Skip to content
  • Wed. Jan 14th, 2026

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed
Build Progress Phase 3 Swimming Lane

Third Row almost complete

Feb 27, 2016 Shaun

We did two loads of the cement mixer today, one bag of cement in total. This allowed us to do a further 39 blocks. 20 this morning and 19 this…

Dumper truck

Suspect Problem with Battery

Feb 27, 2016 Shaun

We suspect that there is a problem with the dumper truck’s battery or the charging circuit from the solar panel. We got only 3 starts out of the battery today…

Build Progress Phase 3 Swimming Lane

2nd Row Complete and 3rd started

Feb 25, 2016 Shaun

We got the 2nd row done today before lunch, having started at 9am this morning. That was 21½ blocks put down. We split one of the concrete blocks in half,…

Build Progress Phase 3 Swimming Lane

Another Half a Wall done

Feb 24, 2016 Shaun

We did only a half day of work today, as we had other commitments in the morning. On Monday, we tried mixing the mortar with 4litres and 50ml of Plasticiser…

Build Progress Equipment and Tools

Made a mortar application tool.

Feb 22, 2016 Stephen

We have made a tool to speed up applying mortar to top of the block for the next row. This is slightly complicated in that there are only narrow rims…

Build Progress Phase 3 Swimming Lane

Back Wall Has Started

Feb 22, 2016 Shaun

Date:21/02/2016 18:33 We started building the back wall of the swimming lane today! We managed to do 43 blocks with 3 mixer loads of mortar before it got dark. Each…

Build Progress Phase 3 Swimming Lane

Concrete Blocks Moved and Ready

Feb 19, 2016 Shaun

We moved all the 120 concrete blocks over to the slab, spread out along the whole length (22.5metres), ready to build up 2 layers of the back wall, and the…

Build Progress Phase 3 Swimming Lane

Removed remaining Foundation shuttering

Feb 19, 2016 Shaun

We also removed the shuttering framework that was wrapping around the foundation slab. The 89mm CLS timber, all 10 lengths of them, are now piled up on the side, ready…

Build Progress Phase 3 Swimming Lane

First Load of Blocks, Sand and Cement Arrives!

Feb 19, 2016 Shaun

Three pallets of concrete (215mm x 215mm x 440mm ) blocks, a pallet of Blue Circle cement bags and a ton of soft sand arrives today. It is our first…

Build Progress Phase 3 Swimming Lane

Contraction Slots and Re-Bars Framework Removed

Feb 18, 2016 Shaun

After two days of rest to recover from the hectic episode of getting the ready-mixed concrete in, we today, went out to cut slots in the slab to “guide” cracks…

Posts pagination

1 … 106 107 108 … 149

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

Proudly powered by WordPress | Theme: Newsup by Themeansar.

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed