Today, we started on the job of slicing up 55 6metres steel bars into 105
lengths of 2metres, and 100 lengths of 1metre.
Then all were bent right angles, so that it would be buried in the concrete
slab and provide vertical reinforcing rods for the hollow blocks.
Tomorrow, we will create the wooden framework to hold these rods in their
correct position.