Today, we finished off doing the last three Downpipe Channels and permanently fitted into place with glue and screws. These were along the back of the building, on IJ, LM and MN corners.

Last Three Downpipe Channels Permanently Installed

MN-Downpipe-installed

Last Three Downpipe Channels Permanently Installed

LM-Downpipe-installed



This concludes the six modules that are fully integrated into our building construction, fitting into the roof structure and the Fascia. The only other two Downpipe Channels are temporary and won’t be installed until we are ready to put on the roof boards around on the “P” and where the Conservatory would be constructed later on and hence why these two are temporary to provide an end cap to the guttering system in the meantime.

By Shaun