Skip to content
  • Tue. Aug 12th, 2025

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed
Build Progress Energy Modules Groundworks Phase 3

Started Loading Water into Modules

Jun 14, 2016 Shaun

Also today, we started filling up the existing and completed Energy Modules (number 1 and Number 2) to make sure we don’t suffer from another incident of rainwater getting underneath…

Build Progress Energy Modules Groundworks Phase 3

Number 4 Progresses..

Jun 14, 2016 Shaun

Today, we dug out the bottom of the hole of the Number 4 Energy Module and inserted the two guide rails to scrape flat the bottom. We then washed the…

Energy Modules Rain Stoppage

Latest News: Number Three Module Has Risen!

Jun 13, 2016 Shaun

 Oh My! The buried energy module, Number 3 – our largest one we have done so far, has risen!! The rain we had today, plus the little we had yesterday,…

Energy Modules Groundworks Rain Stoppage

Module Number Four Progress Disrupted!

Jun 13, 2016 Shaun

 Rain Stops Play! This afternoon, after lunch, we discovered (by sticking our heads out of the door!!) that it was raining quite hard but it got worse even in those…

Build Progress Energy Modules Groundworks Phase 3

Module Number Four Starts!

Jun 13, 2016 Shaun

 This morning, we started on our “Number 4” Energy Module. It is our smallest one at “only” 2 meters by 1.5 meters for the water tank itself and the hole…

Build Progress Energy Modules Groundworks Phase 3

Number Three Module All Done!

Jun 11, 2016 Shaun

 The “Number 3” Energy Module has been completely buried and all finished. The three set of conduit pipes were inserted and connected all together in a central point, so that…

Maintenance Mini Digger

Grease Loaded into All Joints!

Jun 10, 2016 Shaun

 This afternoon, Stephen performed some basic maintenance tasks on the mini-digger and loaded grease into all the joints and moving parts. The digger needs re-greasing fairly regularly, every 20 “clock”…

Dumper truck Repair

New Stop Knob Fitted!

Jun 10, 2016 Shaun

 Stephen replaced the old defunct Engine Stop knob on the dumper truck with a shiny new one! It was a relatively simple job and took about 30 minutes. It is…

Build Progress Energy Modules Groundworks Phase 3

Number 3 Module Half Buried and Got its Lid On!

Jun 10, 2016 Shaun

this morning (only), we half buried the Number 3 Energy Module and put on the insulated lid. We sliced off all the edges and dumped the pieces in and around…

Build Progress Energy Modules Groundworks Phase 3

Number 3 Unit Assembled and Wrapped Up!

Jun 9, 2016 Shaun

We have assembled the third set of our collection of Energy Modules today, the second biggest one! We put down two layers of insulation boards, a total of 240mm thickness…

Posts pagination

1 … 95 96 97 … 148

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

Proudly powered by WordPress | Theme: Newsup by Themeansar.

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed