Day 3 Filling Up Holes
We have finished all the metal shelving uprights slots and boards joints. We have filled in all internal corners (corners of rooms and light flange) to a smooth curve. Started…
A DIY Selfbuild by Stephen, Shaun & Daphne
We have finished all the metal shelving uprights slots and boards joints. We have filled in all internal corners (corners of rooms and light flange) to a smooth curve. Started…
We have started the massive job of filling in all the staple holes, joints between the boards and the slots where the metal shelving uprights live in. Also the ceiling…
The full Light Chamber is now complete, all 20metres of it, going right around the three sides of the garage room, starting from the front left corner, down the left…
Today and yesterday, we have been slicing up leftovers to create our light chamber around the edge of the main garage room. We bought two rolls of aluminium foil to…
Today we finished putting up the metal shelving uprights. The extra ones we needed came today in the post so all the four walls now have some shelves on them.…
We have finished slicing the walls up! All the slots for all the metal upright brackets are now done and ready for them. There are in total 64 individual uprights…
We have been slicing up the walls in the last three days! We have cut out the windows (again) to let in the daylight, trimmed around the counter weight panels…
The staples we are using to hold the Fermacell up are heavy duty wide crown staples. The crown in just under half an inch (11.1mm) and the wire is 1.5mm square.…
We have spent the last three days putting up the Fermacell sheets on the walls of the garage. Virtually all four walls of the front half of the garage is…
After all the analysis of design and everything, we come to a final list of plastic pipes, tubes and crates. It adds up to over £6500! The lion share are…