Category: Groundworks

  • Adjusting Earth Tubes Chamber

    Today, while we waited for the building control inspector to visit us, we
    got on with making adjustments to the Earth Tube Mixing Chamber. We had
    originally constructed it several years ago and since then we had shifted
    the whole house position 300mm closer to the Loke and also put it 100mm
    deeper too! This meant that the chamber, constructed with solid concrete
    blocks (430mm by 215mm by 100mm wide) was slightly out of position and we
    decided to adjust the design of the chamber. Instead of the connecting
    “Tunnel” coming out the side like a letter T, we have moved the connecting
    tunnel to the end of the chamber, and will have it sweeping around and
    coming into the correct position from the Loke side of the house, underneath
    the main house foundation. We have it sloping down and curving around to
    fully go under the 150mm thick foundation strip and arrive exactly in the
    corner of the utility room.

    All this is for our fresh air supply for the house, the concrete tunnel
    measures 450 high by 250mm wide to allow the maximum flow of air with
    minimal resistance.

    Today’s job was to dig dirt and soil out for the route and insert in shuttering to form the foundation slab to build the tunnel upon.

    Earthtube-tunnel-foundation-shuttering

    Earthtube-tunnel-foundation-shuttering

    Tomorrow, we will make up a quantity of strong concrete and pour it in and
    while that is setting, we can get on with filling the sewage trenches.

  • Approval from Inspector!

    This afternoon, our building control inspector, Ken, came along and look at
    our sewage lines. He went around asking questions about what that line is
    for and what this sewage line is for, but he was quietly pleased with our
    quality of our work and gave us the nod!!

    We can now start filling in the trenches and rebuild the ground back up
    again, like the driveway!

  • Third Pipe Run all Finished!

    Today, in the morning, we finished off the 3rd and final pipe run. We bedded
    it down with the gravel and used the laser level machine to determine and
    make sure the slope is maintained all the way along the sewage pipe!!

    Pipe-3-finished

    Pipe-3-finished

    Now we await for the building inspector, Ken, to come and have a look, and
    with his approval, we will refill all the trenches back up!!!

  • Second Line Completed and Third almost Finished too!

    Today, in glorious sunshine for most of the day, we completed the 2nd line
    of sewage pipes and got it bedded down in gravel before any further possible
    collapses of trench walls!! Nothing did after all but .. !

    Pipe-2-Laid-in-drive

    Pipe-2-Laid-in-drive

    Pipe-2-Finished-2

    Pipe-2-Finished-2

    Pipe-2-Finished-1

    Pipe-2-Finished-1


    The 3rd and final trench is now cut, and the pipe has been fitted together.
    We just need to bed that one into gravel and make sure the slope is properly
    maintained.

    Pipe-1-dug-out

    Pipe-1-dug-out

    Pipe-1-pipe-inplace-but-not-leveled

    Pipe-1-pipe-inplace-but-not-leveled


    All the pipe runs goes downhill at an angle of 1° which is “1 in 57” which
    means 1 metre rise (or fall) for every 57 metres of pipeline. The
    requirement for sewage runs is between “1 in 40” and “1 in 80” so we got it
    smack in the middle, the one degree angle is very convenient for when the
    plans were drawn on the computer ? Smile!

  • Dug out Pipe 2 Trench

    We have dug out the trench for the second sewer pipe today. We dug most of it by hand as it was shallow and easy to dig. We stopped when we realized we needed a 15 degree bend in the pipe and we only had 11.5 and 22 degree bends in stock. Stephen went and purchased the bends while Shaun went out to see a client.

    Second-pipe-run-dug-out

    Second-pipe-run-dug-out

  • Second Sewage Line Started

    Today, we started the more difficult sewage pipeline, the one that is
    running across our driveway. It was tight to get the mini-digger in pass the
    garden shed, the air “earth tube” chamber module, the flower bed.

    We started by scraping the road surface off (recycled tarmac chippings)
    along the line required, and then dug down 1200mm (4 feet) for the required
    depth for the pipe to run along, downhill towards the sewage processing
    unit.

    We had a slight problem as the trench walls started collapsing. The sandy
    soil was too loose and didn’t stay up so we actually ended up having our
    mini-digger stranded at one end of the trench and when we tried to turn it
    to drive it out, it also moved the OSB sheet that was trying to provide some
    extra support and one of the tracks slipped slightly into the trench. We
    rescued the poor mini-digger by placing 2 by 6 inch timber planks across the
    trench and using the bucket arm to pressed down on solid ground to tilt the
    digger back up again and slide the timbers planks under the track. Then, we
    managed to drive it off and away from the “danger zone” – phew!

    Digger-nearly-falling-into-Trench-1

    Digger-nearly-falling-into-Trench-1

    Digger-nearly-falling-into-Trench-2

    Digger-nearly-falling-into-Trench-2


    We will have to finish off the trench by hand, the old fashioned way of
    digging! Oh well!!

    The current three quarter done trench is now covered with three OSB boards,
    with another 2 on top plus a third layer on top of that too. this is to
    allow us to get our car out! Fortunately, the car went over the “bridge”
    quite happily – thank goodness!!

    Driveway-Trench-covered-up

    Driveway-Trench-covered-up

    Driveway-Trench

    Driveway-Trench


  • First Pipe Laid!

    Today, we did the 1st of three sewage pipes that needs to be laid in and
    under the house, before we put in the foundations and floor slab.

    Pipe-3-Laid

    Pipe-3-Laid

    This was a short one, from the kitchen and running more or less along the
    front of the house nearest to the Loke and terminating into the man hole
    junction just before the drive way.

    It has to be buried, starting at the kitchen end, 750mm below ground, and
    falling away downhill at the normal “specs” of 1 in 40 slope to arrive at
    the man hole junction point at 950mm deep. That was the easier one to do!
    Tomorrow, weather permitting, will be the one that has to go across the
    drive way and has two bends in it too!

  • Double Check Calculations of Sewage pipe Positions

    This afternoon, we spent the time going over the drawings, calculating the
    exact positions of the sewage pipes coming out the ground (and through the
    concrete slab). We also discovered that the swimming lane is pretty accurate
    and parallel to the house. This and the garage as the 2nd reference point,
    will form the basic alignment for the whole house.

    We created a spreadsheet of all the distances from each of the batter boards markers to all “interest” points on each of the three sewage pipes we have got to
    run under the house.

    We now have these numbers, we can start marking and cutting the narrow
    trench lines for the plastic pipes to go in.

  • Foundation Trench Constructed!

    We have finished constructing the foundation trench framework.

    We put in about 8 tons of crushed builders rubble (maximum 75mm / 3inch
    size) and then blinded the surface with clean sharp sand (about 1.5tons).

    All was compacted down several times for each layer.

    This concludes the framework and now ready for the ready mixed concrete to
    be poured in.

    Base Dug out and Framed

    Base Dug out and Framed

    Hardcore placed and compacted

    Hardcore placed and compacted

    Trench blinded with sand

    Trench blinded with sand


    But first, our next job is to cut the reinforcing bars into required lengths
    and bent right angles for most of them. These are the vertical rods to be
    placed around the edge of the foundation to line up with the block walls and
    the hollows. A wooden support structure will hold the rods at the correct
    level.

  • Swimming Lane is Next to do

    We have decided to start building the swimming lane first before the main house, because we had a serious problem with rain water this week, when we had very heavy rain falls gushing off the neighbours workshop and garage grounds.

    So we are building a steel reinforced heavy duty block wall nearest the fence, this being the back wall of the swimming lane. Then we can rebuild the soil back up again to stabilised the ground so we can repair the fence itself too.

    So the foundation is a 100mm thick concrete slab, set at the 9.200metre point (800mm below the nominal ground level), the first part of the wall will be made using 215mm wide concrete hollow blocks with steel 10mm reinforcing bars through all the holes and then ready mix concrete poured into each column to lock everything together.

    The back wall is 6 blocks high (215mm each equals 1350mm high including mortar joints), which will put us above our ground level but still 500mm (at least!) below the neighbour’s soil level. For this, we will put another two layers of blocks but only using the narrower (140mm wide) hollow blocks because there is less weight and load of soil and also at this point, there is a “return” channel for the water to flow back down to the beginning and circulate around through the swimming lane. This is our natural filtration system for cleaning the water, using lots of water plants.