First Delivery Arrives – 300 Sheets of Plywood
Today, we had our first delivery of the huge order of building materials we got coming, namely the 300 sheets of the 12mm plywood. It should have been 330 sheets…
A DIY Selfbuild by Stephen, Shaun & Daphne
Today, we had our first delivery of the huge order of building materials we got coming, namely the 300 sheets of the 12mm plywood. It should have been 330 sheets…
The Modular Work Bench for our Circular Saw, Router and Mitre Saw is progressing. The last few of days of work have seen the construction of the fence and also preparing…
While we have been waiting for the prices and delivery of the building materials to be completed, we needed a replacement saw table to make it as easy as possible…
Yesterday and today were spent levelling out areas alongside our Loke, so our building materials can be delivered and unloaded. We want to make sure that we can access each…
This morning, we had the confirmation of prices for the rest of the building material for constructing the exterior skin of the house. Nearly everything needed to build the complete…
Today, at last, we have started the ordering process! We have got the last of the prices in and we have selected our suppliers. The first item ordered is 320 sheets…
Today, while we are still waiting for prices and quotes from the last of our building merchants to come back to us, a new Incinerator was constructed!! It was made…