Today, we finished off the installation of the insulation panels on top of our Energy Module Number 5. At the same time, we started pumping water into the module, we will need over 16,000 litres of water to fill it! Also we sliced off the excess pieces that were sticking up above the module level, and inserted the various conduit pipes and inspection tube too.

Module-5-All-Insulation-and-pipes-done

Module-5-All-Insulation-and-pipes-done

We chucked all the “rubbish” bits into the gap alongside the module and buried them with the sandy soil we are pushing back in.

Module-5-End-of-Day-7-Nearly-finished

Module-5-End-of-Day-7-Nearly-finished

Tomorrow, we will finish off the filling around the module plus another whole day of putting water into the tank.