Author: Shaun

  • Back Wall Has Started

    Date:21/02/2016 18:33

    We started building the back wall of the swimming lane today! We managed to
    do 43 blocks with 3 mixer loads of mortar before it got dark. Each row of
    the wall contains 50 blocks and we are doing 5 rows at this stage.

    It was quite difficult in keeping consistent with the mortar gap between the
    concrete blocks and not let it “run” ahead! We had to keep it down to 10mm
    or less because we got our steel rods going up through the hollow cores,
    meaning keeping the rods fairly clear of the edges of the blocks.

    And the other discovery we learnt, is the sloppiness of the mortar mix. Each
    concrete block are much heavier than house bricks so they press down with
    27kg of force, on their narrow edges, which means they squeezed out the
    mortar if it is too sloppy.

    We make a strong mortar mix using 1 bucket of sharp sand with 2 buckets of
    soft sand (a “Builder’s” bucket is about 13litres) which gives a total of
    40litres of sand, together with a 10litre bucket of cement (a complete 25kg
    bag fills just about 2 10litre buckets).

    Currently, we are working with 4litres of water (plus 100ml of plasticiser)
    and this produces a slightly sticky and sloppy mix which just about holds up
    the block.

    It takes a little while for our electric mixer to produce the “flop”
    consistency, and it seems that the plasticiser then starts creating
    microscopic air bubbles which makes the mix even more sloppy after another
    couple of minutes. We think we will reduce the plasticiser down to 50ml in
    our next mix.

    We will inspect our build in the morning to judge the quality of our current
    mortar mix!!

    Only 207 blocks to go!!

    First-42-Blocks-placed

    First-42-Blocks-placed

  • Concrete Blocks Moved and Ready

    We moved all the 120 concrete blocks over to the slab, spread out along the
    whole length (22.5metres), ready to build up 2 layers of the back wall, and
    the extras at the beginning, ready for the end section of the swimming lane,
    and the first few blocks on the front wall.

    We used our new purposed built trolley to move 10 blocks at a time, weighing
    in at least 250kg in total, pushing and pulling the load over the slightly
    soggy ground (we had a recent rain fall!) and rather bumpy at times too.
    Hard Work!

    First-two-rows-opf-blocks-ready-for-building

    First-two-rows-opf-blocks-ready-for-building

  • Removed remaining Foundation shuttering

    We also removed the shuttering framework that was wrapping around the
    foundation slab. The 89mm CLS timber, all 10 lengths of them, are now piled
    up on the side, ready for the next shuttering job of the main house’s
    foundations.

  • First Load of Blocks, Sand and Cement Arrives!

    Three pallets of concrete (215mm x 215mm x 440mm ) blocks, a pallet of Blue
    Circle cement bags and a ton of soft sand arrives today.

    It is our first delivery of many, many pallets of concrete blocks to come!

    It was amazing to see how far the Jewson’s delivery lorry managed to lift
    each pallet over from our Loke, over the top of the stack of OSB sheets and
    put them down actually in our “hole”! Wow!

  • Contraction Slots and Re-Bars Framework Removed

    After two days of rest to recover from the hectic episode of getting the
    ready-mixed concrete in, we today, went out to cut slots in the slab to
    “guide” cracks caused by the contraction of the drying and curing concrete.

    The basic formula is 30mm for every 1mm thickness of the slab, which in our
    case, the slab being 100mm thick, means that a series of slots is needed
    every 3metres, so we cut 8 slots in total. We used a diamond coated cutting
    disc (250mm diameter) in an angle grinder machine and cut 25mm deep slots.

    Then we dismantled the framework that was holding the reinforcing rods in
    place and put bright “lime” green domes on the ends of the sticking up steel
    rods to protect us from potential accidents of falling over and piercing our
    bodies right through, nasty or what!!

    We now have an “avenue” of green “flowers” on steel stalks!!

  • Concrete Is In!

    Our ready mixed concrete duly arrived this morning, 8am sharp! We managed to
    get our little extension chute installed on the dumper truck in time and
    park it over by the Loke.

    But when the concrete lorry arrived, he had only one extension chute himself
    and wouldn’t or couldn’t reach our dumper truck. So we had to drive the
    truck up onto the upper level, and only just managed to get their chute to
    go into our skip!!

    Anyway, it went reasonably smoothly after that, went back and forth a half
    dozen times, distributing the concrete all the way along our trench. That
    phase took 45minutes to empty his lorry load of concrete!

    It then took us a further 7 hours to push and shove the piles of wet gravel
    concrete into all the corners and in and around the re-bars, then chump it
    down, level it off, and get a fairly flat finish. We couldn’t use the float
    at the end as the mix had already set too hard by then.

    Concrete poured and compacted

    Concrete poured and compacted

    We stumbled and staggered back in doors after cleaning the dumper and
    wheelbarrow plus tools with the garden hose, washed our gloves and overalls
    of the worse of the cement. We had put on latex gloves underneath our tough
    rubber coated gloves to protect our hands from the alkaline burns. Thanks
    goodness!!

    So at last, the swimming lane, currently 22.75metres long, now has a
    foundation formed and it is now curing and hardening. All the reinforcing
    rods are sticking out of the concrete, ready for the hollow concrete blocks
    and we can then rebuild the ground up behind the soon to be new wall and
    rebuild the fence again!!

    The last 3 or 4 days has been very, very hectic getting everything ready!!
    Phew! We will have a day or two off now to recover!!

  • re-bar support framework has been constructed

    The framework for holding the reinforcing bars in the correct positions, has
    been constructed using our pile of 63mm CLS timber. We drove in pegs and
    posts to hold the framework together and get the straight lines. this was done yesterday and Friday.

    We then spent today (Sunday) mounting the re-bars themselves onto the “rails”,
    positioned at every 225mm, which is the repeat distance between the holes in
    the hollow concrete blocks.

    And we used broken pieces of 50mm concrete paving slabs to stabilised the
    steel rods in the bottom of the trench.

    we didn’t finish this job until 10pm tonight!! we had to get this done before tomorrow and the arrival of the ready mixed concrete!! Phew!

    Rebar Framing Ready

    Rebar Framing Ready

    Rebar in Place

    Rebar in Place


  • Ready mix concrete ordered

    We have ordered 4 cubic metres of ready mixed concrete for Monday 8am! The
    price has gone up since 5 years ago and now is £425 for this load!! Yes, it
    is not a full load of 6 cubic metres and therefore we must pay an ?empty?
    charge to cover the cost of the driver and equipment but still, the price is
    a shock!

  • Re-Bars cut and bent!

    Today, we started on the job of slicing up 55 6metres steel bars into 105
    lengths of 2metres, and 100 lengths of 1metre.

    Then all were bent right angles, so that it would be buried in the concrete
    slab and provide vertical reinforcing rods for the hollow blocks.

    Pile of cut and Bent Re-Bar

    Pile of cut and Bent Re-Bar

    Tomorrow, we will create the wooden framework to hold these rods in their
    correct position.

  • Foundation Trench Constructed!

    We have finished constructing the foundation trench framework.

    We put in about 8 tons of crushed builders rubble (maximum 75mm / 3inch
    size) and then blinded the surface with clean sharp sand (about 1.5tons).

    All was compacted down several times for each layer.

    This concludes the framework and now ready for the ready mixed concrete to
    be poured in.

    Base Dug out and Framed

    Base Dug out and Framed

    Hardcore placed and compacted

    Hardcore placed and compacted

    Trench blinded with sand

    Trench blinded with sand


    But first, our next job is to cut the reinforcing bars into required lengths
    and bent right angles for most of them. These are the vertical rods to be
    placed around the edge of the foundation to line up with the block walls and
    the hollows. A wooden support structure will hold the rods at the correct
    level.