Skip to content
  • Tue. Aug 12th, 2025

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed
Build Progress Foundations Groundworks Phase 3

The Front Section Virtually Complete!

Jul 28, 2016 Shaun

 We carried on with the front strip of the foundation, with the completion of the Hall and Entertainment bits and also part of the Utility room too. We were constructing…

Build Progress Foundations Groundworks Phase 3

The Front Trench Progresses..

Jul 27, 2016 Shaun

 This afternoon, after the morning was rather damp with rain showers, we started on doing the line of the foundation trenches along the front of the house. we have completed…

Energy Modules Repair

Module Number 4 Repairs All Done!

Jul 26, 2016 Shaun

 Today, we finished off the re-assembly of the Energy Module number 4, with the placement of the thick insulation boards around the outside of the module and then the lid…

Energy Modules Repair

Day 2 of Module Number 2 Repair

Jul 25, 2016 Shaun

 We carried on with the repair work on Energy Module number 4, the module living underneath the entertainment room. We pulled out, on one side, the vertical insulation foam boards…

Energy Modules Repair

Repair of Module Number 4

Jul 23, 2016 Shaun

 We switched over from doing the foundation trenches and its shuttering boards, over to repair the Energy Module number 4 that had risen. We thought we might need the use…

Build Progress Foundations Groundworks Phase 3

Finished Third Strip

Jul 23, 2016 Shaun

 This morning, we quickly finished off the 3rd front to back foundation strip we left over from yesterday. we then also moved some excess soil from around the front of…

Build Progress Foundations Groundworks Phase 3

Third Strip Almost Finished

Jul 22, 2016 Shaun

 For our half day of work today, we almost finished the 3rd front to back foundation strip, with another 2 square pads incorporated in the line. The ground was jolly…

Build Progress Foundations Groundworks Phase 3

Strip 1 and 2 finished and 3rd Started

Jul 21, 2016 Shaun

 Today, in slightly barely cooler weather, completed the first front to back foundation strip shuttering, then completed also the 2nd strip which has two expanded areas to support the legs…

Build Progress Foundations Groundworks Phase 3

Shuttering Boards Cut and Started Next Section

Jul 20, 2016 Shaun

 This afternoon, we sliced up 6 sheets of the 18mm OSB boards to make a collection of 2 different heights of shuttering. We made 12 pieces of 200mm tall and 16…

Build Progress Foundations Groundworks Phase 3

Back Section sides all Completed

Jul 19, 2016 Shaun

 Today, we finished off the shuttering for the back section of the building’s foundations. We put the two layers of the 89mm Timber to form the necessary height to hold…

Posts pagination

1 … 91 92 93 … 148

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

Proudly powered by WordPress | Theme: Newsup by Themeansar.

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed