On Monday, we extended the existing Gable section of the roof that will form part of the Conservatory. Using the new stud walls built last week, we put up a 420mm extension to the ridge beam to make a sum total of 910mm (3feet). This new ridge was sandwiched between two layers of our structural 12mm plywood, glued and screwed together with a second full single length of 95mm by 45mm treated timber underneath to reinforce the extension.

Gable Roof Extended, Two Downpipe Channels Created and Resumed Preparing the P Section of Roof

Extension-of-Q-ridge


Then a couple of CLS 63mm timber pieces were fixed to the long diagonal rafters to provide support for the new roof boards and two fresh lengths of 4by2 timber cut to form the outer rafters of the new extended roof.
The narrow strip was covered with more 12mm plywood segments and it is now ready for the next stage of counter battens and the breathable membrane to be put up.
Gable Roof Extended, Two Downpipe Channels Created and Resumed Preparing the P Section of Roof

Extended-Q-roof


Tuesday through to Saturday morning was spent working on two new Downpipe Channels to connect to the gutters and to the future Conservatory. We carefully measured each position of each channel module (PQ-1 and PQ-2) and then pulled out a couple of planks of Oak timber, 27mm thick but one plank being 150mm wide and the other being 250mm wide. We also had a couple of left-over pieces already planed from a previous job. These forms the two sides and the wider bottom pieces of the channel module.
All was planed and cut to width.
Gable Roof Extended, Two Downpipe Channels Created and Resumed Preparing the P Section of Roof

Start-of-Q-Downpipe-Channels


The next job was to put on the tongue & groove edges to join the pieces together and using a PU glue, formed a very strong joint and a much more robust module. The two sides were shaped in a particular fashion so they will slide in and under the overhanging roof boards of the “Q” conservatory roof.
Gable Roof Extended, Two Downpipe Channels Created and Resumed Preparing the P Section of Roof

Q-Downpipe-Channels-Glued


Another gluing job was to stick on two layers of 12mm plywood squares (150mm across) and stick them under the modules in the position where the plastic drain pipe will come through. After they had set, we drilled a 114mm diameter hole through all the layers (22mm of Oak and the two layers of the 12mm plywood) and then glued in short lengths of drain pipe.
Gable Roof Extended, Two Downpipe Channels Created and Resumed Preparing the P Section of Roof

Q-Downpipe-Channels-with-Pipes-fitted


While that was drying and curing, we went outside to resume work on putting up Slates on the narrow diagonal strip to finish off on the “N” section of the roof. We got half way up by the end of the day.
Gable Roof Extended, Two Downpipe Channels Created and Resumed Preparing the P Section of Roof

N-Nearly-done


On the following day, we carried on working on the downpipe channels by cleaning up all the edges, especially the newly installed plastic pipe sticking through the bottom of the channels and then applied a coat of polyester resin and glass-fibre matting to fully waterproof these channels and provide a smooth surface for the rainwater to flow into the pipework. And finally on Saturday morning, we applied the black coloured top coat layer of resin to provide the slick surface and colour.
Gable Roof Extended, Two Downpipe Channels Created and Resumed Preparing the P Section of Roof

Q-Downpipe-Channels-ready-for-fitting


While that was hardening, we brought in all the thin OSB strips that has a “bull-nose” on one edge. We discovered from the first time we used these strips to form a flashing waterproof barrier for the Hip and Ridge lines, that the resin soaked into the open grain of the material so we spent a hour or so applying Polyfilla to all of them to bulk fill these gaps.
Gable Roof Extended, Two Downpipe Channels Created and Resumed Preparing the P Section of Roof

Bullnose-Strips-filled


We are in the middle of some very changeable and windy weather at the moment so we hope we can still proceed with our work. We have been lucky so far this year in general. Next week, we will install the new downpipe channels, put on the guttering and then start laying on the strips of roofing membranes all along “P” and the “Q” roof sections.

By Shaun