Skip to content
  • Mon. Jul 7th, 2025

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed
Build Progress Guttering Phase 4 Porch Roof

Metal Posts Installed, Platform Modules Rearranged and Guttering Completed for E

Sep 7, 2019 Shaun

Monday, we had a little quick job of making some extra shelving for our living quarters, made out of pieces of plywood lying around Then we got on with installing…

Build Progress Phase 4 Roof Slates

Roof Section A More or Less Complete and Three New Aluminium Posts Created for Front Porch

Aug 31, 2019 Shaun

We had a bank holiday Monday to our week so we did a slow day of measuring the Front Porch various elements so we can adjust the level of the…

Build Progress Guttering Phase 4 Roof Slates

“P” Roof All Complete, Mesh on “A” Gutter, Half of “A” Roof Covered in Slates and Flashing Installed Along Skylight

Aug 24, 2019 Shaun

Another week is complete, with lots of Slates being mounted plus some little bit of work on the window’s octagon pillars. The hip flashing was first to be done, with…

Build Progress Guttering Phase 4 Porch Roof Slates Windows

Membrane Installed on Section A and B with Half of Wooden Battens Plus Work on Oak Timber for Windows

Aug 17, 2019 Shaun

This report is for the last two weeks of work, we had some of the days on other commitments, but we mostly worked on our roof with some in our…

Build Progress Guttering Phase 4 Roof Site Maintenance

Gutters Installed but also more Site Clearance done too

Aug 3, 2019 Shaun

It was another week of a mixed bag of jobs and tasks, but we made progress on the guttering, oak planks for our windows and did some site clearance too.…

Build Progress Phase 4 Roof Site Maintenance Slates Windows

A Mixed Bag of Tasks and Jobs Done This Week

Jul 27, 2019 Shaun

A week of a mixed bag of lots of little tasks, jobs and errands, with a mixed bag of super-hot days, thunderstorms and a cool damp day to finish the…

Build Progress Phase 4

26 Oak Vertical Pieces Produced for 13 Windows

Jul 20, 2019 Shaun

For the last three days of this week’s work, we were in the workshop processing the pile of Oak timber that makes up the vertical elements of the window frames.…

Build Progress Phase 4 Roof Slates

Both Sides of Q and Three Quarters of P Covered in Slates

Jul 17, 2019 Shaun

For the first three days of the this week of work, we were lucky with the weather but also unlucky as we suffered in the heat too! But we did…

Build Progress Phase 4 Roof Slates

Nearly 2000 Slates Mounted + Some Work on Window Frames

Jul 13, 2019 Shaun

We started this week with good dry weather in resuming the job of mounting Slates up on to the roof. We finished off the little bit left to do on…

Build Progress Phase 4

Finished off the Oak Sills and Headers for the 13 Windows

Jul 6, 2019 Shaun

On this rainy day, we worked in the workshop on our Oak timber pieces for our window frames. We carried on with the task of shaping the Sills and the…

Posts pagination

1 … 27 28 29 … 148

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

Proudly powered by WordPress | Theme: Newsup by Themeansar.

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed