels to a slab of timber, already predrilled with the holes because these 2inch by 6inch short planks were used several years ago when we were moving the huge steel RSJ beams!
    But this time, we moved the 120kg concrete beams, once at a time, by clamping the wheels to the beginning of the beam and clamping a long wooden handle to the other end to allow us both to lift it up. Dragging the beam over to align with the Side Door, we proceeded to push each beam into the house, down the ramp and slipped past the various obstacles and parked them half way down in the middle of house, next to the metal roof legs.
    Ten Concrete Beams Arrives

    Beams-carried-inside


    It took us all afternoon to move the ten beams, being careful not to overtax ourselves and not to cause any damage to our house! The big challenge will be when we need to hoist them up and put them on our Entertainment Room concrete walls to form the roof! That’s another day’s Job!

  • Jig to Slice Concrete Blocks

    This morning, we created a jig to help us slice up concrete blocks using our large mains powered angle grinder fitted with a diamond coated cutting blade. We put several chunks of timber and OSB pieces together, to form a fence with a ruler attached to it, plus a right-angle flat surface using a piece of plywood to guide the machine at close to 90degree as possible.

    Jig to Slice Concrete Blocks

    Block-cutting-jig-1

    Jig to Slice Concrete Blocks

    Block-cutting-jig-2



    The angle grinder and the blade was able to cut fairly easily through just over half way through the 100mm thick concrete block and just turning the block over, we could slice quite neatly a block to a given size.

  • Concrete Blocks Arrives

    The first load of new building material arrived today. 576 dense concrete blocks arrived with a ton bag of soft sand, eight bags of cement, two large paving slabs and one concrete lintel.

    Concrete Blocks Arrives

    Concrete-Blocks-and-Sand


    The remaining 74 blocks will be delivered soon, along with the 10 concrete beams. We are glad that we beat the lock-down deadline!

  • Stud Wall Built and Covered in Fermacell Boards

    This week, we started on building our timber Stud Wall that surrounds the concrete shell that encloses the Entertainment Room. But before that, we created another piece of equipment down in our Great Room area, to help us chop up the various timber planks into precise lengths required for each wall around the house (see Chop Saw Plank Slicing Station).
    We marked out on the footplate the spacing for all the stud posts for each section of the wall, requiring a 400mm separation of the posts for the 89mm wide walls (the left and right sides of the room joining the Utility Room and hall leading from the front door) and a 600mm spacing for the end wall opposite the window. We duplicated these marks on another set of horizontal planks we made, ready for the top plate that goes on top of the stud posts.
    We then chopped up twenty-one 89mm CLS and eleven 63mm CLS planks measuring 2638mm long, then two 2600mm long pieces, both being the 89mm CLS width and finally, an one off 2804 length of 63mm CLS.
    We proceeded to nail each post into place using 90mm ring-shank nails and put on the top plate planks on too. We also glued two of the 63mm posts to the steel leg (holding up the Skylight and roof).

    Stud Wall Built and Covered in Fermacell Boards

    Entertainment-Studs-Finished


    The last job of the week was to nail up sheets of the fermacell boards on the inside surface of the stud walls to improve the sound deadening potential of the whole Entertainment Room. We placed each sheet horizontally, over two and bit rows and applied to all the edges with PU construction glue to ensure a continuous uniform and solid barrier.
    Stud Wall Built and Covered in Fermacell Boards

    Entertainment-Fermacell-all-installed-1

    Stud Wall Built and Covered in Fermacell Boards

    Entertainment-Fermacell-all-installed-2

    Stud Wall Built and Covered in Fermacell Boards

    Entertainment-Fermacell-all-installed-3




    We are now ready for the concrete blocks and beams which will hopefully will be delivered Monday and Tuesday, just before the lock down is enforced. That will keep us busy for a few weeks.