Sorting Oak Timber for Windows
Because we had an interruption of work outside, due to rain all day Wednesday and also Thursday morning, we switched over to doing alternative work indoors. This time, we tackled…
A DIY Selfbuild by Stephen, Shaun & Daphne
Construction of External Skin of House: External Walls, Roof and Skylight. Slate tiles on roof and timber cladding on walls.
Because we had an interruption of work outside, due to rain all day Wednesday and also Thursday morning, we switched over to doing alternative work indoors. This time, we tackled…
For our week’s work, we got on with the next three sections, the L, M and N which forms a U shaped inset. We first got all the tile battens…
We started the new week by finishing off the “Hat” covering the Hips for J-K and K-L as well as the ridge between J-L roof slopes. We filled in the…
It was a week of lovely dry weather. We started the week by tidying the workshop and completing the making of the Ladder Support stainless steel brackets and setting out…
The work this week was to cover the next three sections of the roof surface with the breathable membrane and protect the wooden Oak guttering with the required rubber material.…
Another week is done, apart from two days of interruptions (due to a day of rain and two half days of other commitments), we had a good week of work.…
Another week is done and we are progressing on the roof putting Slates on the J roof segment and Guttering on the next four sections from L to O. We…
We resumed work in new week by continuing slating the I section of the roof, Creating a roof ladder support system and getting the flashing line of slates onto the…
For this week’s worth of work, with lots of weather interruptions along the way, we started the actual process of putting up our Slates! Using our new collection of tools…
Today, following on from Saturday’s work, we designed and built a slate cutting guillotine with supporting stand which has rubbish collection built in. The guillotine sits on top of the…