Skip to content
  • Sat. Jul 26th, 2025

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed
Rafters Rain Stoppage

Postponed O Ridge Installation!

Sep 15, 2017 Shaun

Starting really early this morning, at round 8:30am, to avoid the incoming thunderstorm front, we went outside to have a go at installing our latest created rafter, this time, the…

Build Progress Phase 4 Rafters

O Ridge Parts Are Married Together!

Sep 13, 2017 Shaun

Today, we tidied up the two sections of the O Ridge rafter by running the power planer along all the edges, the top and bottom edges. This made sure that…

Rain Roof Temporary Accommodations

High Winds Rips Off Roofing Felt!

Sep 13, 2017 Shaun

We woke up to the rattle of tremors of storm Agnes passing over and when we looked outside, we discovered a piece, actually quite a long piece of roofing felt…

Build Progress Phase 4 Rafters

O Ridge Part 1 and 2 Assembled and Rafter LM is Installed

Sep 12, 2017 Shaun

This morning, we resumed our work on the O Ridge Rafter. The first part (the horizontal Ridge section) was vacuumed and then glued and nailed together. Then the second part…

Build Progress Phase 4 Rafters

Rafter IJ Goes Up and O Ridge is Started

Sep 11, 2017 Shaun

This morning, in a bit of a stiff breezy and chilly wind, we took out our first of the two rafters we completed on Saturday, but before that, I just…

Build Progress Phase 4 Rafters

Rafter IJ and LM Created!

Sep 9, 2017 Shaun

Today, resuming where we left off from the very short morning’s work day yesterday (which was cutting the legs for corners IJ and LM and then measuring the distance from…

Build Progress Phase 4 Rafters

Rafter JK and KL are Now Up!

Sep 7, 2017 Shaun

Today in the pleasant sunshine, we tackled the job of hoisting up the next two rafters, which are the rafters going into the corners JK and KL. After fiddling with…

Build Progress Phase 4 Rafters

Rafter JK and KL are Both Created

Sep 6, 2017 Shaun

Today, we carried on with the creation of the rafters for the corners where wall J and K meets and again for walls K and L meet, all part of…

Build Progress Phase 4 Rafters

JK Rafter Being Created

Sep 5, 2017 Shaun

After lunch, we resumed the task of creating the next rafter, this time, the JK diagonal LVL going from the K Ridge and down into the far outside corner of…

Build Progress Phase 4 Rafters

K Ridge Is UP!

Sep 5, 2017 Shaun

This morning, we resumed the battle with the K Ridge Rafter!! We first applied Plan K by slicing off the sticking out webbing down on the wall end of the…

Posts pagination

1 … 59 60 61 … 148

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

Proudly powered by WordPress | Theme: Newsup by Themeansar.

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed