Front Trench Completed and Gone Around the Bend!
We managed to finish off the front line of trenches, going around the complex air tunnel and chimney section, and continued along the final long side, F6 to B6 front…
A DIY Selfbuild by Stephen, Shaun & Daphne
We managed to finish off the front line of trenches, going around the complex air tunnel and chimney section, and continued along the final long side, F6 to B6 front…
This evening, we had a short sharp heavy rain shower lasting only for 15 minutes or so and we had about 20mm of rain land on us! Generally, our new…
We carried on with the front strip of the foundation, with the completion of the Hall and Entertainment bits and also part of the Utility room too. We were constructing…
This afternoon, after the morning was rather damp with rain showers, we started on doing the line of the foundation trenches along the front of the house. we have completed…
Today, we finished off the re-assembly of the Energy Module number 4, with the placement of the thick insulation boards around the outside of the module and then the lid…
We carried on with the repair work on Energy Module number 4, the module living underneath the entertainment room. We pulled out, on one side, the vertical insulation foam boards…
We switched over from doing the foundation trenches and its shuttering boards, over to repair the Energy Module number 4 that had risen. We thought we might need the use…
This morning, we quickly finished off the 3rd front to back foundation strip we left over from yesterday. we then also moved some excess soil from around the front of…
For our half day of work today, we almost finished the 3rd front to back foundation strip, with another 2 square pads incorporated in the line. The ground was jolly…
Today, in slightly barely cooler weather, completed the first front to back foundation strip shuttering, then completed also the 2nd strip which has two expanded areas to support the legs…