Today, we started assembling the wooden dividers which go across the whole Floor Slab from the sections we made last week. We have done the Great Room and the section that includes the Kitchen and Bedroom 1.

Floor-slab-Cells-Day-1

Floor-slab-Cells-Day-1

It is working out reasonably OK, without too many difficulties, apart from sometimes the concrete foundation strip having a lumpy edge so we have to cut into the OSB strip a little bit to make it fit like a jigsaw. The fluffy expansion strips will be done later when we have completed all the wooden cells.

Floor-slab-Cells-Joints

Floor-slab-Cells-Joints

We carried on with the front extension section and tomorrow, will continue across from the Hall and Entertainment Room, towards the back and Bedroom 2 and then over to Bedroom 3 and finally the Utility Room.

By Shaun

Leave a Reply