Category: Phase 2

Phase 2 is the massive clearance of our site.

  • Utility Disconnect

    There are still two utility services connected to the Old Place, water and telephone. The electricity has been moved last November.

    For the water, we dug down near the meter and capped off the pipeline running off to the Old Place. The modern plastic pipes is very easy to deal with, just push on the End Cap, screw it down tight and hey presto! All sealed and done!

    Next was the telephone line, or rather installing the necessary underground conduits ready for the new cable to the garage. We needed to cut a trench across our little Loke to the telegraph pole and lay down a plastic pipe and come out at the base of the pole.

    Next is the threading of the string. But first, we discovered that there was quite a lot of water lurking in the conduit that have had been laid 18 months ago and the open end got buried! We used the workshop vacuum cleaner to suck this water out and then suck the string through, being tied to an old dishcloth. It worked very well indeed.

    Having marked the string beforehand, the distance from end to end is about 46metres!

    The engineers will be coming in a few days to connect the new phone line.

    This means the last utility connection will be cut from the Old Place and we can start dismantling it! Yippee!

  • Monster Plastic shopping Order finished!

    After all the analysis of design and everything, we come to a final list of plastic pipes, tubes and crates. It adds up to over £6500! The lion share are the AquaCell crate modules for our energy storage system. We have ordered most of what we need for phase 2 of our build and that would represent about £500 saving in the next six months and we would never get that kind of interest rate on any saving account out there!

    Phew!

    Now back to the grind and back to the garage interior work!

  • Monster Plastic Shopping Order

    We have been working on building up a shopping list of all the plastic pipework, crates and other plastic items. We were told that the prices for these will be going up by 8% on 1st March probably caused by the higher oil price. So we sat down to analyse our house design to quantify what we need in the following areas:

    . Central Vacuum system

    . Hot water

    . Cold water

    . Sewage above ground & underground

    . Rain water underground & downpipes

    . Energy storage modules and connections to and from each underground tanks

    We have done quite a bit of analysis so far but a few more days to go. We are taking a break for a change of scene and are back to working in the garage.