Skip to content
  • Mon. Jan 12th, 2026

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed
Build Progress Garage Groundworks Phase 1

Garage Slab Formwork done

Oct 18, 2010 Stephen

As we are on a tight schedule we started work at 9:00am and finished at 6:40pm, this is the longest day we have done so far! The morning was spent…

Build Progress Garage Phase 1

Preparing for the Floor Slab!

Oct 17, 2010 Shaun

This morning we pulled up the foundation’s formwork and it wasn’t too difficult thank goodness! Very nice smooth finishes with just a hint of a textured surface picked up from…

Build Progress Phase 1 Temporary Accommodations

Guttering is Up!

Oct 17, 2010 Shaun

Yesterday we put up the guttering on the front of the wooden temporary shed and our new front door. It was something we were meaning to do for a while…

Build Progress Garage Groundworks Phase 1

Temporary Driveway nearly finished

Oct 15, 2010 Stephen

We have been laying the granulated asphalt down over the last 2 days. On Thursday we laid an area in front of the garage which has a slope towards the…

Build Progress Phase 1

20tons of Asphalt recycled chippings

Oct 14, 2010 Shaun

We had a delivery of 20tons of recycled asphalt road chippings. We have spread it all over the area where our future drive way will be (in a couple of…

Build Progress Garage Groundworks Phase 1

Pouring the Garage Foundations

Oct 13, 2010 Stephen

The time has come! We are placing the first concrete on the site. We are using a special concrete from Lafarge called ‘Agilia Trench flow’. This should allow us the…

Build Progress

Early Start

Oct 13, 2010 Stephen

Well early for us! About 8:30 we started to prepare formwork infront of the temporary front door. This will give us a place to put any excess concrete later on. We…

Build Progress Phase 1 Site

Levelling and Tidying up ground around garage

Oct 12, 2010 Shaun

Spent yesterday and today levelling and tidying up the grounds in front of the garage and the storage shed to get them ready for laying down an asphalt hard-core layer…

Build Progress Garage Groundworks Phase 1

Concrete Man Comes!

Oct 12, 2010 Shaun

The concrete Rep from Lafarge came today to see our site. Full of very useful information. We have ordered 4.5 cubic metres and it is coming tomorrow at 11am. The…

Build Progress Building Control Garage Groundworks Phase 1

BCO approves Holes!

Oct 11, 2010 Shaun

Our friendly BCO have been and inspected our holes, ready for the concrete foundations of the garage. It looks very nice and well compacted he said so he’s happy, we…

Posts pagination

1 … 136 137 138 … 149

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

Proudly powered by WordPress | Theme: Newsup by Themeansar.

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed