The Main Six Legs Are Bolted Down
We continued the work of setting the legs to be in their absolutely correct positions and bolting them down. We are using a special bolts which ‘self tap’ into concrete,…
A DIY Selfbuild by Stephen, Shaun & Daphne
We continued the work of setting the legs to be in their absolutely correct positions and bolting them down. We are using a special bolts which ‘self tap’ into concrete,…
In the morning, we spent making 7 wooden struts with metal tabs on the ends to control and bring together the distances at the top of the six legs that…
On a rather warmer day, we got the seventh and final steel leg hoisted and positioned in the required place. We prepared for this operation by making two bracing beams…
As reported in the previous blog the wooden crane leg was damaged, we spent the last hour of the daylight to repairing the damage . About two thirds the way…
This morning, in a freezing strong wind, we connected the second pair of legs (number 2 and 6) back to the first pair (number 1 and 7) using U Channel…
It wasn’t so bad today in regards to ice, there were still patches of ice here and there but they were just melting and breaking up as soon as you…
Our concrete slab is frozen again and there are too many patches of solid ice. Again, we abandoned the outside work. Tomorrow, there are other meetings that have to be…
Today, Sunday, we woke up to a world of white over everything and a real chilly snap in the air .. this is indoors we are talking about! We were…
Yippee! The temperature overnight was warm, positively balmy at 5°C and the water lying around on our concrete didn’t freeze again and nearly all the remaining ice had melted by the…
Here we go! Here we go .. again! It was such a lovely sunny morning to the start of the day but we had freezing temperatures overnight and it refreeze…