Platform Number 2 Completed
We finished the 2nd platform today with a paint of exterior shed treatment which will help repel the rain water. The wooden safety hand rails were made using 50mm square…
A DIY Selfbuild by Stephen, Shaun & Daphne
We finished the 2nd platform today with a paint of exterior shed treatment which will help repel the rain water. The wooden safety hand rails were made using 50mm square…
We also spent some of the morning tidying up and doing minor servicing tasks around the site. We dismantled the painting tent and framework. We moved the 7 painted steel…
Today, we resumed work on our house building project after the disruptions of Christmas and new year holidays, some illnesses and a jury call up!! We needed another platform for…
We started to paint all the legs yesterday but ran out of paint, after ordering some more of the metal primer paint, we finished painting the last steel legs and…
Over the last couple of days, We took in the shortest steel I Beams into the workshop where a short piece of the top and bottom flanges, at both ends was…
This afternoon, we unloaded the 3 heavy legs and loaded the remaining 4 lighter legs onto the trolley and transferred them into the workshop. The Foot plates and Top plates…
Today, we tackled the heavy duty legs (number 1, 4 and 7), each measuring 160mm by 80mm by 5.4metres tall and with a wall thickness is 8mm!! (Each weighs about…
The 6 steel brackets were hung up in our painting tent this morning and painted this afternoon. Plus also the preparations for making the Steel Legs, all 7 of them,…
The task of the last two weeks (interrupted by a bought of illness), has been to cut and weld together pieces of 3mm thick steel plates into brackets. These are…
The last 4 steel cross strut members were painted this afternoon. The next job is to weld and make joist brackets to anchor the hip ridge and valley box beams…