Today, in glorious summer weather, we went around all the foundations and filled in the gaps and drop-offs around the edges of the foundations to the surrounding soil, so we didn’t “fall” off and twist an ankle or our trolley won’t move as it bogged down in the groove or the uneven surface.
Then we moved about 450 of the 720 blocks we have ordered, and positioned them spread out along the sides of the foundations strips for the Great Room, Bedroom 1, Bedroom 2 and finally part of Bedroom 3.
Tomorrow in the morning before the rain comes in the afternoon, we will finish off along the front of the building and down the garage side of the foundation strips.