Steel work Preparation Continues ..
Today, drilling and cutting of steel pieces continues with the 9 pieces which tie the front and back beams together.. These are about 2.6m long 50mm square tubes with two…
A DIY Selfbuild by Stephen, Shaun & Daphne
Today, drilling and cutting of steel pieces continues with the 9 pieces which tie the front and back beams together.. These are about 2.6m long 50mm square tubes with two…
Today, in the workshop, lots of pieces were drilled, like for example, the 10mm thick plates with 13mm holes in the 4 corners (7 of these, one for each leg).
This morning, again in brilliant sunshine, we finished off the smoothing and levelling out the ground around the Great Room. It is all very neat and tidy now and we…
Today, in lovely sunshine, we carried on with the job of moving and levelling out the excess piles of soil and sand heaped around the outside of the house. We…
The work continued today in preparing all the pieces of steel work, cutting some to the correct sizes, some being drilled with bolt holes and screw holes. There are hundreds…
Today, now that the steel has all arrived, all cross checked against original order list, the major task of preparing the pieces and practicing the various welds and drilling tasks…
Today, the work of smoothing out the ground around the outside of the house continues, working alongside the Garage and the side door of the house. Then, around the corner,…
This afternoon, the steel arrived and was off loaded. The lorry came backwards down the Loke. The big I-beam pieces were offloaded down inside the house itself, lying on concrete…
Today, before the steel arrived, the soil around the perimeter of the house and it’s wall, continued to be levelled, covering up the rainwater pipework and making it smooth and…
This afternoon, we continued with the tidying up operation, while we waited for the steel pieces to be delivered, by tackling the garage workshop! We took a load of rubbish…