In quite strong winds, we concluded the job of hoisting and installing the remaining rafters to complete the “E” section of the roof.
Well, actually, there is an additional bit of the “E” section to do but this is part of the porch extending over the back door over the Utility Room and that will be done when we got the roof boards laid down first.
The next job is to measure and make the long rafters that forms part of the “B” and “D” roof sections, over the Entertainment Room and Front Door, this will be the next stage of the roof construction, switching to the 33 degree sloped roof sections. These are the C Ridge and K Ridge extensions, these two being the front door, hallway, stairs and the entertainment room and then all the en-suites, bathroom and Bedroom Two going back out of the building.