While we were waiting for some replacement router tongue and groove cutters, we decided to get on and finish the final piece of work we started last year in May, see Installed Dozens of Conduits and Pipes through the External Wall for Future Expansion for more details. We had to wait because the location had […]
To finish off filling in the outer walls, and to provide a vapour barrier too stop moisture getting into our timber elements, we proceeded to cover up the glass wool with a layer of a plastic membrane, from top to bottom. We used the thick heavy duty DPM polyethene material, comes in rolls of 4metres […]
We spent a day or so making an air duct that will extract the hot air from the Conservatory. It needed to go inside the wall between the window and the door, going all the way from the concrete floor level and right up to the top of the wall and beyond. We used more […]
In preparation for filling and covering the walls we went around and planed off any of the plywood spacers between inner and outer wall posts which were sticking out from the wall, this will allow the horizontal rails to be nailed on without damaging the vapour barrier. It then only took a few days to […]
We spent these last four days putting in extra insulation foam boards over the top of all the doors and windows. We needed to do this first because when the vapour barrier plastic membrane goes around the walls, they will go over the doors and windows, and below the windows too. So we put some […]
At the beginning of the three weeks waiting for the arrival of our First Floor Joists, we sat down to analyse all requirements of providing connections to the outside world like electricity, data, water and waste services. We looked at the underground situation as well as the Eves too. We wanted to make sure that […]
Our Glass Wool insulation we ordered last week has arrived today. The delivery truck parked in our local Tesco Express (after asking the staff inside the shop for permissions) and came down to confirm that we were expecting this order. There were three pallets plus two loose packets. But fortunately, he had his own diesel […]
We continued the task of putting up reinforced wall posts for the hanging toilets for the cloakroom and for the en-suite of Bedroom 3 where we had to put down an additional footplate inside the knick-knack cupboard, to allow for a box to be built around the back of the toilet pipework and the sewage […]
We have resumed our task of building up the Ground Floor’s walls, at least, the structural framework structure using our 63mm CLS timber planks and over the last eight days we got quite a long way forward. But one of the first jobs was to redo the vertical timber pieces that were glued to five […]
By Thursday, after a couple of delayed days due to icy cold weather that would have stopped the gun foam from working properly, we finally finished installing the 200mm (on average) thick layer of polyurethane (PU) “seconds” foam boards. The last section was around the Great Room, in the west end, finishing off the Patio […]