Module Number 3 Repair – Day 3
Today, we finished off the job of resetting and re-establishing Energy Module Number 3 back into working order again. we dug out behind one of the ends to allow us…
A DIY Selfbuild by Stephen, Shaun & Daphne
Today, we finished off the job of resetting and re-establishing Energy Module Number 3 back into working order again. we dug out behind one of the ends to allow us…
It has been raining quite heavily all day so far and it is not nice out there. Our half completed repair work on Module Number 3 is sitting there gaining…
We continued with our repair of the Energy Module Number 3. We have managed to rescue the remaining crates, the rubber membrane and the geotextile fabric The we lifted the insulation…
Today, we started the chore of digging out the Energy Module Number 3 to reset it back down into the ground at the correct flat level again (after the flood…
In damp weather, we tackled the next source of flooding, this time coming off the Loke as the rain water collects together off the surface of the loke and some…
Today, we attempted to block off the rain water spillage coming from the workshop. See the little movie of the “river” gushing out of their workshop area (river starts at…
We were driven in by a sudden rain shower! it was very heavy and we have already 8mm of rain in just the 20 minutes we had so far as…
This morning, we connected the conduit pipes and inspection tube down into the Number 4 Energy Module. Then we pushed in the remaining sand / soil from around the hole…
We carried on with the task of filling our Energy Modules with water. Today, we finished filling Number 2 and started on filling Number 4 modules. The water in Number…
Today, we put on the insulation panels around the number 4 Energy Module. We inserted at least 300 mm thick of insulating boards, more like 350mm to 380mm thick! We…